Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 27, Cited by 4]

Bombay High Court

Itd Cementation India Limited vs Konkan Railway Corporation Limited on 12 December, 2019

Equivalent citations: AIRONLINE 2019 BOM 2877

Author: G.S.Kulkarni

Bench: G.S. Kulkarni

 pvr                                     1/66           carap1106-1107-18.doc



                 IN THE HIGH COURT OF JUDICATURE AT BOMBAY

                      ORDINARY ORIGINAL CIVIL JURISDICTION
                          IN ITS COMMERCIAL DIVISION

                  Commercial Arbitration Petition No. 1106 OF 2018

 ITD Cementation India Ltd.                          ...Petitioner
       Versus
 Konkan Railway Corporation Ltd.                     ...Respondent

                                          AND

                  Commercial Arbitration Petition No. 1107 OF 2018

 ITD Cementation India Limited.                      ...Petitioner
       Versus
 Konkan Railway Corporation Limited.                 ...Respondent
                                  ----

 Dr.Birendra Saraf with Mr.Raj Panchmatia, Ms.Jyoti Sinha, Mr.Himanshee
 Vidhani and Mr.Varun Mansinghka i/b. Khaitan & Co., for the Petitioner.

 Ms.Kiran Bagalia              with Subhash Gutle, Mushraf Shaikh, for the
 Respondent.
                                       -----
                                 CORAM    :          G.S. KULKARNI, J.

                                 Dated          :    12 December 2019

 Judgment:


 1.       These are two applications under Sections 11(6) read with Section

 14(2) and 15(2) of the Arbitration and Conciliation Act,1996 (for short

 'the Arbitration Act') whereby the petitioner has prayed that it be declared




::: Uploaded on - 12/12/2019                        ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                      2/66           carap1106-1107-18.doc


 that the mandate of the "standing arbitral tribunal" constituted under the

 agreement between the parties stands terminated and has further prayed

 for appointment of an arbitral tribunal for adjudication of present and

 future disputes between the parties arising under the agreement between

 the parties, in accordance with the provisions of the Arbitration Act as

 amended.



 2.       The prayers in both these petitions are identical. It would be

 appropriate to note the prayers as made in one of the petitions

 (Commercial Arbitration Petition no.1106 of 2018) which reads thus:-

                  (a)    that this Hon'ble Court in exercise of its powers under
                  Section 14(2) of the Arbitration and Conciliation Act,1996 be
                  pleased to hold that the mandate of the present Standing Arbitral
                  Tribunal constituted under the Agreement, has been terminated;

                  (b)     that this Hon'ble Court in exercise of its powers under
                  Section 11(6) read with Section 15(2) of the Arbitration and
                  Conciliation Act,1996 be pleased to take necessary steps to appoint
                  an arbitral tribunal to adjudicate upon the all present and future
                  disputes between the parties under the agreement, in accordance
                  with the procedure agreed upon between the parties and the
                  provisions of the Arbitration and Conciliation Act,1996, as
                  amended;"



 3.       As the parties have advanced arguments on the above petition, it

 would be appropriate to refer to the facts in Commercial Arbitration

 Petition no.1106 of 2018.




::: Uploaded on - 12/12/2019                         ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                       3/66            carap1106-1107-18.doc




 4.       In nutshell the facts are:

          The petitioner is a company incorporated under the Companies Act,

 1956 interalia engaged in the business of construction and infrastructure.

 Respondent-Konkan Railway Corporation is a Government Company.

 Respondent had issued a tender for the work of construction of tunnels

 namely "T1 on the Katra-Dharam section of the Udhampur-Srinagar-

 Baramulla, New B.G.Rail Link Project" in the State of Jammu and Kashmir.

 The petitioner was a successful bidder and was awarded the contract for

 the said work. A contract agreement dated 24 September 2014 came to

 be executed between the petitioner and the respondent which interalia

 contained general and special conditions of contract. A clause for dispute

 resolution was provided, being Clause 55 of the Special Conditions of the

 Contract, whereunder the parties agreed for reference of the disputes to

 arbitration by forming a "standing arbitral tribunal". Clause 55 which

 provides for composition of a "standing arbitral tribunal" reads thus:-

                   55.0 Standing Arbitral Tribunal

                   55.1 The Arbitral Tribunal shall consist of a panel of three
                   Gazetteed Rly. Officers not below JA Grade, or two Railway
                   Gazetted Officers not below JA Grade and a retired Railway
                   Officer,retired not below the rank of SAG Officer as the Arbitrators.
                   The Standing Arbitral Tribunal shall be formed within three months
                   from the date of the execution of the Contract. For this purpose, the
                   Corporation will send a panel of more than 3 (Three) names of




::: Uploaded on - 12/12/2019                           ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                        4/66            carap1106-1107-18.doc

                   Gazetted Rly. Officers of one or more departments of the Railway,
                   which may also include the name (s) of Retired Railway Officers to
                   the contractor from the panel approved by Northern Railway.
                   Within two weeks from the receipt of the list, the Contractor shall
                   intimate in writing two names from the said list to the Chairman
                   and Managing Director KRCL. The Chairman and Managing
                   Director/KRCL shall appoint at least one out of them as the
                   contractor's nominee and will also simultaneously appoint the
                   balance number of arbitrators from the panel approved by Northern
                   Railways duly indicating the presiding Arbitrator from amongst the
                   3 Arbitrators so appointed. While nominating the Arbitrators, it will
                   be necessary to ensure that one out of them is from the Accounts
                   department.

                   55.5    Reference to Arbitration

                   55.5.1. In partial modification of Clause 43 of the Standard
                   General Conditions of Contract of Northern Railway,                the
                   Contractor has to prepare and furnish to the Engineer-in-charge
                   and to Chief Engineer of Project once in every six months an
                   account giving full and detailed particulars of all the claims for any
                   additional expenses, to which the contractor may consider himself
                   entitled to and all extra or additional works ordered by the
                   engineer which he has executed during the preceding six months. If
                   any dispute has arisen as regards execution of the works under the
                   contract, while submitting the said half yearly claims, the
                   contractor shall give full particulars of such dispute in the said
                   submission. After signing Contract Agreement, within six months,
                   contractor shall submit all the claims from the date of award of
                   contract in first submission of claims.

                   55.5.2       The Contractor will submit a copy of the half yearly
                   claims under 55.5.1 to the Chief Engineer, along with particulars of
                   any other disputes which may have arisen between the parties in
                   respect of the execution of the contract to the Arbitral Tribunal.

                   55.5.3 The parties shall submit all the relevant documents in
                   support of their claims and the reasons for raising the dispute to
                   the TRIBUNAL.

                   55.5.4 If the claims made by the Contractor in the said submission
                   to Chief Engineer is refuted or the payment is not made within one
                   month from the date of the submission of the said half yearly
                   claims, a dispute would be deemed to have arisen between the
                   parties. The contractor, within one month from the date when the
                   dispute arises or is deemed to have arisen, will communicate to the




::: Uploaded on - 12/12/2019                            ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                       5/66           carap1106-1107-18.doc

                   Arbitral Tribunal on a half-yearly basis of the said
                   refusal/nonpayment. The said communication will be the reference
                   of the dispute to the ARBITRAL TRIBUNAL appointed under the
                   present agreement.

                   55.5.5 The said claims of the contractor so referred to ARBITRAL
                   TRIBUNAL so far as it relates to the disputed claims, shall be
                   treated as Statement of Claims of the Contractor and the ARBITRAL
                   TRIBUNAL shall call upon KRCL to submit its reply. The ARBITRAL
                   TRIBUNAL after giving an opportunity of being heard to both
                   parties, decide the dispute within a period of two months from the
                   date of communication of the dispute under clause 55.5.3 above.
                   The Arbitral Tribunal will pass a reasoned award in writing, while
                   deciding the Dispute. Once the award is declared, the Arbitral
                   Tribunal cannot review the same except what is permissible in
                   terms of provisions contained in Arbitration and Conciliation Act,
                   1996. The parties shall be entitled to the remedies under the
                   Arbitration and Conciliation Act, 1996 or any amendment thereof.

                   56. Settlement through court

                   56.1 It is a term of this contract that the Contractor shall not
                   approach any Court of Law for settlement of such disputes or
                   differences unless an attempt has first been made by the parties to
                   settled such disputes or differences through clauses 55.0 above.

                   56.2. The contract shall be governed by the law for the time being
                   in force in the Republic of India.               In case of any
                   disputes/differences resulting in court cases/ between contractor &
                   KRCL the jurisdiction shall be of courts at Mumbai only."


 5.       In terms of the above clauses, after execution of the contract

 agreement, the respondent by its letter dated 3 February 2015 forwarded

 to the petitioner a panel of arbitrators (comprising of four names) and

 requested the petitioner to suggest two names out of the said panel one of

 whom can be appointed as the petitioner's nominee on the Standing

 arbitral tribunal. The petitioner by its letter dated 12 February 2015




::: Uploaded on - 12/12/2019                          ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                        6/66         carap1106-1107-18.doc


 informed the respondent of it s choice of two names from the said panel.



 6.       Respondent           thereafter   formed   a   standing      arbitral      tribunal,

 comprising of Mr.P.K.Aggarwal - Presiding Arbitrator, Mr.Rajkumar Sarkar

 - petitioner's nominee and Mrs.Preeti Jha- Respondent's nominee. The

 petitioner has contended that two of the appointed arbitrators were

 serving employees of the Northern Railways.



 7.       In executing the contractual work, the petitioner had addressed

 various communications to the respondent and more particularly letters

 dated 17 April 2015 and 3 June 2016 with regard to the revision in the

 applicable toll tax cost being levied pursuant to the notification dated 31

 March 2015 and 30 May 2016 issued by the Government of Jammu and

 Kashmir. Petitioner had requested the respondent to reimburse the

 petitioner, the amount of additional toll tax incurred by the petitioner.



 8.       The petitioner also by its letter dated 26 August 2016 requested the

 respondent to furnish reasons for the respondent deducting excess works

 contract tax, based on the Jammu and Kashmir General Sales Tax Act,

 1962, in lieu of the work carried out by the petitioner under the contract




::: Uploaded on - 12/12/2019                         ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                         7/66          carap1106-1107-18.doc


 agreement,         over       and   above    the   petitioner's     contractual        liability.

 Thereafter, correspondence exchanged between the parties. The petitioner

 made a grievance to the respondent that the deduction of this amount was

 severely hampering the cash flow and general progress of the work under

 the agreement and demanded release of the amounts.



 9.       Thereafter, the petitioner by its letter dated 30 August 2016

 informed the respondent about complete stoppage of all tunneling

 activities under the contract agreement since 28 August 2016 owing to a

 cavity formation at TIP2 tunnel face. It was highlighted that stoppage of

 the work was beyond the control of the petitioner. Further by its letter

 dated 3 January 2017 the petitioner appraised the respondent of the

 various steps which were taken towards resumption of tunneling activity

 consequent to formation of cavity at TIP2 tunnel phase. The petitioner

 also informed the respondent of additional cost incurred as a result of

 tunnel collapse at tunnel face at TIP2 and that only an amount of Rs.2.43

 crores was received from the respondent by the petitioner and substantial

 amounts being outstanding towards the balance un-recovered cost payable

 by the respondent. A half yearly statement of claim for the period ending

 31 December 2018 came to be submitted by the petitioner to the




::: Uploaded on - 12/12/2019                           ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                8/66          carap1106-1107-18.doc


 respondent by petitioner's letter dated 14 February 2017 with a request to

 the respondent to release pending dues owed to the petitioner.



 10.      The petitioner contends that due to repeated tunnel collapse during

 the period August 2016 to September 2016 and further tunnel collapse

 during February 2017 to October 2017 in all there being six major tunnel

 collapses, the petitioner was constrained to take urgent remedial measures

 to work on the instances and for prevention of future instances. For this

 the petitioner had incurred huge additional cost which according to the

 petitioner were in the best interest of the project. The petitioner contends

 that repeatedly the respondent was informed of the additional

 expenditure incurred and the serious financial crunch being faced by the

 petitioner and that despite these difficulties the petitioner had continued

 to work as the project was of national importance. The petitioner

 contended that the payment however was withheld by the respondent

 despite repeated requests to the respondent to release these payments.



