Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 6, Cited by 0]

Kerala High Court

Power Grid Corporation Of India Ltd vs Aisha Umma on 18 February, 2025

Author: K.Babu

Bench: K. Babu

                                                     2025:KER:28971

CRP NO.580 OF 2018 & CONN. CASES
                                      1

            IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                   PRESENT

                 THE HONOURABLE MR.JUSTICE K. BABU

 TUESDAY, THE 18TH DAY OF FEBRUARY 2025 / 29TH MAGHA, 1946

                          CRP NO. 580 OF 2018

         AGAINST THE COMMON ORDER DATED 16.12.2017 IN OP(ELE)

  NO.11 OF 2012 AND OTHER CASES OF THE ADDITIONAL DISTRICT

                          COURT, NORTH PARAVUR

REVISION PETITIONER/PETITIONER:


            VARGHESE,
            AGED 63 YEARS,
            S/O.ULHANNAN, KIZHKKUMPARAMBIL HOUSE,
            PULLUVAZHI KARA,RAYAMANGALAM VILLAGE.


            BY ADV.
            SRI.P.C.HARIDAS
RESPONDENTS/RESPONDENTS:

     1      POWER GRID CORPORATION OF INDIA LTD.,
            CONSTRUCTION AREA OFFICE,MAVELIPURAM
            COLONY,KAKKANAD, COCHIN - 682 030.

     2      SPECIAL TAHSILDAR (LA),
            POWER GRID CORPORATION INDIA LTD.,
            CHEVARAMBALAM, KOZHIKODE - 17.

             BY ADV.
             SRI.MILLU DANDA PANI SC,
             SMT.G SHEEBA GP
      THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD
ON 18.02.2025, ALONG WITH CONNECTED CASES, THE COURT ON THE
SAME DAY DELIVERED THE FOLLOWING:
                                                      2025:KER:28971

CRP NO.580 OF 2018 & CONN. CASES
                                      2



            IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                   PRESENT

                 THE HONOURABLE MR.JUSTICE K. BABU

 TUESDAY, THE 18TH DAY OF FEBRUARY 2025 / 29TH MAGHA, 1946

                          CRP NO. 137 OF 2020

         AGAINST THE ORDER DATED 05.03.2019 IN OP(ELE) NO.126

  OF 2015 OF THE ADDITIONAL DISTRICT COURT, NORTH PARAVUR

REVISION PETITIONER/1ST RESPONDENT IN OP(ELE) 126/2015:

            POWER GRID CORPORATION OF INDIA LTD.,
            400 KV SUB STATION, PALLIKKARA,
            KIZHAKKAMBALAM VILLAGE, KUMARAPURAM P.O.,
            KUNNATHUNADU TALUK-683 565,
            REPRESENTED BY GENERAL MANAGER.


            BY ADV
            SRI.PRAVEEN K. JOY
RESPONDENTS/PETITIONERS 1 TO 6 & 2ND RESPONDENT IN OP(ELE)
126/2015:

     1      HAWAMMA,AGED 67 YEARS,
            W/O.KOCHUMUHAMMAD, PIRAMBILLYKUDY,
            VENGOLA KARA, ARAKKAPPADY VILLAGE,
            KUNNATHUNADU TALUK-683 554.

     2      SUDHEER,AGED 50 YEARS,
            S/O.KOCHUMUHAMMAD, PIRAMBILLYKUDY,
            VENGOLA KARA, ARAKKAPPADY VILLAGE,
            KUNNATHUNADU TALUK-683 554.

     3      JASMI,AGED 44 YEARS,
            D/O.KOCHUMUHAMMAD, PIRAMBILLYKUDY,
            VENGOLA KARA, ARAKKAPPADY VILLAGE,
            KUNNATHUNADU TALUK-683 554.
                                                          2025:KER:28971

CRP NO.580 OF 2018 & CONN. CASES
                                    3


     4       SHUKOOR,AGED 43 YEARS,
             S/O.KOCHUMUHAMMAD, PIRAMBILLYKUDY,
             VENGOLA KARA, ARAKKAPPADY VILLAGE,
             KUNNATHUNADU TALUK-683 554.

