Section 15 in Central Electricity Regulatory Commission (Cross Border Trade of Electricity) Regulations, 2019

15. Access Bank Guarantee.

(1)An Applicant seeking long-term access for cross border trade of electricity shall be required to furnish to the CTU, along with the application, an Access Bank Guarantee valid for five (5) years from the date of operationalization of long term access, for an amount of Rs. Five (5) Lakhs/MW corresponding to the quantum of long-term access sought.
(2)In case the grant of long-term access requires augmentation of transmission system in India, the CTU shall intimate the cost of augmentation within ninety (90) days from the date of the month in which the application is made and the Applicant shall furnish a fresh Access Bank Guarantee valid for five (5) years for an amount equivalent to the cost of such augmentation within one (1) month of intimation of the cost of augmentation by CTU.Provided that on receipt of the Access Bank Guarantee in pursuance to above, CTU shall return the Access Bank Guarantee submitted in terms of Clause (1).
(3)The Cross Border Customer who has been granted long-term access may approach CTU and seek permission to exit prior to the award of contract for execution of transmission system by the transmission licensee. All such requests shall be considered and decision communicated to the applicant not later than thirty (30) days from the date of the request.Provided that where exit is permitted, the CTU may encash Rs. 20 lakhs from the Access Bank Guarantee submitted in terms of Clause (1) or Clause (2), as the case may be, and return the balance amount to the Cross Border Customer.
(4)If a Cross Border Customer relinquishes Transmission Access granted under these Regulations after the award of the contract for execution of transmission system and before operationalization of long-term access, Access Bank Guarantee shall be encashed by the CTU.
(5)In case there is delay in commissioning of the generating station and associated dedicated transmission system beyond the timelines agreed in the Long Term Transmission Access Agreement, and longterm access has been operationalized, the transmission charges if not paid by the generator as provided in Clause (3) of Regulation 14, shall be recovered by CTU by encashing the Access Bank Guarantee submitted in terms of Clause (1) or Clause (2), as the case may be.
(6)If a Cross Border Customer relinquishes Transmission Access granted under these Regulations after operationalization of long term access, Access Bank Guarantee submitted in terms of Clause (1) or Clause (2), as the case may be, shall be encashed by the CTU subject to Clause (7) of this Regulation.
(7)The quantum of Access Bank Guarantee submitted in terms of Clause (1) or Clause (2), as the case may be, shall be progressively reduced each year after the generating company begins to avail long term access corresponding to one fifth of its total value. On completion of each year, one fifth of the value of Access Bank Guarantee shall be returned to the Applicant each year up to fourth year and one-fifth of the Access Bank Guarantee shall be retained upto twelfth year of the long term access as a security towards relinquishment charges. The Applicant shall submit revised Access Bank Guarantee accordingly.