 11.      The petitioner has contended that time for completion of the project

 was also extended which was however for reasons beyond the petitioner's

 control. Despite the same, the petitioner was unable to reduce its staff and




::: Uploaded on - 12/12/2019                  ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                9/66          carap1106-1107-18.doc


 minimise the loss in view of Clause 48.4 of Special conditions of contract

 which entitled the respondent to recover the amounts from the petitioner

 on monthly basis in case the petitioner did not deploy the minimum staff

 at site.



 12.       As there was no response from the respondent to the petitioner in

 regard to the petitioner's correspondence on release of payments and to

 clear the outstanding dues, the petitioner by its letter dated 5 July 2017

 informed the respondent that as the dues were not cleared, the dispute

 relating to non payment of the dues be referred to arbitration. In this

 letter the petitioner also made specific reference to the amendments under

 the Arbitration and Conciliation (Amendment) Act, 2015 and the decision

 of the Supreme Court on eligibility of the arbitrators as held in Voestalpine

 Schienen GmbH Vs. Delhi Metro Rail Corporation Ltd. 1, and requested the

 respondent to provide the entire list of arbitrators on the panel maintained

 by the respondent alongwith their qualifications and professional

 experience. The petitioner states that thus there was no favourable reply

 to this letter from the respondent.




 1     (2017)4 SCC 665




::: Uploaded on - 12/12/2019                  ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                              10/66          carap1106-1107-18.doc


 13.      Thereafter, the petitioner by its letter dated 13 February 2018

 submitted its statement of claim to the respondent for the period ending

 31 December 2017 with all details and supporting documents. The

 petitioner requested the respondent to clear the outstanding dues

 approximately Rs.3455.73 lacs on account of these claims. The petitioner

 has contended that the entire claims alongwith the interest thereon has

 remained unpaid, as despite the petitioner's letter dated 13 February 2018

 respondent had failed to take any steps. As no reply was received to the

 petitioner's letters dated 5 July 2017 and 13 February 2018 and the

 respondent not having taken any steps in accordance with the amended

 provisions of the Act, for appointing an arbitral tribunal to adjudicate

 upon the disputes between the parties, the petitioner has filed the present

 petition.



 14.      The petitioner has contended that the current members of the

 standing arbitral tribunal namely Mr.P.K.Aggarwal-Presiding Arbitrator,

 and Mrs.Preeti Jha-Respondent's nominee, are existing employees of

 Indian Railways (as part of the Northern Railways, a functional division of

 Indian Railways) and as such are working under the Indian Railways. As

 regards the third member Mr.Satya Pal, the petitioner has contended that




::: Uploaded on - 12/12/2019                ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                         11/66        carap1106-1107-18.doc


 he is also a former employee of Indian Railways (as a part of South

 Central Railways, functional division of Indian Railways). The petitioner

 contends that neutrality, impartiality and independence of the present

 members of the standing arbitral tribunal is likely to be compromised, in

 the event the present members of the standing arbitral tribunal arbitrate

 upon the disputes between the petitioner and respondent.



 15.      It is contended by the petitioner that the respondent is an

 undertaking of the Indian Railways and entirely under its authority,

 Supervision, and control. It is contended that an "affiliate" entity is

 defined under the Seventh Schedule of the Act as amended, to encompass

 "all companies in one group of companies including the parent company".

 The petitioner has contended that on account of current shareholding of

 51% of the Indian Railways in the share capital of the respondent, the

 Indian Railways qualifies as the parent entity of the Respondent and

 hence, is an "affiliate" of the respondent. The petitioner referring to sub-

 section (5) of Section 12 of the Act contends that the spirit of the non-

 obstante clause as incorporated by the 2015 Amendment Act is to ensure

 neutrality       in    the    arbitration    proceedings.    It    is   contended         that

 notwithstanding the fact that the source of arbitrator's appointment is




::: Uploaded on - 12/12/2019                         ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                12/66           carap1106-1107-18.doc


 deduced from the contract and has been explicitly agreed between the

 contracting parties, the appointment of an arbitrator must nonetheless

 withstand the test of impartiality and independence as the Act would

 prescribe. The petitioner also contends that Section 12(5) read with

 Seventh Schedule makes it clear that if an arbitrator falls in any one of the

 categories specified in the Seventh Schedule, such arbitrator becomes

 ineligible to act as arbitrator. Once such ineligibility is established, then he

 becomes de jure unable to perform his functions within the meaning of

 Section 14(1)(a) of the Act. It is thus contended that the mandate of

 ineligible arbitrator's appointment is liable to be terminated pursuant to

 Section 14(2) of the Act as amended. The petitioner contends that in the

 light of the respondent's continued failure and neglected to undertake

 steps to ensure appointment of arbitral tribunal in compliance with the

 provisions of the Act as amended, the prayers as made in the petition

 ought to be granted.



 16.      A reply affidavit has been filed on behalf of the respondent. The

 respondent at the outset has contended that the petitioner was earlier

 awarded construction of T6, T10, T11, T12 and T19 contractual work in

 respect of Udhampur Srinagar Baramullah Rail Link project under an




::: Uploaded on - 12/12/2019                   ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                              13/66           carap1106-1107-18.doc


 agreement dated 18 October 2010. It is contended that the said contract

 also provided for standing Arbitral Tribunal during the execution of the

 contract and for resolution of all the disputes between the parties under

 Clause 56. The said arbitration agreement also provided for panel of three

 or more gazetted railway officers not below JA grade or two railway

 Gazetted Officers not below JA grade and a retired Railway Officer, who

 retried not below the rank of SAG officer from the panel approved by the

 Northern Railway. There was also a procedure that a list of at least three

 names of the Gazetted Railway officers from the panel approved by the

 Northern Railway should be sent to the contractor and the contractor was

 required to intimate two names from the said list, out of which the

 Managing Director of the respondent shall appoint one, as contractor's

 nominee and simultaneously appoint the remaining arbitrators indicating

 the name of Presiding Arbitrator.        It is contended that the present

 agreement was signed by the petitioner without demur and following the

 procedure as contained in the said agreement, an arbitral tribunal of

 Mr.P.K.Agarwal, Mr.Satya Pal and Mr.Ajit Kumar was constituted and

 intimated to the petitioner on 25 February 2015. It is stated that one of

 the arbitrator Mr.Ajit Kumar retired and in his place the respondent

 appointed Ms.Preeti Jha and the petitioner was so informed by




::: Uploaded on - 12/12/2019                 ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                14/66          carap1106-1107-18.doc


 respondent's letter dated 8 February 2016.



 17.      The respondent has contended that after the dispute arose between

 the parties, the constituted arbitral tribunal is available. It is contended by

 the respondent that the present arbitral tribunal, after retirement of

 Mr.Ajit Kumar has been reconstituted in the year 2016 and thus after the

 amendment of the Arbitration Act and after the dispute had arisen, the

 parties have accepted the constitution of the arbitral tribunal in

 accordance with the agreed terms.



 18.      The respondent has contended that the railway is one of the largest

 employer in India, next to the Indian Army. The railway engineering is a

 special class of engineering and specially the Udhampur Srinagar

 Baramulla Rail Link is a project one of its kind in Asia. It is contended

 that from the thousands of employees of the Indian Railways, a

 proposition that a railway officer merely because he is in the employment

 of the Railways would be a biased arbitrator, is only imaginary and

 baseless. It is contended that the agreed procedure for constitution of

 arbitral tribunal does not offend the provisions of Section 12(5) of the

 Amended Act. The respondent has contended that the Northern Railway




::: Uploaded on - 12/12/2019                  ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                               15/66           carap1106-1107-18.doc


 had circulated to the petitioner vide respondent's letter dated 11 August

 2017 a panel of names consisting of serving officers of Northern Railway,

 Central Railway and other Railway Zones, Retired Officers (Finance-SAG

 and above), Retired Officers (Engineering SAG and above). The

 respondent has also contended that the list consists of members of

 Railway Board, Chief Engineers, Chief Executive Officers, FA & CAOs, the

 Director/Executive Director (Finance) etc. and that there are officers also

 from other PSUs like IRCON, the Chief Safety Officers who are

 independent officers of Aviation department. It is contended that a bare

 perusal of these lists would show very high ranking officers having

 expertise are being appointed and that none of the officers are even

 remotely involved in execution of the contract. Hence, there is no reason

 for any apprehension that the members of the panel being biased or not

 independent. It is stated that the members of the panel are not covered in

 any of the embargo created under Section 12 of the Act who would have

 any influence on the contractual work. The respondent has contended

 that the Courts have consistently held having named arbitrators from the

 same department or Government servants does not prove any bias or

 partiality. Thus the contention as urged on behalf of the petitioner that the

 arbitral tribunal as constituted, is hit by the provisions of Section 12(5) of




::: Uploaded on - 12/12/2019                  ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                16/66          carap1106-1107-18.doc


 the Act, according to the respondent, is completely misconceived.


 19.      A rejoinder affidavit has been placed on record on behalf of the

 petitioner denying the contentions as urged in the reply affidavit of the

 respondent. Referring to the decision of the Supreme Court in

 "Voestalpine Schienen GMBH Vs. Delhi Metro Rail Corporation" (supra) it

 is contended that a broad panel of arbitrators to be provided is what is

 expected from the respondent to have neutrality and impartiality of the

 arbitral process.


 20.      It is on the above pleadings, I have heard the learned Counsel for

 the parties.

 Submissions on behalf of the Petitioner.

 21.      Dr.Saraf, learned Counsel for the petitioner has made the following

 submissions:-

 (i)      The standing arbitral tribunal constituted in accordance with clause

 55 of the contract is violative of Section 12(5) of the Act as amended by

 the 2015 Amendment Act, as the tribunal is formed from a restricted list

 out of a panel comprising only of existing/retired railway employees. In

 doing so the respondent is obliged to give to the petitioner a panel of only

 three names of Gazetted Railway Officer who may include retired officers




::: Uploaded on - 12/12/2019                  ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                   17/66          carap1106-1107-18.doc


 from which the petitioner is expected to select two nominees and out of

 the two nominees so selected, the Chairman and Managing Director of the

 respondent to appoint at least one person as nominee on behalf of the

 petitioner. It is submitted that this apart the Managing Director is required

 to appoint one more person from the restricted list as a nominee on behalf

 of the respondent. It is the Managing Director himself who appoints the

 third arbitrator from the said restricted list. Thus, the standing arbitral

 tribunal formed by following the said procedure under Clause 55 raises

 justifiable doubts about independence and impartiality of the arbitral

 tribunal.



 (ii)     It is submitted that the reference of disputes to arbitration is distinct

 and different from the formation of the tribunal and it takes place every

 six months. Each dispute is a separate reference which is evident from

 reading of clause 55.5 and in particular Clause 55.5.4 which in no

 uncertain terms provides ".... ... .. The said communication will be the

 reference of the dispute to the Arbitral Tribunal appointed under the

 present agreement".           It is submitted that it is incumbent upon the

 respondent to follow the directions and guidelines as laid down by the

 Supreme Court in the case Voestalpine Schienen GMBH Vs. Delhi Metro




::: Uploaded on - 12/12/2019                     ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                     18/66          carap1106-1107-18.doc


 Rail Corporation"(supra) and cannot compel the petitioner to first refer

 the dispute to an arbitral tribunal which was constituted contrary to the

 said guidelines. It is contended that the Supreme Court in paragraphs 26

 and 27 of this decision while holding that appointment of former

 Government employees was in violation of Section 12 of the Arbitration

 Act, in paragraph 21 has clearly held that providing of a restricted list

 /panel, leads to suspicion about independence and/or impartiality of the

 arbitrators to be appointed and that such a provision should be deleted.

 The Supreme Court has also held that a wide choice from the panel should

 be offered to the contractor and two arbitrators should be given the

 freedom to choose third arbitrator from the entire panel.



 (iii)     Even the Delhi High Court in the case Afcons Infrastructure Ltd. vs

 Rail Vikas Nigam Limited2 considering the similar case, appointed an

 independent arbitrator while considering the judgment of the Supreme

 Court       in    Voestalpine      Schienen     GMBH     Vs.    Delhi       Metro       Rail

 Corporation"(supra). The contention of the respondent that Section 12

 does not have retrospective effect and that the standing arbitral tribunal as

 already formed, would continue to exist and to be valid, is erroneous. It is


 2     2017 SCC Online (Del) 8675




::: Uploaded on - 12/12/2019                       ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                 19/66          carap1106-1107-18.doc


 submitted that formation of standing arbitral tribunal does not in any

 manner exclude the application of Section 12 after the amendment to

 Section 12. It is submitted that, Section 21 of the Act clearly provides that

 arbitration proceedings in respect of a particular dispute would commence

 on the date on which a request for that dispute to be referred to

 arbitration is received by the respondent. It is submitted that in the

 present case, the dispute which is a subject matter of the present

 proceedings, has arisen after coming into force 2015 amendment. Even

 Clause 55.5.4 of the agreement expressly provides that the communication

 of the dispute shall be the reference of the dispute to the arbitral tribunal.