     5       FATHIMA, AGED 42 YEARS,
             D/O.KOCHUMUHAMMAD, PIRAMBILLYKUDY,
             VENGOLA KARA, ARAKKAPPADY VILLAGE,
             KUNNATHUNADU TALUK-683 554.

     6       KADHEEJA,AGED 39 YEARS,
             D/O.KOCHUMUHAMMAD, PIRAMBILLYKUDY,
             VENGOLA KARA, ARAKKAPPADY VILLAGE,
             KUNNATHUNADU TALUK-683 554.

     7       SPECIAL TAHSILDAR(LA),
             POWER GRID CORPORATION OF INDIA LTD.,
             CHEVARAMBALAM, KOZHIKODE-673 017.


             BY ADVS.
             SRI.P.C. HARIDAS PULICKAL CHANDRASEKHARA PILLAI
             SRI.SURESH V.S.(K/000350/1992)
             SMT.G.SHEEBA, GP



      THIS    CIVIL     REVISION   PETITION   HAVING   COME   UP   FOR
ADMISSION ON 18.02.2025, ALONG WITH CONNECTED CASES, THE
COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
                                                      2025:KER:28971

CRP NO.580 OF 2018 & CONN. CASES
                                      4



            IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                   PRESENT

                 THE HONOURABLE MR.JUSTICE K. BABU

 TUESDAY, THE 18TH DAY OF FEBRUARY 2025 / 29TH MAGHA, 1946

                          CRP NO. 533 OF 2018

         AGAINST THE COMMON ORDER DATED 16.12.2017 IN OP(ELE)

  NO.12 OF 2012 AND OTHER CASES OF THE ADDITIONAL DISTRICT

                          COURT, NORTH PARAVUR

REVISION PETITIONER/PETITIONER:

            RAJALAKSHMI, AGED 54 YEARS,
            W/O. ASHOKAN, KAPPILLIL HOUSE,
            PULLUVAZHI KARA, RAYAMANGALAM VILLAGE.

            BY ADV
            SRI.P.C.HARIDAS
RESPONDENTS/RESPONDENTS:

     1      POWER GRID CORPORATION INDIA LTD.,
            CONSTRUCTION AREA OFFICE,
            MAVELIPURAM COLONY, KAKKANAD,
            COCHIN - 682 030.

     2      SPECIAL TAHSILDAR (LA)
            POWER GRID CORPORATION INDIA LTD.,
            CHEVARAMBALAM, KOZHIKKODE - 17.

             BY ADVS.
             SMT.G SHEEBA,GP
             SRI.MILLU DANDAPANI,SC


      THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD
ON 18.02.2025, ALONG CONNECTED CASES, THE COURT ON THE SAME
DAY DELIVERED THE FOLLOWING:
                                                      2025:KER:28971

CRP NO.580 OF 2018 & CONN. CASES
                                      5




            IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                   PRESENT

                 THE HONOURABLE MR.JUSTICE K. BABU

 TUESDAY, THE 18TH DAY OF FEBRUARY 2025 / 29TH MAGHA, 1946

                          CRP NO. 139 OF 2020

         AGAINST THE ORDER DATED 11.03.2019 IN OP(ELE) NO.70

  OF 2014 OF THE ADDITIONAL DISTRICT COURT, NORTH PARAVUR



REVISION PETITIONER/1ST RESPONDENT IN OP(ELECTRICTY)
70/2014:

            POWER GRID CORPORATION OF INDIA LTD.,
            CONSTRUCTION AREA OFFICE,
            MAVELIPURAM COLONY,
            KAKKANAD, KOCHI-682030,
            REPRESENTED BY GEENRAL MANAGER

            BY ADV
            SRI.PRAVEEN K. JOY



RESPONDENTS/PETITIONERS/2ND RESPONDENT IN OP(ELECTRICITY)
70/2014:

     1      AISHA UMMA,AGED 76 YEARS,
            W/O.MAITHEEN, PIRAMBILLYKUDY HOUSE,
            VENGOLA KARA, ARACKAPPADY VILLAGE,
            KUNNATHUNADU TALUK-683554

     2      SPECIAL TAHSILDAR(LA),
            POWER GRID CORPORATION OF INDIA LTD.,
            CHEVARAMBALAM, KOZHIKODE-673017
                                                    2025:KER:28971

CRP NO.580 OF 2018 & CONN. CASES
                                   6


            BY ADVS.
            SRI.P.C.HARIDAS PULICKAL CHANDRASEKHARA PILLAI
            SRI.SURESH V.S.(K/000350/1992)
            SMT.G.SHEEBA, GP



      THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD
ON 18.02.2025, ALONG WITH CONNECTED CASES, THE COURT ON THE
SAME DAY DELIVERED THE FOLLOWING:
                                                      2025:KER:28971

CRP NO.580 OF 2018 & CONN. CASES
                                      7




            IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                   PRESENT

                 THE HONOURABLE MR.JUSTICE K. BABU

 TUESDAY, THE 18TH DAY OF FEBRUARY 2025 / 29TH MAGHA, 1946

                          CRP NO. 426 OF 2019

         AGAINST THE COMMON ORDER DATED 11.03.2019 IN OP(ELE)

 NO.70 OF 2014 AND OTHER CASES OF THE ADDITIONAL DISTRICT -

                            II, NORTH PARAVUR




REVISION PETITIONER/PETITIONER:

            AISHA UMMA,
            AGED 70 YEARS,
            W/O. MAITHEEN,
            PIRAMBILLYKUDY HOUSE,
            VENGOLA KARA, ARACKAPPADY VILLAGE,
            KUNNATHUNADU TALUK.


            BY ADV
            SRI.P.C.HARIDAS


RESPONDENTS/RESPONDENTS:

     1      POWER GRID CORPORATION INDIA LTD.,
            CONSTRUCTION AREA OFFICE,
            MAVELIPURAM COLONY, KAKKANAD,
            COCHIN-682 030.

     2      SPECIAL TAHSILDAR (LA),
            POWER GRID CORPORATION INDIA LTD.,
            CHEVARAMBALAM, KOZHIKKODE-17.
                                                  2025:KER:28971

CRP NO.580 OF 2018 & CONN. CASES
                                   8


            BY ADVS.
            SRI.MILLU DANDAPANI
            SMT.G.SHEEBA, GP



      THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD
ON 18.02.2025, ALONG WITH CONNECTED CASES, THE COURT ON THE
SAME DAY DELIVERED THE FOLLOWING:
                                                      2025:KER:28971

CRP NO.580 OF 2018 & CONN. CASES
                                      9



            IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                   PRESENT

                 THE HONOURABLE MR.JUSTICE K. BABU

 TUESDAY, THE 18TH DAY OF FEBRUARY 2025 / 29TH MAGHA, 1946

                          CRP NO. 474 OF 2019

         AGAINST THE COMMON ORDER DATED 05.03.2019 IN OP(ELE)

   NO.126 OF 2015 OF THE ADDITIONAL DISTRICT COURT, NORTH

                                   PARAVUR

REVISION PETITIONERS/PETITIONERS:

     1      HAWAMMA,
            AGED 66 YEARS,
            W/O. KOCHUMUHAMMED, PIRAMBILLYKUDY,
            VENGOLA KARA, ARACKAPPADY VILLAGE,
            KUNNATHUNADU TALUK.

     2      SUDHEER,
            AGED 48 YEARS,
            S/O. KOCHUMUHAMMED, PIRAMBILLYKUDY,
            VENGOLA KARA, ARACKAPPADY VILLAGE,
            KUNNATHUNADU TALUK.

     3      JASMI,
            AGED 42 YEARS,
            D/O. KOCHUMUHAMMED, PIRAMBILLYKUDY,
            VENGOLA KARA, ARACKAPPADY VILLAGE,
            KUNNATHUNADU TALUK.

     4      SHUKOOR,
            AGED 41 YEARS,
            S/O. KOCHUMUHAMMED, PIRAMBILLYKUDY,
            VENGOLA KARA, ARACKAPPADY VILLAGE,
            KUNNATHUNADU TALUK.