 Thus, it is not as if Section 12(5) of the Act is being applied to the pending

 arbitral proceedings, but the same is applied to the disputes and

 commencement of the arbitration which has arisen after 2015

 amendment. It is submitted that Section 26 of the Amendment Act (Act

 no.3 of 2016) excludes application of the amendment to arbitral

 proceedings which have commenced in accordance with the provisions of

 Section 21 of the Principal Act before commencement of the Act and those

 which commence after the 2015 Amendment Act was brought into force.



 (iv)     It is next submitted that considering all pervasive control of Indian




::: Uploaded on - 12/12/2019                   ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                20/66          carap1106-1107-18.doc


 Railways on the respondent, the standing arbitral tribunal constituted out

 of the panel of only existing/retired railway employees, is violative of

 Section 12(5) of the Act and in any case raises justifiable doubts as

 regards independence and impartiality of the tribunal.



 (v)      In supporting these submissions, a reference is being made to clause

 (2) of the General Conditions of the Contract in the present case wherein

 it is specifically mentioned that the present project has been entrusted to

 the respondent by the Railway Board, Government of India, through

 Northern Railways and in this regard a contract agreement dated 9 August

 2005 has been executed between the respondent and Northern Railways.

 It is further submitted that it is an admitted position that Indian Railways

 (through Government of India) holds 51% of the respondent's

 shareholding. The rest of the shareholding in the respondent is held by

 Government of Maharashtra, Government of Goa, Government of

 Karnataka and Government of Kerala. It is submitted that even the

 organizational structure of Ministry of Railways makes the respondent as

 one of the Central Public Sector Enterprises. The Articles of Association

 also clearly show that the Government of India controls with all force, the

 respondent including appointment of contractors of the respondent,




::: Uploaded on - 12/12/2019                  ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                           21/66            carap1106-1107-18.doc


 issuance of contractors, investing monies, borrowings /raising /securing /

 payment of monies, dividends, accounts etc. Even the auditors of the

 respondent are to be appointed with the specific approval of the

 Comptroller and Auditor General of India. It is thus submitted that the

 respondent is an undertaking of Indian Railways and entirely under their

 direction and control and therefore, affiliated entity as defined under

 Seventh Schedule of the Act.



 (vi)      It is submitted that in the case of this very respondent, the learned

 Single Judge of this Court (K.R.Shriram, J.) in Afcons Infrastructure Ltd.

 Vs. Konkan Railway Corporation3, following the decision of the Supreme

 Court       in       Voestalpine       Schienen       GMBH        Vs.    Delhi      Metro       Rail

 Corporation"(supra) has directed the respondent to prepare a broad based

 list of panel of the arbitrators. In support of this submission, learned

 Counsel for the petitioner has principally relied on the the decision of the

 Supreme Court in Voestalpine Schienen GmBH Vs. Delhi Metro Rail

 Corporation (supra), the decision of the learned Single Judge of the Delhi

 High Court in Afcons Infrastructure Ltd. Vs. Rail Vikas Nigam Ltd.4,



 3     Commercial Appeal No.135 of 2017 decided on 23.10.2018
 4     2017 SCC OnLine Del 8675




::: Uploaded on - 12/12/2019                               ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                  22/66          carap1106-1107-18.doc


 Bernard Ingenieure ZT - GMBH Vs. Ircon International Ltd. 5, and the

 decision in NCCL-Premco(JV) Vs. Rail Vikas Nigam Ltd.6


 Submissions on behalf of the Respondent.

 22.       On the other hand, Ms.Kiran Bagalia, learned Counsel for the

 respondent reiterating the contentions as urged by the respondent in the

 reply affidavit would refer to the previous contract between the parties

 dated 18 October 2010 to submit that the arbitral tribunal was constituted

 under the earlier contract shall remain in force during the entire period of

 principal contract as per clause 55.6.5.



 23.       It is submitted that under the provisions of the Special Conditions of

 the contract, the parties having agreed for establishment of standing

 arbitral tribunal in the manner provided under clause 55 of the Special

 Conditions of the Contract, which was formed after following the

 procedure and which now cannot be disturbed. It is submitted that the

 amended Section 12 shall not apply in a case where the arbitral tribunal

 has already been appointed before 23 October 2015. It is submitted that

 the arguments of the petitioner are against the proviso to sub-section (5)

 5 2018 SCC OnLine Del 7941
 6     2018 SCC OnLine Del 11926




::: Uploaded on - 12/12/2019                    ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                 23/66            carap1106-1107-18.doc


 of Section 12 of the Act.



 24.      It is submitted that it is not open for the petitioner to take a stand

 that each of six monthly claim as provided in the contract, a fresh consent

 of the parties, is necessary. It is submitted that the standing arbitral

 tribunal constituted in March 2011 (under an earlier contract) has been

 continued. The petitioner had also earlier submitted its claim before the

 standing arbitral tribunal. It is submitted that the standing arbitral

 tribunal has to continue till the end of the contract and till a no claim

 certificate is issued. It is submitted that during the execution of the

 contract, the tribunal was already appointed and the disputes have been

 referred to arbitration and hence, the amended provision does not apply

 to constitution of arbitral tribunal.       It is submitted that the procedure

 provided under the contract is similar to the procedure considered in

 Voestalpine Schienen GMBH Vs. Delhi Metro Rail Corporation" (supra) by

 the Supreme Court.



 25.      It is submitted that the arbitral tribunal was established on 3 March

 2011 qua the earlier contract and the petitioner had participated in

 constitution of the arbitral tribunal by selecting two names from the list of




::: Uploaded on - 12/12/2019                     ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                24/66          carap1106-1107-18.doc


 the arbitrators forwarded by the respondent, is by communication dated

 21 February 2011 and at no point of time the petitioner ever raised a

 challenge to the arbitral tribunal on the ground that there were

 circumstances giving rise to justifiable doubts as to the arbitrator's

 independence and impartiality. It is submitted that none of the amended

 provisions of the Act are applicable to the facts of the present case.



 26.      It is next submitted that the provisions of the Seventh Schedule are

 not applicable inasmuch as the Indian Railways' Employee/ Railway

 officer is a qualification provided in the arbitration agreement executed

 between the parties and it is unthinkable that each of these large number

 of railway employees would be ineligible under the Seventh Schedule as

 he is a railway officer, though such a person never had dealing even

 remotely related to the subject contract. The decision of the Supreme in

 Voestalpine Schienen GMBH Vs. Delhi Metro Rail Corporation" (supra) in

 fact supports the case of the respondent.



 27.      In support of her submission, learned Counsel for the respondent

 relies on the decision of the Supreme Court in Aravali Power Company




::: Uploaded on - 12/12/2019                  ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                           25/66              carap1106-1107-18.doc


 Pvt. Ltd. vs M/S. Era Infra Engineering Ltd. 7; HRD Corporation (Mercus

 Oil & Chemical Division) Vs. GAIL (India) Ltd. 8 (supra), S.P.Singla

 Constructions Pvt.Ltd. Vs. State of Himachal Pradesh & Anr. 9 , Union of

 India Vs. M.P. Gupta10, BTP Structural (I) Pvt.Ltd. Belgaum Vs. Bharat

 Petroleum Corporation Ltd.11



 Discussion and Conclusion

 28.               The short issue which falls for consideration in this petition is

 whether the standing arbitral tribunal being constituted by the respondent

 as per Clause 55 of the Special Conditions of the Contract would satisfy

 the requirement of law as prescribed under Section 12 read with the

 Schedules to the Arbitration Act as incorporated by the 2015 Amendment

 Act.



 29.       Section 12 as amended by the 2015 Amendment Act provides for

 number of requirements with an object that the arbitral tribunal which

 would be constituted is independent and impartial and further that the

 members of the arbitral tribunal do not have any direct or indirect, past or

 7     (2017) 15 SCC 32
 8     Civil Appeal no.11126 of 2017. Date:31/8/2017
 9     Civil Appeal no.11824-11825 of 2018. Date 4/12/2018
 10    (2004)10 SCC 504
 11    2014(4) Mh.LJ 598




::: Uploaded on - 12/12/2019                                 ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                       26/66             carap1106-1107-18.doc


 present relationship or interest with any of the parties. Section 12 thus

 provides for grounds of challenge to the appointment of                            an arbitral

 tribunal. Proviso to Sub-section 5 of Section 12 stipulates that

 notwithstanding any prior agreement to the contrary, any person whose

 relationship, with the parties or counsel or the subject matter of the

 dispute, falls under any of the categories as specified in the Seventh

 Schedule (which provides for arbitrator's relation with the parties or

 counsel) shall be ineligible to be appointed as an arbitrator. The proviso

 to sub-section (5), however, carves out an exception to stipulate that the

 parties may subsequent to disputes having arisen between them, waive the

 applicability of this sub-section by an express agreement in writing. The

 fulcrum of the contentions of the parties being based on Section 12, this

 provision is required to be extracted, which reads thus:-

                  12. Grounds for challenge.--[(1) When a person is approached in
                  connection with his possible appointment as an arbitrator, he shall
                  disclose in writing any circumstances,-
                  (a) such as the existence either direct or indirect, or any past or
                  present relationship with or interest in any of the parties or in
                  relation to the subject-matter in dispute, whether financial,
                  business, professional or other kind, which is likely to give rise to
                  justifiable doubts as to his independence or impartiality; and

                  (b) which are likely to affect his ability to devote sufficient time to
                  the arbitration and in particular his ability to complete the entire
                  arbitration within a period of twelve months.

                  Explanation 1.--The grounds stated in the Fifth Schedule shall
                  guide in determining whether circumstances exist which give rise
                  to justifiable doubts as to the independence or impartiality of an




::: Uploaded on - 12/12/2019                            ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                       27/66             carap1106-1107-18.doc

                  arbitrator.

                  Explanation 2.--The disclosure shall be made by such person in
                  the form specified in the Sixth Schedule.]

                  (2) An arbitrator, from the time of his appointment and throughout
                  the arbitral proceedings, shall, without delay, disclose to the parties
                  in writing any circumstances referred to in sub-section (1) unless
                  they have already been informed of them by him.

                  (3) An arbitrator may be challenged only if--

                  (a) circumstances exist that give rise to justifiable doubts as to his
                  independence or impartiality, or

                  (b) he does not possess the qualifications agreed to by the parties.

                  (4) A party may challenge an arbitrator appointed by him, or in
                  whose appointment he has participated, only for reasons of which
                  he becomes aware after the appointment has been made.

                  [(5)Notwithstanding any prior agreement to the contrary, any
                  person whose relationship, with the parties or counsel or the
                  subject-matter of the dispute, falls under any of the categories
                  specified in the Seventh Schedule shall be ineligible to be
                  appointed as an arbitrator:

                  Provided that parties may, subsequent to disputes having arisen
                  between them, waive the applicability of this sub-section by an
                  express agreement in writing.]"




 30.      The fifth schedule to the Act deals with the grounds which gives rise

 to justifiable doubts as to the independence and impartiality of the

 arbitrator. The seventh schedule deals with the arbitrators relationship

 with the parties or counsel. The relevant extracts of the fifth and seventh

 schedules read thus:




::: Uploaded on - 12/12/2019                            ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                       28/66            carap1106-1107-18.doc

                                        THE FIFTH SCHEDULE
                                        (See Section 12(1)(b))

                  The following grounds give rise to justifiable doubts as to the
                  independence or impartiality of arbitrators:

                   ARBITRATOR'S RELATIONSHIP WITH THE PARTIES OR COUNSEL

                  1.     The arbitrator is an employee, consultant, advisor or has
                  any other past or present business relationship with a party.

                  ... ... ... ... ..
                  5.       The arbitrator is a manager, director or part of the
                  management, or has a similar controlling influence, in an affiliate
                  of one of the parties if the affiliate is directly involved in the
                  matters in dispute in the arbitration.
                  .. .. ...
                  12.      The arbitrator is a manager, director or part of the
                  management, or has a similar controlling influence in one of the
                  parties.

                  13.     The arbitrator has a significant financial interest in one of
                  the parties or the outcome of the case.
                  .. ... ... ..