     5      FATHIMA,
            AGED 40 YEARS,
                                                    2025:KER:28971

CRP NO.580 OF 2018 & CONN. CASES
                                   10


            D/O. KOCHUMUHAMMED, PIRAMBILLYKUDY,
            VENGOLA KARA, ARACKAPPADY VILLAGE,
            KUNNATHUNADU TALUK.

     6      KADEEJA,
            AGED 37 YEARS,
            D/O. KOCHUMUHAMMED, PIRAMBILLYKUDY,
            VENGOLA KARA, ARACKAPPADY VILLAGE,
            KUNNATHUNADU TALUK.

            BY ADV
            SRI.P.C.HARIDAS


RESPONDENTS/RESPONDENTS:

     1      POWER GRID CORPORATION INDIA LTD.,
            NO.400 KV SUB STATION, PALLIKKARA,
            KIZHAKKAMBALAM VILLAGE, KUMARAPURAM P.O.,
            KUNNATHUNADU TALUK, PIN - 683 356.

     2      SPECIAL TAHSILDAR (LA),
            POWER GRID CORPORATION INDIA LTD.,
            CHEVARAMBALAM, KOZHIKKODE - 673 017.


             BY ADVS.
             SRI.MILLU DANDA PANI,SC
             SMT.G.SHEEBA, GP


      THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD
ON 18.02.2025, ALONG WITH CONNECTED CASES, THE COURT ON THE
SAME DAY DELIVERED THE FOLLOWING:
                                                      2025:KER:28971

CRP NO.580 OF 2018 & CONN. CASES
                                     11



            IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                   PRESENT

                 THE HONOURABLE MR.JUSTICE K. BABU

 TUESDAY, THE 18TH DAY OF FEBRUARY 2025 / 29TH MAGHA, 1946

                          CRP NO. 664 OF 2019

         AGAINST THE ORDER DATED 16.12.2017 IN OP(ELE) NO.12

  OF 2012 OF THE ADDITIONAL DISTRICT COURT, NORTH PARAVUR

PETITIONER/1ST RESPONDENT:

            THE POWER GRID CORPORATION OF INDIA LTD.,
            CONSTRUCTION AREA OFFICE,
            MAVELIPURAM COLONY,
            KAKKANAD,
            COCHIN - 682030.


            BY ADV
            SRI.ROJO J.THURUTHIPARA


RESPONDENTS/PETITIONER AND RESPONDENT - 2:

     1      RAJALAKSHMI,
            AGED 56 YEARS,
            W/O. ASHOKAN, KAPPILLIL HOUSE,
            PULLUVAZHI KARA,
            RAYAMANGALAM VILLAGE,
            KUNNATHUNAD TALUK,
            PIN - 683545.

     2      SPECIAL THASILDHAR (LA),
            POWER GRID CORPORATION OF INDIA LTD.,
            CHEVARAMBALAM,
            KOZHIKODE - 673017.


            BY ADVS.
            SRI.P.C.HARIDAS
                                                          2025:KER:28971

CRP NO.580 OF 2018 & CONN. CASES
                                   12


             SHRI.SURESH V.S.
             SMT.G.SHEEBA, GP



      THIS    CIVIL     REVISION   PETITION   HAVING   COME   UP   FOR
ADMISSION ON 18.02.2025, ALONG WITH CONNECTED CASES, THE
COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
                                                      2025:KER:28971

CRP NO.580 OF 2018 & CONN. CASES
                                     13



            IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                   PRESENT

                 THE HONOURABLE MR.JUSTICE K. BABU

 TUESDAY, THE 18TH DAY OF FEBRUARY 2025 / 29TH MAGHA, 1946

                           CRP NO. 44 OF 2020

         AGAINST THE COMMON ORDER DATED 16.12.2017 IN OP(ELE)

    NO.11 OF 2012 OF THE ADDITIONAL DISTRICT COURT, NORTH

                                   PARAVUR

PETITIONER/RESPONDENT:

            M/S POWER GRID CORPORATION OF INDIA LIMITED,
            CONSTRUCTION AREA OFFICE, KAKKANADU,
            KOCHI-682030.