                     PREVIOUS SERVICES FOR ONE OF THE PARTIES OR OTHER
                                       INVOLVEMENT IN THE CASE
                  ... .. .. ..
                  22.       The arbitrator has within the past three years been
                  appointed as arbitrator on two or more occasions by one of the
                  parties or an affiliate of one of the parties.
                  ... .. .. ..

                        RELATIONSHIP BETWEEN ARBITRATOR AND PARTY AND
                              OTHERS INVOLVED IN THE ARBITRATION

                  .. .. ..
                  31.       The arbitrator had been associated within the past three
                  years with a party or an affiliate of one of the parties in a
                  professional capacity, such as a former employee or partner.
                  ........
                                        OTHER CIRCUMSTANCES
                  ... .. .. .. .. .....
                  34.       The arbitrator is a manager, director or part of the
                  management, or has a similar controlling influence, in an affiliate
                  of one of the parties, where the affiliate is not directly involved in




::: Uploaded on - 12/12/2019                           ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                        29/66              carap1106-1107-18.doc

                  the matters in dispute in the arbitration.

                  Explanation 1- .. .. . .
                  Explanation 2- The term "affiliate" encompasses all companies in
                  one group of companies including the parent company."
                                               ...

                                 "THE SEVENTH SCHEDULE
                                     (See section 12(5))
                  ARBITRATORS RELATIONSHIP WITH THE PARTIES OR COUNSEL

                  1. The arbitrator is an employee, consultant, advisor or has any
                  other past or present business relationship with a party.

                  .. .. ...

                  5. The arbitrator is a manager, director or part of the management,
                  or has a similar controlling influence, in an affiliate of one of the
                  parties if the affiliate is directly involved in the matters in dispute
                  in the arbitration.

                  ... .. .. ..

                  14. The arbitrator regularly advises the appointing party or an
                  affiliate of the appointing party, and the arbitrator or his or her firm
                  derives a significant financial income therefrom.

                  15.... .. .. .

                  16... ... . .

                  17.. .. .. .

                  18. .. .. ..

                  19. ... ...

                  Explanation 1 .. .. .

                  Explanation 2 - The term "affiliate" encompasses all companies in
                  one group of companies including the parent company.

                  Explanation 3 - For the removal of doubts, it is clarified that it may
                  be the practice in certain specific kinds of arbitration, such as
                  maritime or commodities arbitration, to draw arbitrators from a
                  small, specialised pool. If in such fields it is the custom and practice




::: Uploaded on - 12/12/2019                            ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                       30/66            carap1106-1107-18.doc

                  for parties frequently, to appoint the same arbitrator in different
                  cases, this is a relevant fact to be take into account while applying
                  the rules set out above."




 31.               It can be thus clearly seen from the aforesaid provisions of the

 Arbitration Act that an arbitrator ought not to have either direct or

 indirect or any past or present relationship or interest with any of the

 parties which is likely to give rise to justifiable doubts as to his

 independence or impartiality. The provisions of the Fifth Schedule amplify

 this position in interalia providing that an arbitrator cannot be an

 employee of a party to the arbitral proceedings. In other words the

 arbitrator's employment cannot have any relation or bearing on the

 arbitrator discharging his duties as an adjudicator. The arbitrator ought

 not to be in the controlling influence of a party by virtue of being an

 employee of an organization.



 32.               On behalf of the petitioner the "Organizational Structure" of

 the respondent is also placed on record, pointing out the control of the

 Ministry of Railways on the respondent. The organizational structure is as

 under:-




::: Uploaded on - 12/12/2019                           ::: Downloaded on - 14/12/2019 13:59:16 :::
    pvr                                               31/66                 carap1106-1107-18.doc


                                     ORGANIZATION STRUCTURE

                                        MINISTER OF RAILWAYS

          MINISTER OF STATE OF RAILWAYS(S)                    MINISTER OF STATE OF RAILWAYS (G)

                                                   RAILWAY BOARD

                                                     CHAIRMAN
                                                   RAILWAY BOARD
                    MEMBER             MEMBER                MEMBER            MEMBER                 FINANCIAL
MEMBER
                     STAFF           ENGINEERING            TRACTION           ROLLING               COMMISSIONE
TRAFFIC
                                                                                STOCK                     R


DIRECTOR GENERAL/                                                               SECRETARY               DIRECTOR GENERAL/S&T
                                     DIRECTOR GENERAL/RHS
       RPF                                                                    ESTT.   ADMN.             DIRECTOR GENERAL/RS
                                   DIRECTOR GENERAL/
                                                                             MATTERS MATTERS



   ZONAL RAILWAYS (OPEN LINE)            PRODUCTION UNITS                       OTHER UNITS               CPSE/CORP
   GENERAL MANAGERS                         GENERAL MANAGERS                    GENERAL MANAGERS                BCL
                                                                                                               BSCL
        CENTRAL                         CHITTARANJAN LOCOMOTIVE             CENTRAL ORGANIZATION FOR           BWEL
        EASTERN                                    WORKS                     RAILWAY ELECTRIFICATION         CONCOR
     EAST CENTRAL                       DIESEL LOCOMOTIVE WORKS,            NF RAILWAY (CONSTRUCTION)         DFCCIL
      EAST COAST                                 VARANASI                                                     IRCON
        METRO**                          INTEGRAL COACH FACTORY,                     CAO (R)*                 IRCTC
       NORTHERN                                   CHENNAI                    CENTRAL ORGANIZATION FOR          IRFC
    NORTH CENTRAL                          RAIL COACH FACTORY,                   MODERNIZATION OF             KMRCL
    NORTH EASTERN                               KAPURTHALA                     WORKSHOP (COFMOW)               KRCL
  NORTHEAST FRONTIER                       RAIL WHEEL FACTORY,                    INDIAN RAILWAY               MRVC
    NORTH WESTERN                               YELAHANKA                   ORGANIZATION FOR ALTERNATE         RCIL
       SOUTHERN                         MODERN COACH FACTORY, RAE                  FUELS (ROAF)                RITES
    SOUTH CENTRAL                                  BARELI                                                      RVNL
    SOUTH EASTERN                                                                DIRECTOR GENERAL
      SOUTH EAST                                   CAO(R)*                  NATIONAL ACADEMY OF INDIAN Autonomous Bodies/
        CENTRAL                          DIESEL LOCO MODERNIZATION              RAILWAYS, VADODARA         Authorities
    SOUTH WESTERN                               WORKS/PATIALA
        WESTERN                                                                 DG & EX-OFFICIO GM             CRIS
     WEST CENTRAL                          RAIL WHEEL PLANT, BELA                RDSO, LUCKNOW                 RLDA




   "METRO RLY, KOLKATA          'CHIEF ADMINISTRATIVE OFFICER (RAILWAYS)

   2                                                   INDIAN RAILWAYS ANNUAL REPORT AND ACCOUNTS 2016-17




   33.      The petitioner has also placed on record the Indian Railways Annual

   Reports and Accounts 2016-2017, which would indicate that the




  ::: Uploaded on - 12/12/2019                                       ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                              32/66          carap1106-1107-18.doc


 respondent is directly under the control of the Ministry of Railways and

 apart from its Zonal railways, the Central public sector enterprises like

 respondent also forms part of the organizational structure under the

 Ministry of Railways. Hence, it can certainly be said that various zonal

 railways like Central Railways, Eastern Railways, Northern Railways etc.

 are having not only business relationship but also controlling influence on

 the respondent. From the General Conditions of the contract it is seen

 that the project in question has been entrusted to the respondent by the

 Railway Board of Government of India through Northern Railways and in

 this regard a contract dated 9 August 2005 is executed between the

 respondent and Northern railways. Even the Articles of Association would

 go to show that the Government of India controls by all force the

 respondent, including appointment of the contractors by the respondent.

 It also cannot be overlooked that the shareholding of the Indian Railways

 in the share capital of the respondent is 51%. The Indian Railways

 therefore, qualifies as a parent entity of the respondent. Thus, certainly

 the respondent can be said to be "an affiliate" of the Indian

 Railways/Northern Railways within the meaning of "an affiliate" as

 described in "Explanation 2" to the Seventh Schedule to the Arbitration

 Act. It thus cannot be said that the existing employee of the northern




::: Uploaded on - 12/12/2019                ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                33/66         carap1106-1107-18.doc


 railways would not have any relationship with the respondent. It is also

 likely that the officers can very well be posted by the Ministry of Railways

 on deputation with the respondent in which case such employees under

 the Ministry of Railways would also be             the employees with the

 respondent. Hence, it can be said that an employee of the railways can

 also be an employee of the northern railways, central railway or any other

 railways who can be appointed as an arbitrator in connection with the

 dispute to which the respondent is a party. In this situation it cannot be

 said that such an employee/arbitrator would be an independent or an

 impartial arbitrator having no relationship with the respondent, and more

 particularly in the spirit of the amended provisions of Section 12 read

 with Fifth and Seventh schedule as noted above.


 34.      There is another facet which would have relevance, namely that the

 dispute between the parties can arise at any stage of the contract. It need

 not be that only when the work under the contract is concluded a

 reference to arbitration can be made. This is also clear from the facts of

 the present case that the dispute has arisen in an ongoing contract, when

 certain bills were raised by the petitioner and which are being disputed by

 the respondent. Thus once the dispute arises and the arbitration is




::: Uploaded on - 12/12/2019                 ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                    34/66           carap1106-1107-18.doc


 required to be commenced, Section 21 of the Arbitration Act would get

 attracted which provides for commencement of arbitral proceedings.

 Section 21 provides that unless otherwise agreed between the parties, the

 arbiral proceedings in respect of a particular dispute would commence on

 the date on which the request of that dispute being referred to the

 arbitrator, is received by the respondent. Section 21 reads thus:-

                  "21.    Commencement of arbitral proceedings:- Unless otherwise
                  agreed by the parties, the arbitral proceedings in respect of a
                  particular dispute commence on the date on which a request for
                  that dispute to be referred to arbitration is received by the
                  respondent."



 35.      Once a request has been made by a party for reference of the

 disputes to an an arbitral tribunal, normally only in that event the

 respondent to whom such a request is made, would be required to accept

 the request and appoint an arbitral tribunal. In case the request is rejected

 then the party is entitled to approach the Court under Section 11 of the

 Act praying for appointment of arbitral tribunal. Once the parties are

 before the Court for appointment of an arbitral tribunal, then certainly all

 the parameters falling under Section 12 read with Fifth and Seventh

 Schedule would become applicable.




::: Uploaded on - 12/12/2019                       ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                35/66          carap1106-1107-18.doc


 36.      In the present case considering the arbitration clause, the position

 in regard to the commencement of the arbitral proceedings is not different

 from what Section 21 provides. Clause 55 of the Contract which provides

 for constitution of "a standing arbitral tribunal" cannot be taken to be any

 agreement otherwise entered between the parties to be taken as an

 exception to deviate from the commencement of the arbitral proceedings,

 as stipulated by Section 21, namely from the date on which the reqeust for

 a dispute to be referred to arbitration, is made. This more particularly

 considering the very next clause in the agreement namely Clause 55.5

 providing for a reference to arbitration and the manner in which a

 reference would be made. On reading of Clause 55.5 it can be concluded

 that constitution of a Standing Arbitral Tribunal and reference of the

 disputes are independent from each other. Hence, mere constitution of an

 arbitral tribunal cannot be presumed to be any commencement of arbitral

 proceedings, even within the meaning of Section 21 of the Arbitration Act.

 Thus, necessarily the arbitraiton proceedings in the present case would

 commence when the petitioner by its letter dated 5 July 2017 addressed to

 the respondent, calling upon the respondent to constitute an arbitral

 tribunal as per law. Thus, the requirement of law, on the day such a

 request was made for the constitution of the arbitral tribunal, would be




::: Uploaded on - 12/12/2019                  ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                36/66          carap1106-1107-18.doc


 relevant, namely the applicability of Section 12 as amended by the 2015

 Amendment Act alongwith the applicability of the provisions of Schedule

 V and Schedule VII.


 37.      In the context of Clause 55.1 of the agreement between the parties,

 the concept of a "standing arbitral tribunal" and of a nature as agreed, in

 my opinion, cannot have any implicit recognition under the provisions of

 the Act and more particularly when the arbitral tribunal comprises of in-

 service railway Gazetted Officers to be appointed by the Chairman and

 Managing Director of the respondent. It is also quite peculiar that the

 choice of the railway officers in-service or retired is also supplied by the

 respondent to the contractor (petitioner) who would be compulsorily

 required to make a selection of its nominees, only from the names as

 provided by the respondent. Thus, the choice of persons as offered is also

 completely under the control of the respondent, and the contractor is

 being foisted upon such names, from which he is required to select two

 names out of which one would be appointed by the Managing Director of

 the respondent as the contractor's nominee on the arbitral tribunal. In my

 opinion, the arbitration clause certainly finds foul of the requirement of

 Section 12 read with the noted provisions of the Fifth and Seventh




::: Uploaded on - 12/12/2019                  ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                               37/66          carap1106-1107-18.doc


 Schedule of the Act.          Having come to the above conclusion on

 consideration of the provisions of the Arbitration Act, this conclusion in

 my opinion is also supported by the decisions which I refer below.


 38.       In Voestalpine Schienen GMBH (supra) the issue which fell for

 consideration of the Supreme Court was whether the arbitral tribunal in

 the said case as constituted by the respondent-Metro Rail Corporation

 Ltd., was in violation of the provisions of Section 12 of the Act, as it was

 contended on behalf of the petitioner that the arbitral panel being

 constituted of serving and retired engineers of the Government

 Department and from the public sector undertakings, defied the neutrality

 aspect as they had direct or indirect access or privity to the respondent. In

 the said case Clause 9.2(A) of the Special Conditions of the Contract

 interalia stipulated that the respondent therein shall forward names of five

 persons from the panel maintained by the respondent and the petitioner

 will have to chose his nominee arbitrator from the said panel which was

 quite similar as in the present case. The respondent therein, in fact had

 furnished names of five persons to the petitioner with a request to

 nominate its arbitrator from the said panel.          However, this was not

 acceptable to the petitioner who contended that the panel prepared by the




::: Uploaded on - 12/12/2019                 ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                    38/66           carap1106-1107-18.doc


 respondent consisting of serving or retired engineers either of the

 respondent or of the Government Department or public sector

 undertakings would not qualify as independent arbitrators. It was the

 petitioner's contention that such constitution would lose its validity as it

 would be contrary to the provisions of Section 12. However, in the facts of

 the case as noted by the Court in paragraph 27 of the report, as the

 respondent had thereafter forwarded a list of about 31 persons and had

 given a free and wide choice to the petitioner to nominate its arbitrator

 and such panel consisted of the persons who were not employees or ex-

 employees or in any way related to the respondent, and that as the

 persons who were to be ultimately picked up as arbitrators would have to

 disclose their interest in terms of the provisions of Section 12 of the Act,

 the Supreme Court did not find it to be a fit case to exercise jurisdiction

 and appoint an arbitral tribunal. However, what is relevant in the context

 of the present case are the observations of the Supreme Court                              in

 paragraphs 28, 29 and 30 whereby the Court criticised such a procedure

 as provided for in the contract in Clause 9.2 and the adverse consequence

 as entailed by such a clause. The Supreme Court in paragraphs 28,29 and

 30 observed thus:

                  "28. Before we part with, we deem it necessary to make certain
                  comments on the       procedure contained in the arbitration




::: Uploaded on - 12/12/2019                       ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                       39/66             carap1106-1107-18.doc

                  agreement for constituting the arbitral tribunal. Even when there
                  are number of persons empaneled, discretion is with the DMRC to
                  pick five persons therefrom and forward their names to the other
                  side which is to select one of these five persons as its nominee
                  (Though in this case, it is now done away with). Not only this, the
                  DMRC is also to nominate its arbitrator from the said list. Above
                  all, the two arbitrators have also limited choice of picking upon the
                  third arbitrator from the very same list, i.e., from remaining three
                  persons. This procedure has two adverse consequences. In the first
                  place, the choice given to the opposite party is limited as it has to
                  choose one out of the five names that are forwarded by the other
                  side. There is no free choice to nominate a person out of the entire
                  panel prepared by the DMRC. Secondly, with the discretion given to
                  the DMRC to choose five persons, a room for suspicion is created in
                  the mind of the other side that the DMRC may have picked up its
                  own favourites. Such a situation has to be countenanced. We are,
                  therefore, of the opinion that Sub-clauses (b) & (c) of Clause 9.2 of
                  SCC need to be deleted and instead choice should be given to the
                  parties to nominate any person from the entire panel of arbitrators.
                  Likewise, the two arbitrators nominated by the parties should be
                  given full freedom to choose third arbitrator from the whole panel.
                  29.      Some comments are also needed on the Clause 9.2(a) of
                  the GCC/SCC, as per which the DMRC prepares the panel of
                  'serving or retired engineers of government departments or public
                  sector undertakings'. It is not understood as to why the panel has
                  to be limited to the aforesaid category of persons. Keeping in view
                  the spirit of the amended provision and in order to instill
                  confidence in the mind of the other party, it is imperative that
                  panel should be broad based. Apart from serving or retired
                  engineers of government departments and                  public sector
                  undertakings, engineers of prominence and high repute from
                  private sector should also be included. Likewise panel should
                  comprise of persons with legal background like judges and lawyers
                  of repute as it is not necessary that all disputes that arise, would be
                  of technical nature. There can be disputes involving purely or
                  substantially legal issues, that too, complicated in nature. Likewise,
                  some disputes may have the dimension of accountancy etc.
                  Therefore, it would also be appropriate to include persons from this
                  field as well.
                  30.     Time has come to send positive signals to the international
                  business community, in order to create healthy arbitration
                  environment and conducive arbitration culture in this country.
                  Further, as highlighted by the Law Commission also in its report,
                  duty becomes more onerous in Government contracts, where one of
                  the parties to dispute is the Government or          public sector




::: Uploaded on - 12/12/2019                            ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                       40/66           carap1106-1107-18.doc

                  undertaking itself and the authority to appoint the arbitrator rests
                  with it. In the instant case also, though choice is given by DMRC to
                  the opposite party but it is limited to choose an arbitrator from the
                  panel prepared by the DMRC. It, therefore, becomes imperative to
                  have a much broad based panel, so that                   there is no
                  misapprehension that principle of impartiality and independence
                  would be discarded at any stage of the proceedings, specially at
                  the stage of constitution of the arbitral tribunal. We, therefore,
                  direct that DMRC shall prepare a broad based panel on the
                  aforesaid lines, within a period of two months from today."



 39.        In Afcons Infrastructure Ltd. Vs Ircon International Ltd. 12, the

 learned Single Judge of the Delhi High Court has taken a similar view also

 referring to the decision of the Supreme Court in Voestalpine Schienen

 GMBH (supra). The arbitration clause in the said case was similar as in

 the present case. The learned Single Judge held the arbitration clause to

 be invalid in view of the provisions of Section 12 of the Act and directed

 the respondent to prepare broad based panel. The learned Single Judge

 made the following observations in paragraphs 21, 22, and 23:-

        21. With reference to a similar clause, the Supreme Court in Voestalpine
        Schienen GMBH(supra) has directed that the panel has to be broadbased.
        The rationale given by the Supreme Court is that if a restricted panel is
        proposed, then the choice given to the opposite party is very limited,
        resulting in there being no free choice to nominate a person and it also gives
        room for suspicion in the mind of the other side. Such a situation has been
        countenanced by the Supreme Court. Accordingly, the Supreme Court
        directed that apart from serving or retired Engineers of Government
        Departments and Public Sector Undertakings, Engineers of prominence and
        high repute from private sector should also be included. It directed that a
        panel should comprise of persons with legal background like Judges and
        Lawyers of repute as it is not necessary that all disputes that arise, would be
        of technical nature. There could be disputes involving purely or substantially
        legal issues, that too, complicated in nature and some disputes may have the

 12 2017 SCC OnLine Del 10049




::: Uploaded on - 12/12/2019                          ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                      41/66           carap1106-1107-18.doc

        dimension of accountancy etc. It is, in these circumstances, that the
        Supreme Court directed the respondent in the said case to broadbase the
        panel and to be restricted not only to retired Engineers or Officers. Another
        reason given by the Supreme Court is that in case there is a broadbased
        panel, then there would be no misapprehension that impartiality or
        independence would be discarded at any stage of the proceedings. In those
        circumstances, the Supreme Court directed Delhi Metro Rail Corporation to
        prepare a broadbased panel on the principles, as laid down therein.
        22.      Similarly, in the present case, it would be expedient to direct the
        respondent to boradbase their panel on the same lines as directed by the
        Supreme Court in Voestalpine Schienen GMBH (supra) as expeditiously as
        possible preferably within a period of three weeks from today.
        23.     The direction to expedite the process of preparing a broadbased
        panel has been issued so that the two Arbitrators, who have been
        nominated, would have broadbased panel to choose the third Arbitrator
        from.


 40.      Again in Bernard Ingenieure ZT - GMBH Vs. Ircon International Ltd.

 (supra) considering a similar arbitration agreement and as the broad base

 panel was not prepared by the respondent, the learned Single Judge of the

 Delhi High Court made the following observations:-

        11.       The above judgment was passed by the Supreme Court as far back,
        as 10 February, 2017. More than a year has passed, however, even now the
              th

        so-called broad based panel of the respondent still does not contain names
        of Engineers of prominence and high repute from private sector, persons
        with legal background like judges and lawyers of repute, people having
        knowledge and expertise in accountancy etc. The panel of Arbitrators now
        framed by the respondent is, therefore, in my opinion, still not in conformity
        with the judgment of the Supreme Court in Voestalpune Schienen GMBH
        (supra) and, therefore, in my opinion, the respondent has failed to act in
        accordance with the procedure prescribed under the arbitration agreement
        between the parties. It is again emphasised that even the Supreme Court in
        the above judgment had suggested, if not directed, that a clause in the
        arbitration agreement restricting the right of the contracting party to
        appoint/nominate his own Arbitrator should be deleted.


 41.      In NCCL-Premco(JV) Vs. Rail Vikas Nigam Ltd. (supra), a similar




::: Uploaded on - 12/12/2019                         ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                       42/66           carap1106-1107-18.doc


 view was taken by the learned Single Judge of the Delhi High Court

 referring to the decision in the Supreme Court in Voestalpine Schienen

 GmbH Vs. Delhi Metro Rail Corporation Ltd. (supra). The Court in

 paragraphs 10 to 14 has observed thus:-

                  10. I have considered the submissions made by the counsels for the
                  parties. As noted above, this Court in Larsen & Arb. P. No.627/2018
                  Page 5 Toubro Ltd. (supra) in similarly situated facts had held that
                  mere forwarding of a list of five persons (in that case) would be a
                  failure of the respondent to discharge its obligations that have been
                  cast upon it under the Arbitration Agreement read with Section 12
                  of the Amended Act as also the Judgment of the Supreme Court in
                  Voestalpine Schienen(supra).
                  11. As in spite of the judgment of the Supreme Court in Voestalpine
                  Schienen(supra) and of this Court in Larsen & Toubro Ltd. (supra),
                  the respondent insisted on giving only a limited number of names
                  from its panel of Arbitrators to the petitioner for choosing its
                  nominee Arbitrator, the same clearly amounts to a failure on part of
                  the respondent to act in accordance with the Arbitration Agreement
                  read with Section 12 of the Amended Act.
                  12. Even the panel of Arbitrators that has been framed by the
                  respondent and has been offered by it to the petitioner alongwith
                  its reply to the present petition, in my opinion, does not conform to
                  the Judgment of the Supreme Court in Voestalpine Schienen(supra)
                  inasmuch as it still does not include Engineers of prominence and
                  high repute from private sector, persons with legal background like
                  Judges and lawyers of repute or people having knowledge in
                  accountancy, i.e. Chartered Accountant, etc. The panel is still
                  predominantly of former employees with the Railways and Public
                  Sector Companies connected thereto.
                  13. Be that as it may, as the respondent had failed to Arb. P.
                  No.627/2018 Page 6 discharge its obligations in terms of the
                  Arbitration Agreement read with Section 12 of the Act, the
                  appointment of the nominee Arbitrator of the petitioner is
                  confirmed.
                  14. I appoint Mr.B.K.Makhija, Former Director-Projects, RITES as
                  the nominee Arbitrator for the respondent."




::: Uploaded on - 12/12/2019                          ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                      43/66            carap1106-1107-18.doc


 42.      Apart from the above decisions, of the Delhi High Court, a learned

 Single Judge of this Court (K.R.Shriram, J.) in " Afcons Infrastructure Ltd.

 Vs. Konkan Railway Corporation " (supra) in the case of the present

 respondent in a similar situation, considering an identical agreement, as

 entered by the respondent with the applicant-Afcons Infrastructure Ltd.,

 has come to a clear conclusion that the respondent KRCL would fall under

 the common control of the Indian Railways as per the organizational

 structure. It was also held that considering the law laid down by the

 Supreme Court in Voestalpine (supra) it was incumbent for the respondent

 to prepare a broad based panel. The learned Single Judge has made the

 following observations in paragraphs 20,22,24,25, 26 and 27:-

                  20.     Therefore, even if the panel of 31 names recommended by
                  respondent does not contain anyone who are employees of KRCL
                  or ex-employees of KRCL (respondent) still all of them would fall
                  under the common control of the Railway Board-Indian Railways,
                  as per the organization structure given above.
                  22.     Voestalpine (supra) was delivered by the Apex Court way
                  back on 10.2.2017. More than 20 months have passed since then. I
                  can understand the contract was entered into before this decision
                  in Voestalpine. But nothing prevented respondent to take the cue
                  from Voestalpine and talk to applicant to revise clause 55. Not only
                  respondent has not taken that initiative (they may or they may
                  not)but even now the so-called broad based panel of respondent
                  are only having names of those who were either connected with
                  railways or PSU. It does not contain names of engineers of
                  prominence and high repute from private sector. They should also
                  be included. Like wise panel should comprise of persons with legal
                  background like Judge sand lawyers, people having knowledge
                  and expertise in accountancy etc. The panel of arbitrators
                  maintained by respondent is, therefore,in my opinion, not in
                  conformity with the judgment of the Supreme Court of India in




::: Uploaded on - 12/12/2019                          ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                        44/66            carap1106-1107-18.doc

                  Voestalpine (supra). Not only the panel recommended is not in
                  conformity with Voestalpine (supra), even the procedure of
                  appointment of arbitrator as prescribed in clause-55 is totally
                  wrong. I cannot accept that one of the party to the agreement will
                  recommend four names from the panel, thereby limiting their
                  choice, which means there is no free choice, and the other party
                  has to select and forward two names from those four names to
                  Managing Director of the other party to decide who will be the
                  first party's arbitrator. Further, with the discretion given to KRCL to
                  choose more than 3 names, a room of suspicion is created in the
                  mind of other side that KRCL may have picked up its own
                  favorites. Such a situation has to be countenanced. This procedure,
                  therefore, certainly falls foul of the requirement of neutrality of
                  arbitrators. I also agree with Mr. Engineer that the part in the
                  arbitration clause which empowers the Chairman and Managing
                  Director of respondent to even appoint the presiding arbitrator is
                  violative of section 11(3) of the Act. The two arbitrators appointed
                  by the parties shall decide who shall be the presiding arbitrator.
                  24.      In the circumstances, I would expect respondent to rework
                  on clause 55 and discuss with applicant to amend that clause or
                  prepare a broad based panel of arbitrators consisting of engineers
                  of prominence and high repute from private sector, persons with
                  legal background like Judges and lawyers,         people    having
                  knowledge and expertise in accountancy etc. Respondent shall,
                  while deciding the broad based panel, keep in mind the true
                  spirit and intent of the word "broadbased panel". I would suggest
                  broadbased would mean at least eight to ten names under each
                  category.
                  25.      Respondent shall also not decide who will be the arbitrator
                  to be appointed by applicant. Respondent, once it prepares the
                  broadbased panel of arbitrators, shall only forward those names to
                  applicant and it will be open for applicant, i.e., the applicant will
                  have a free choice, to decide who shall be its nominated arbitrator.
                  It will be open to respondent to decide who will be its arbitrator
                  and the two arbitrators shall appoint the presiding arbitrator and
                  the trio shall form the arbitral panel.
                  26.     Respondent shall furnish a broad based list of panel of
                  arbitrators to applicant within two months from today. Applicant
                  will respond with the name of its arbitrator within four weeks of
                  receiving the list. Respondent thereafter shall nominate its
                  arbitrator within 14 days and the two arbitrators shall nominate
                  the third and presiding arbitrator.
                  27.    If, after appointment, applicant still feels that the arbitrator
                  appointed by respondent or the presiding arbitrator appointed
                  could be disqualified, it is open to applicant to approach this court




::: Uploaded on - 12/12/2019                            ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                     45/66            carap1106-1107-18.doc

                  for appropriate orders. All rights and contentions of the parties
                  are kept open in this regard."


 43.      Apart from the above clear position in law as being consistently

 accepted, this Court cannot overlook that in the present case the

 Managing Director has the ultimate say in appointing the arbitral tribunal

 even if the arbitration agreement is now required to be given effect to on a

 fresh invocation. In TRF Ltd vs. Energo Engineering Projects Ltd. 13, the

 three Judges Bench of the Supreme Court was considering whether the

 appointment of an arbitrator made by the Managing Director of the

 respondent therein was valid one. The agreement was entered into prior

 to the 2015 Amendment Act was brought into force on 23 October 2015.

 The contention of the appellant was that by virtue of the provisions of the

 Amendment Act by insertion of the Fifth and Seventh Schedule of the Act,

 the Managing Director of the respondent had a direct interest in the

 dispute and as such could not act as an arbitrator. The submission was also

 that a person who himself was disqualified is also not entitled to nominate

 any other person to act as an arbitrator. The Supreme Court held that the

 Managing Director in such a situation would not have any authority to

 nominate any other person to act as an arbitrator.



 13 (2017)8 SCC 377




::: Uploaded on - 12/12/2019                         ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                               46/66          carap1106-1107-18.doc


 44.      In Bharat Broadband Network Ltd. Vs. United Telecoms Ltd. 14

 (supra) an issue arising under Section 12 of the Arbitration Act fell for

 consideration of the Supreme Court, in the context of the arbitration

 agreement between the parties, which was contained in clause 20 of the

 agreement in question, which provided for sole arbitration of the CMD of

 the appellant or any other person at the discretion of the CMD. This was a

 case wherein, in pursuance of the tender dated 5 August 2013, a purchase

 order came to be issued in favour of the respondent on 30 September

 2014. The dispute had arisen between the parties on 3 January 2017. On

 17 January 2017 the CMD nominated the sole arbitrator. The Court

 referring to the decision in TRF Ltd. (supra) held that Section 12(5) has

 brought about a situation of de jure inability of the arbitrator in the event

 the requirements of Section 12 read with Fifth and Seventh Schedule are

 not satisfied. It was held that under the said provisions any prior

 agreement to the contrary is wiped out by the non-obstante clause in

 Section 12(5) the moment any person whose relationship with the parties

 or the counsel or the subject matter of the dispute falls under the Seventh

 Schedule. It was held that Section 12(5) then clearly declares that such

 person is "ineligible" to be appointed as arbitrator, except when the parties


 14 2019 SCC OnLine SC 547




::: Uploaded on - 12/12/2019                 ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                        47/66            carap1106-1107-18.doc


 otherwise agree in a manner provided under the proviso to sub-section (5)

 of Section 12. The Supreme Court has clearly held that when the

 arbitrator is ineligible to be appointed as an arbitrator, there is no question

 of challenge to such arbitrator. It is held that in a case which falls under

 Section 12(5), Section 14(1)(a) of the Arbitration Act gets attracted and

 the arbitrator becomes as a matter of law - de jure , unable to perform his

 functions under Section 12(5), being ineligible to be appointed as an

 arbitrator. The observations in this regard as made in paragraphs 14, 15,

 17 and 18, 20 are relevant which read thus:-

                  14.     From a conspectus of the above decisions, it is clear that
                  Section 12(1), as substituted by the Arbitration and Conciliation
                  (Amendment) Act, 2015 ["Amendment Act, 2015"], makes it clear
                  that when a person is approached in connection with his possible
                  appointment as an arbitrator, it is his duty to disclose in writing
                  any circumstances which are likely to give rise to justifiable doubts
                  as to his independence or impartiality. The disclosure is to be made
                  in the form specified in the Sixth Schedule, and the grounds stated
                  in the Fifth Schedule are to serve as a guide in determining
                  whether circumstances exist which give rise to justifiable doubts as
                  to the independence or impartiality of an arbitrator. Once this is
                  done, the appointment of the arbitrator may be challenged on the
                  ground that justifiable doubts have arisen under sub-section (3) of
                  Section 12 subject to the caveat entered by sub- section (4) of
                  Section 12. The challenge procedure is then set out in Section 13,
                  together with the time limit laid down in Section 13(2). What is
                  important to note is that the arbitral tribunal must first decide on
                  the said challenge, and if it is not successful, the tribunal shall
                  continue the proceedings and make an award. It is only post award
                  that the party challenging the appointment of an arbitrator may
                  make an application for setting aside such an award in accordance
                  with Section 34 of the Act.
                  15.      Section 12(5), on the other hand, is a new provision which
                  relates to the de jure inability of an arbitrator to act as such. Under
                  this provision, any prior agreement to the contrary is wiped out by




::: Uploaded on - 12/12/2019                            ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                       48/66            carap1106-1107-18.doc

                  the non- obstante clause in Section 12(5) the moment any person
                  whose relationship with the parties or the counsel or the subject
                  matter of the dispute falls under the Seventh Schedule. The sub-
                  section then declares that such person shall be "ineligible" to be
                  appointed as arbitrator. The only way in which this ineligibility can
                  be removed is by the proviso, which again is a special provision
                  which states that parties may, subsequent to disputes having arisen
                  between them, waive the applicability of Section 12(5) by an
                  express agreement in writing. What is clear, therefore, is that
                  where, under any agreement between the parties, a person falls
                  within any of the categories set out in the Seventh Schedule, he is,
                  as a matter of law, ineligible to be appointed as an arbitrator. The
                  only way in which this ineligibility can be removed, again, in law,
                  is that parties may after disputes have arisen between them, waive
                  the applicability of this sub-section by an "express agreement in
                  writing". Obviously, the "express agreement in writing" has
                  reference to a person who is interdicted by the Seventh Schedule,
                  but who is stated by parties (after the disputes have arisen
                  between them) to be a person in whom they have faith
                  notwithstanding the fact that such person is interdicted by the
                  Seventh Schedule.
                  17.     Thus, it will be seen that party autonomy is to be respected
                  only in certain exceptional situations which could be situations
                  which arise in family arbitrations or other arbitrations where a
                  person subjectively commands blind faith and trust of the parties
                  to the dispute, despite the existence of objective justifiable doubts
                  regarding his independence and impartiality.
                  18.     The scheme of Sections 12, 13, and 14, therefore, is that
                  where an arbitrator makes a disclosure in writing which is likely to
                  give justifiable doubts as to his independence or impartiality, the
                  appointment of such arbitrator may be challenged under Sections
                  12(1) to 12(4) read with Section 13. However, where such person
                  becomes "ineligible" to be appointed as an arbitrator, there is no
                  question of challenge to such arbitrator, before such arbitrator. In
                  such a case, i.e., a case which falls under Section 12(5), Section
                  14(1)(a) of the Act gets attracted inasmuch as the arbitrator
                  becomes, as a matter of law (i.e., de jure), unable to perform his
                  functions under Section 12(5), being ineligible to be appointed as
                  an arbitrator. This being so, his mandate automatically terminates,
                  and he shall then be substituted by another arbitrator under
                  Section 14(1) itself. It is only if a controversy occurs concerning
                  whether he has become de jure unable to perform his functions as
                  such, that a party has to apply to the Court to decide on the
                  termination of the mandate, unless otherwise agreed by the
                  parties. Thus, in all Section 12(5) cases, there is no challenge
                  procedure to be availed of. If an arbitrator continues as such, being




::: Uploaded on - 12/12/2019                           ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                       49/66            carap1106-1107-18.doc

                  de jure unable to perform his functions, as he falls within any of
                  the categories mentioned in Section 12(5), read with the Seventh
                  Schedule, a party may apply to the Court, which will then decide
                  on whether his mandate has terminated. Questions which may
                  typically arise under Section 14 may be as to whether such person
                  falls within any of the categories mentioned in the Seventh
                  Schedule, or whether there is a waiver as provided in the proviso
                  to Section 12(5) of the Act. As a matter of law, it is important to
                  note that the proviso to Section 12(5) must be contrasted with
                  Section 4 of the Act. Section 4 deals with cases of deemed waiver
                  by conduct; whereas the proviso to Section 12(5) deals with
                  waiver by express agreement in writing between the parties only if
                  made subsequent to disputes having arisen between them.
                  20.          Whether such ineligible person could himself appoint
                  another arbitrator was only made clear by this Court's judgment in
                  TRF Ltd. (supra) on 03.07.2017, this Court holding that an
                  appointment made by an ineligible person is itself void ab initio.
                  Thus, it was only on 03.07.2017, that it became clear beyond
                  doubt that the appointment of Shri Khan would be void ab initio.
                  Since such appointment goes to "eligibility", i.e., to the root of the
                  matter, it is obvious that Shri Khan's appointment would be void.
                  There is no doubt in this case that disputes arose only after the
                  introduction of Section 12(5) into the statute book, and Shri Khan
                  was appointed long after 23.10.2015. The judgment in TRF Ltd.
                  (supra) nowhere states that it will apply only prospectively, i.e.,
                  the appointments that have been made of persons such as Shri
                  Khan would be valid if made before the date of the judgment.
                  Section 26 of the Amendment Act, 2015 makes it clear that the
                  Amendment Act, 2015 shall apply in relation to arbitral
                  proceedings commenced on or after 23.10.2015. Indeed, the
                  judgment itself set aside the order appointing the arbitrator, which
                  was an order dated 27.01.2016, by which the Managing Director
                  of the respondent nominated a former Judge of this Court as sole
                  arbitrator in terms of clause 33(d) of the Purchase Order dated
                  10.05.2014. It will be noticed that the facts in the present case are
                  somewhat similar. The APO itself is of the year 2014, whereas the
                  appointment by the Managing Director is after the Amendment
                  Act, 2015, just as in the case of TRF Ltd. (supra). Considering that
                  the appointment in the case of TRF Ltd. (supra) of a retired Judge
                  of this Court was set aside as being non-est in law, the
                  appointment of Shri Khan in the present case must follow suit."



 45.      In a recent decision of the Supreme Court in Perkins Eastman




::: Uploaded on - 12/12/2019                           ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                         50/66                carap1106-1107-18.doc


 Architects DPC & Anr. Vs. HSCC (India) Ltd. 15 the issue which fell for

 consideration of the Supreme Court was whether as per Clause 24.1(ii) of

 the agreement between the parties, which provided that the disputes or

 differences shall be referred for adjudication through arbitration by a sole

 arbitrator appointed by the CMD-HSCC within thirty days from the receipt

 of request from the Design Consultant, can be held to be valid considering

 the provisions of Section 12 of the Arbitration Act and the decisions

 rendered in that regard. The Supreme Court referring to the decision in

 TRF Ltd vs. Energo Engineering Projects Ltd. (supra) observed that in the

 category of cases where the Managing Director is not to act as an

 arbitrator himself but is empowered or authorised to appoint any other

 person of his choice or discretion as an arbitrator, the element of invalidity

 which can be attributed in the category of cases where the Managing

 Director was found to be incompetent, as he would have interest in the

 outcome or result of the dispute, the same element of invalidity, would

 always arise and spring, even in the category of the cases where the

 Managing Director is called upon to nominate an arbitral tribunal. The

 observations in this regard in paragraphs 15 and 16 are required to be

 noted which reads thus:-


 15 Arbitration Application no.32 of 2019 dated 26/11/2019




::: Uploaded on - 12/12/2019                                 ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                        51/66             carap1106-1107-18.doc

                  "15. It was thus held that as the Managing Director became
                  ineligible by operation of law to act as an arbitrator, he could not
                  nominate another person to act as an arbitrator and that once the
                  identity of the Managing Director as the sole arbitrator was lost,
                  the power to nominate someone else as an arbitrator was also
                  obliterated. The relevant Clause in said case had nominated the
                  Managing Director himself to be the sole arbitrator and also
                  empowered said Managing Director to nominate another person to
                  act as an arbitrator. The Managing Director thus had two capacities
                  under said Clause, the first as an arbitrator and the second as an
                  appointing authority. In the present case we are concerned with
                  only one capacity of the Chairman and Managing Director and that
                  is as an appointing authority.
                  We thus have two categories of cases. The first, similar to the one
                  dealt with in TRF Limited where the Managing Director himself is
                  named as an arbitrator with an additional power to appoint any
                  other person as an arbitrator. In the second category, the Managing
                  Director is not to act as an arbitrator himself but is empowered or
                  authorised to appoint any other person of his choice or discretion
                  as an arbitrator. If, in the first category of cases, the Managing
                  Director was found incompetent, it was because of the interest that
                  he would be said to be having in the outcome or result of the
                  dispute. The element of invalidity would thus be directly relatable
                  to and arise from the interest that he would be having in such
                  outcome or decision. If that be the test, similar invalidity would
                  always arise and spring even in the second category of cases. If the
                  interest that he has in the outcome of the dispute, is taken to be the
                  basis for the possibility of bias, it will always be present irrespective
                  of whether the matter stands under the first or second category of
                  cases. We are conscious that if such deduction is drawn from the
                  decision of this Court in TRF Limited, all cases having clauses
                  similar to that with which we are presently concerned, a party to
                  the agreement would be disentitled to make any appointment of an
                  Arbitrator on its own and it would always be available to argue that
                  a party or an official or an authority having interest in the dispute
                  would be disentitled to make appointment of an Arbitrator.

                  16.     But, in our view that has to be the logical deduction from
                  TRF Limited. Paragraph 50 of the decision shows that this Court
                  was concerned with the issue, "whether the Managing Director,
                  after becoming ineligible by operation of law, is he still eligible to
                  nominate an Arbitrator" The ineligibility referred to therein, was as
                  a result of operation of law, in that a person having an interest in
                  the dispute or in the outcome or decision thereof, must not only be
                  ineligible to act as an arbitrator but must also not be eligible to
                  appoint anyone else as an arbitrator and that such person cannot




::: Uploaded on - 12/12/2019                             ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                       52/66            carap1106-1107-18.doc

                  and should not have any role in charting out any course to the
                  dispute resolution by having the power to appoint an arbitrator.
                  The next sentences in the paragraph, further show that cases where
                  both the parties could nominate respective arbitrators of their
                  choice were found to be completely a different situation. The
                  reason is clear that whatever advantage a party may derive by
                  nominating an arbitrator of its choice would get counter balanced
                  by equal power with the other party. But, in a case where only one
                  party has a right to appoint a sole arbitrator, its choice will always
                  have an element of exclusivity in determining or charting the
                  course for dispute resolution. Naturally, the person who has an
                  interest in the outcome or decision of the dispute must not have the
                  power to appoint a sole arbitrator. That has to be taken as the
                  essence of the amendments brought in by the Arbitration and
                  Conciliation (Amendment) Act, 2015 (Act 3 of 2016) and
                  recognised by the decision of this Court in TRF Limited."



          Thus applying the above principles of law, Clause 55.1 of the

 agreement providing for an arbitral tribunal to be constituted by the

 Chairman and Managing Director is rendered wholly illegal and of no

 consequence.



 46.      In so far as the contention as urged on behalf of the respondent that

 if the case of the petitinoer is accepted, the Court would be accepting the

 restrospective application of Section 12 as amended by the 2015

 Amendment Act. This contention of the respondent cannot be accepted for

 two reasons. Firstly, as noted above it cannot be overlooked that in the

 present case commencment of the arbitral proceedings can only be in a

 manner as recognized under Section 21 of the Act, that is when the




::: Uploaded on - 12/12/2019                           ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                              53/66          carap1106-1107-18.doc


 dispute would arise, a party to a contract would urge the opposite party to

 refer the dispute to arbitral tribunal. In the present case the

 commencement of the arbitral proceedings has taken place after the 2015

 Amendment Act was brought into force namely by the petitioner's letter

 dated 5 July 2017. It is in the context of this letter and in fulfilling the

 requirement of law as it stood on the day when the petitioner sought

 reference of the disputes to arbitration, the arbitral tribunal would be

 required to be constituted. For this purpose the standing arbitral tribunal

 constituted prior to coming into force of the Act certainly would not clear

 the test of law, when the commencement itself has taken place after the

 2015 Amendment Act has come into force. Thus, there is no question of

 any retrospective application of the 2015 Amendment Act.                 The only

 conclusion which can be drawn is that the Standing Arbitral Tribunal, in

 this situation constituted prior to the dispute in question having been

 arisen, by operation of law is rendered invalid and wiped out applying the

 principles of law as laid down by the Supreme Court in Bharat Broadband

 Network Ltd. Vs. United Telecoms Ltd. (supra) and Perkins Eastman

 Architects DPC & Anr. Vs. HSCC (India) Ltd. (supra).




 47.      Now I refer to some of the decisions as relied on behalf of the




::: Uploaded on - 12/12/2019                ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                  54/66         carap1106-1107-18.doc


 respondent.

          In Aravali Power Company Pvt.Ltd. Vs. Era Infra Engineering Ltd.

 (2017)15 SCC 32, the appellant had appointed its Chief Executive Officer

 as a sole arbitrator in terms of the arbitration clause, while rejecting the

 demand of the respondent to appoint an independent arbitrator. The

 invocation of the arbitration was made by the respondent by a letter dated

 29 July 2015 (prior to the 2015 Amendment Act coming into force). The

 arbitrator was appointed on 19 August 2015 which was also prior to

 coming into force of the 2015 Amendment Act. The respondent initially

 participated in the arbitral proceedings without raising any objection.

 After coming into force of the 2015 Amendment Act, for the first time on

 12 January 2016, the respondent raised an objection referring to the

 provisions of Section 12 of the Arbitration Act that the arbitrator as

 appointed by the respondent would not be an independent and impartial

 arbitrator.       The objection being rejected by the arbitral tribunal, the

 respondent approached the High Court under Section 11(6) praying that

 an impartial and neutral arbitrator be appointed. The High Court allowed

 the application. In a challenge to the said order, the Supreme Court held

 that there was nothing on record which could give rise to justifiable

 doubts about impartiality of the named arbitrator. It was held that no




::: Uploaded on - 12/12/2019                   ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                        55/66                carap1106-1107-18.doc


 challenge was raised by the respondent within time and in terms of the

 procedure prescribed and in fact the respondent had participated the

 arbitral proceedings. It was held that in these circumstances, the High

 Court ought not to have interfered in the process and the progress of the

 arbitration. I am afraid as to how this decision would in any manner

 forward the case of the respondent, when in the present case, the

 petitioner had intended reference of the disputes to arbitration after

 coming into force the 2015 Amendment Act. In this situation an arbitral

 tribunal satisfying the provisions of law and the law as laid down in the

 decisions as noted above, can only be held to be a valid arbitral tribunal.



 48.      In SP Singla Constructions Pvt. Ltd. Vs. State of Himachal Pradesh &

 Anr.16 the Supreme Court was concerned with the arbitration proceedings

 which had commenced on 18 October 2013 which was much prior to the

 commencement of the amended provisions of Section 12 of the Arbitration

 Act as amended by the 2015 Arbitration Amendment Act. The

 appointment of the arbitrator was made on 30 October 2013 and the

 arbitrator entered a reference on 11 November 2013. The appellant

 therein had approached the High Court in a petition filed under Section


 16 Civil Appeal nos.11824-11825 of 2018, decided on 4/12/2018




::: Uploaded on - 12/12/2019                             ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                               56/66          carap1106-1107-18.doc


 11(6) of the Arbitration Act praying for an appointment of an independent

 arbitrator. The High Court rejected the petition on the ground that the

 appointment of the arbitrator could not be challenged by way of an

 application under Section 11(6) of the Arbitration Act, referring to the

 decision of the Supreme Court in Antrix Corporation Ltd. Vs. Devas

 Multimedia Pvt.Ltd.17. The appellant being aggrieved by the order passed

 by the High Court approached the Supreme Court, contending that it was

 not permissible, after coming into force the 2015 Amendment Act, for the

 respondent to appoint its officer as an arbitrator. It is in this context the

 Supreme Court considering the arbitration agreement between the parties

 as contained in Clause 65 of the General Conditions of the Contract, held

 that it was not permissible for the appellant therein, to approach the High

 Court under Section 11(6) of the Act when the parties were already before

 the arbitral tribunal. It was held that considering the provisions of Section

 26 of the 2015 Amendment Act, the provisions of the amended Act were

 not to apply to the arbitral proceedings commenced in accordance with

 Section 21 of the Principal Act before the commencement of the amended

 Act, unless the parties otherwise agreed, and as in the said case the

 arbitration proceedings had commenced way back in 2014 much prior to


 17 (2014)11 SCC 560




::: Uploaded on - 12/12/2019                 ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                57/66          carap1106-1107-18.doc


 commencement of the Amended Act, hence the provisions of the Amended

 Act could not be invoked.

          In my opinion the facts of the present case are completely distinct.

 This decision would not in any manner help the respondent and more

 particularly when the arbitral proceedings in the present case have

 commenced after coming into force 2015 Amendment Act.



 49.      In Rajasthan Small Industries Corporation Ltd. Vs. Ganesh

 Containers Movers Syndicate 2019 SCC OnLine SC 65, the principal

 agreement between the parties was dated 28 January 2000. A dispute had

 arisen between the parties regarding imposition of transit penalty by the

 appellant upon the respondent interalia for delay in transportation of

 containers. The terms of the contract, Clause 4.20.1 of Schedule-4

 (General Conditions) provided for arbitration by the Managing Director

 himself or his or her nominee for the sole arbitration. The respondent

 requested for appointment of an arbitrator in terms of the said clause. The

 appellant therein appointed I.C.Shrivastava, IAS (Retd) as sole arbitrator

 on 21 February 2005 (prior to coming into force the 2015 Amendment

 Act). Since the progress of the sole arbitrator was not satisfactory, the sole

 arbitrator was removed on 26 March 2009, and in his place Chairman-




::: Uploaded on - 12/12/2019                  ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                              58/66         carap1106-1107-18.doc


 cum-Managing Director of the appellant-Corporation was appointed to act

 as sole arbitrator by consent of both the parties. For one reason or other

 the arbitral proceedings could not be concluded. On 16 March 2010 the

 respondent raised its doubt regarding impartiality of newly appointed sole

 arbitrator. The sole arbitrator passed an order on this application of the

 respondent on 6 April 2010 that the arbitration agreement provided for

 arbitration by the Chairman cum Managing Director of the Corporation or

 his nominee and only at the request of both the parties the Chairman cum

 Managing Director has taken up the arbitration to resolve the disputes

 between the parties. The disputes proceeded and on 7 February 2013 the

 respondent sent legal notice to the petitioner stating that despite number

 of requests, the sole arbitrator has not passed an award and hence called

 upon the appellant to pay an amount of Rs.3,90,81,602/-. This was

 responded by the appellant stating that since the Chairman-cum-Managing

 Director has been transferred, award could not be passed and there is no

 question of payment to the respondent. In these circumstances, two years

 thereafter on 13 May 2015 the respondent filed an application under

 Section 11(6) and Section 15 of the Arbitration Act before the High Court

 seeking appointment of an independent arbitrator for adjudication of the

 disputes between the parties. On 18 December 2015 it was brought to the




::: Uploaded on - 12/12/2019               ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                  59/66           carap1106-1107-18.doc


 notice of the arbitrator that an arbitration application has been filed

 before the High Court. On 5 January 2016 the Arbitral Tribunal adjourned

 the proceedings to 13 January 2016 as a last opportunity for hearing the

 parties. On 13 January 2016 the arbitrator rejected the application of the

 respondent contractor and the request to adjourn the proceedings till the

 decision of the High Court, and held that arbitral proceedings would be

 finalized on the basis of available facts and adjourned the arbitral

 proceedings to 21 January 2016. On 21 January 2016 the arbitrator

 passed an ex-parte award. The High Court by its judgment and order

 dated 22 April 2016 allowed the application filed by the respondent and

 appointed Mr.J.P.Bansal, Retired District Judge as sole arbitrator to resolve

 the disputes between the parties. This order of the High Court was the

 subject matter of challenge before the Supreme Court in the said case. It is

 in this context the following questions fell for consideration as noted in

 paragraph 10 of the decision:-

          (i)    In the light of the proceedings before the sole arbitrator on
          various dates and when the proceedings before the arbitrator was
          pending, whether the respondent was right in filing arbitration
          petition approaching the High Court under Section 11 and Section
          15 of the Arbitration Act, 1996 for appointment of a substitute
          arbitrator?

          (ii) When by virtue of arbitration agreement Clause 4.20.1 of
          Schedule-4 (General Conditions), parties have agreed that the
          dispute, differences between the parties to be resolved by the




::: Uploaded on - 12/12/2019                     ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                  60/66          carap1106-1107-18.doc


          Managing Director or his nominee, whether the High Court was
          right in deviating from the terms of the agreement between the
          parties and appointing an independent Arbitrator?
          (iii) Whether by virtue of Section 12 of the Arbitration and
          Conciliation (Amendment) Act, 2015, the Chairman- cum-Managing
          Director has become ineligible to act as the arbitrator?
          (iv) Whether the High Court was right in terminating the
          mandate of the arbitrator whom the parties have agreed and
          appointing substitute arbitrator on the ground that there was delay
          in passing the award?



          In the facts of the case, the Court held that the respondent had no

 material to show that the arbitrator had not acted independently or

 impartially. It was also held that the respondent had participated in the

 proceedings before the arbitral tribunal for quite some time and had

 expressed its faith in the sole arbitrator and the respondent was not

 justified in challenging the appointment of the Managing Director of the

 appellant. The Supreme Court also held that Section 12 of the Amended

 Act was not applicable in the facts of the case as the arbitral proceedings

 has commenced prior to the commencement of the 2015 Amendment Act.

 Having noted the context in which the above decision was rendered, I do

 not see how the same would assist the respondent in the facts of the

 present case.



 50.      There are other decisions as cited on behalf of the respondent which




::: Uploaded on - 12/12/2019                    ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                61/66         carap1106-1107-18.doc


 are much prior to coming into force of the Amended Act which I do not

 find to have any relevance after the 2015 Amendment Act was brought

 into force.



 51.      Now coming to the case at hand, applying the provisions of Section

 12 of the Arbitration Act read with the relevant items in the Fifth and the

 Seventh Schedules as noted above and principles of law as laid down in

 the decisions of the Supreme Court in Voestalpine Schienen GmbH Vs.

 Delhi Metro Rail Corporation Ltd. (supra), TRF Ltd vs. Energo Engineering

 Projects Ltd. (supra); Bharat Broadband Network Ltd. Vs. United Telecoms

 Ltd. (supra) and Perkins Eastman Architects DPC & Anr. Vs. HSCC (India)

 Ltd. (supra), to the facts of the present case, it is quite clear that the

 contract between the parties in the present case was executed on 24

 September 2014. Clause 55 of the Special Conditions of the Contract is the

 arbitration agreement between the parties providing for a standing

 arbitral tribunal which provides that an arbitral tribunal should consist of

 panel of three Gazetted Railway Officers not below JA Grade and a retired

 Railway Officer, retied not below the rank of SAG officer, as the

 arbitrators. The clause provides that the arbitral tribunal shall be formed

 within three months from the date of the execution of the contract and for




::: Uploaded on - 12/12/2019                 ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                              62/66          carap1106-1107-18.doc


 which purpose the respondent will send a panel of more than three names

 of Gazetted Railway Officers of one or more departments of the railways

 which may also include the name/s of retired railway officers, to the

 contractor from the panel approved by Northern Railway and within two

 weeks from the receipt of the list, the Contractor shall intimate in writing

 two names from the said list to the Chairman and Managing Director of

 the respondent. On such receipt of the nomination, the Chairman and

 Managing Director has to appoint at least one out of them as the

 petitioner's (contractor) nominee and will simultaneously appoint the

 balance number of arbitrators from the panel approved by Northern

 Railways duly indicating the presiding Arbitrator from amongst the three

 arbitrators so appointed and one out of them would be from the accounts

 department.



 52.      It is thus clear that not only the nominee arbitrator for the

 petitioner would be from the panel of serving railway officer but also the

 nominee arbitrator for the respondent and the presiding arbitrator is to be

 appointed by the Chairman and Managing Director of the respondent.

 The invocation of the arbitration in the present case as noted above was

 when the petitioner by its letter dated 5 July 2017 raised disputes on non




::: Uploaded on - 12/12/2019                ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                              63/66          carap1106-1107-18.doc


 payment of the amounts by the respondent and invoked arbitration,

 however, in accordance with the law laid down by the Supreme Court in

 Voestalpine Schienen GmbH Vs. Delhi Metro Rail Corporation Ltd. (supra)

 which was by the petitioner's letter dated 5 July 2017 and as no steps

 were taken, the petitioner has approached this Court invoking Section

 11(6) and making grievance on appointment of standing arbitral tribunal

 also has invoked Sections 14(2) and 15(2) of the Arbitration Act. It can

 therefore be clearly seen that commencement of the arbitral proceedings

 in the present case is well after commencement of 2015 Amendment Act.

 Considering the clear provision of Section 21 of the Arbitration Act, it

 would be required to be held that the arbitration proceedings have

 commenced when the request of the petitioner made on 5 July 2017 refer

 the disputes for arbitration by constituting an arbitral tribunal as per the

 law prevailing on the date of the invocaton. Thus, there can be no manner

 of doubt that the provisions of Section 12 as amended by the 2015

 Amendment Act read with the Fifth and Seventh Schedule squarely have

 become applicable in the facts of the present case and a neutral, impartial

 and an independent arbitral tribunal was required to be constituted. The

 request of the petitioner to constitute such arbitral tribunal was not

 accepted by the respondent on the ground that the standing tribunal




::: Uploaded on - 12/12/2019                ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                64/66          carap1106-1107-18.doc


 already existed. The respondent was not correct in foisting upon the

 standing arbitral tribunal on the petitioner, in view of the clear

 requirement of the provisions of Section 12 read with Fifth and Seventh

 Schedule as noted above.



 53.      The standing arbitral tribunal as constituted by the respondent in

 the present case had lost its validity and would stand wiped out,

 considering the clear position in law as laid down by the Supreme Court

 in the decisions in Voestalpine Schienen GmbH Vs. Delhi Metro Rail

 Corporation Ltd. (supra), TRF Ltd vs. Energo Engineering Projects Ltd.

 (supra); Bharat Broadband Network Ltd. Vs. United Telecoms Ltd. (supra)

 and Perkins Eastman Architects DPC & Anr. Vs. HSCC (India) Ltd. (supra).


 54.      In my opinion, the respondent had no authority to reject the request

 of the petitioner to have an appointment of an independent and neutral

 arbitral tribunal and more particularly when the standing arbitral tribunal

 as constituted by the respondent, by operation of law had become invalid

 as clearly held by the Supreme Court in Bharat Broadband Network Ltd.

 Vs. United Telecoms Ltd. (supra) and Perkins Eastman Architects DPC &

 Anr. Vs. HSCC (India) Ltd. (supra). The inevitable consequence would be




::: Uploaded on - 12/12/2019                  ::: Downloaded on - 14/12/2019 13:59:16 :::
  pvr                                  65/66         carap1106-1107-18.doc


 that an independent arbitral tribunal is required to be constituted and the

 respondent having failed to do so, this Court necessarily would have to

 exercise jurisdiction under Section 11(6) read with Sections 14 and 15 of

 the Arbitration Act.


 55.      In the above circumstances, the petitions need to succeed. They are

 accordingly allowed by the following order:-

                                       ORDER

(i) Mr.Justice M.S.Sanklecha, Former Judge of this Court, is appointed as a nominee arbitrator on behalf of the petitioner.

(ii) The respondent is directed to appoint its independent nominee arbitrator within two weeks from today.

(iii) The nominee arbitrators of both the parties shall appoint a Presiding Arbitrator before entering a reference, in accordance with the provisions of the Arbitration Act.

(iv) The learned prospective arbitrators, before entering a reference, shall make a statement of disclosure as per the requirement of Section 11(8) read with Section 12(1) of the Arbitration and Conciliation Act,1996, and forward the same to the Prothonotary and Senior Master of this Court to be placed on record of the applications, with a copy to be ::: Uploaded on - 12/12/2019 ::: Downloaded on - 14/12/2019 13:59:16 ::: pvr 66/66 carap1106-1107-18.doc forwarded to both the parties.

(v) The fees payable to the arbitral tribunal shall be governed by the provisions prescribed under the Bombay High Court (Fees Payable to Arbitrators) Rules,2018.

(vi) All contentions of the parties are expressly kept open.

(vii) The petitions are disposed of in the above terms.

(viii) A copy of this order be forwarded to the learned Arbitrator on the following e-mail address:-

"[email protected]"

(G.S.Kulkarni, J.) ::: Uploaded on - 12/12/2019 ::: Downloaded on - 14/12/2019 13:59:16 :::