            BY ADVS.
            SMT.V.A.HARITHA
            SRI.S.SREEKUMAR (SR.)(S-571)



RESPONDENTS/PETITIONER/2ND RESPONDENT:

     1      V. VARGHESE,
            S/O. ULAHANNAN, AGED 65,
            KIZHAKKUMPARAMBIL HOUSE, PULLUVAZHI KARA,
            RAYAMANGALAM VILLAGE,
            REPRESENTED BY HIS POWER OF ATTORNEY HOLDER,
            PAUL K. JOHN, AGED 53, S/O. ULAHANNAN,
            KIZHAKKUMPARAMBIL HOUSE, PULLUVAZHI KARA,
            RAYAMANGALAM VILLAGE, PIN-683541.

     2      SPECIAL TAHSILDAR (L.A.),
            POWER GRID CORPORATION OF INDIA LTD.,
            CHEVARAMBALAM, KOZHIKODE- 673017.
                                         2025:KER:28971

CRP NO.580 OF 2018 & CONN. CASES
                                   14


            BY ADVS.
            SRI.P.C.HARIDAS
            SRI.SURESH V.S.
            SMT.G.SHEEBA, GP



    THIS CIVIL REVISION PETITION HAVING BEEN
FINALLY HEARD ON 18.02.2025, ALONG WITH CONNECTED
CASES, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
                                                                  2025:KER:28971

CRP NO.580 OF 2018 & CONN. CASES
                                       15




                                 K.BABU, J.
                   -------------------------------------------
                    CRP Nos. 580, 533 of 2018,
                      426, 664, 474 of 2019
                      & 139, 44, 137 of 2020
                ---------------------------------------------
            Dated this the 18th day of Februrary, 2025


                                   ORDER

Common questions arise for consideration in all these Civil Revision Petitions. The Power Grid Corporation of India Limited drew 400 KV double circuit lines through the properties of the claimants. The respective claimants filed petitions under Sections 10 and 16 of the Telegraph Act read with Section 151 of the Indian Electricity Act, 1910 and Section 42 of the Electricity Supply Act, 1948 before the Additional District Court, North Paravur, claiming enhanced compensation under various heads. The Trial Court allowed those applications. The claimants approached this Court contending that the compensation awarded is meagre, whereas the Power Grid Corporation challenged the awards contending that the amount awarded is exorbitant.

2025:KER:28971 CRP NO.580 OF 2018 & CONN. CASES 16 CRP Nos. 426 of 2019 and 139 of 2020

2. The Power Grid Corporation of India Limited had drawn a 400 KV electric line through the property of the claimant comprised in Sy.No.337/6 of Arackappady Village. The property was a wet land, cultivated with various crops including plantains. The Corporation quantified the compensation as Rs.25,263/-. The Trial Court granted a sum of Rs.12,17,237/- as compensation with interest at the rate of 6% from 04.07.2011 till the date of realisation. CRP No.474 of 2019 and 137 of 2020

3. The case of the claimants is that their property is used for the purpose of drawing 400 KV Cochin-Trichur electric line. The claimants received only an amount of Rs.7,12,170/- towards compensation for various trees cut and removed from their property. The Trial Court granted a sum of Rs.86,15,600/- as compensation with interest at the rate of 8% from the date of cutting of trees till the date of realisation.

2025:KER:28971 CRP NO.580 OF 2018 & CONN. CASES 17 CRP No.580 of 2018 and 44 of 2020

4. The case of the claimant is that he is the owner in possession of 26.15 Ares of property comprised in Re.Sy.Nos.203/2, 203/17, 203/4 of Rayamangalam Village. The land is very fertile, cultivated with yielding and non- yielding trees. For the purpose of drawing 400 KV Kochi- Trichur electric line through his property, trees were cut and removed by the Power Grid Corporation of India Limited. The Trial Court granted a sum of Rs.85,13,500/- as compensation with interest at the rate of 8% from the date of cutting of trees till the date of realisation. CRP No.533 of 2018 and 664 of 2019

5. The case of the claimant is that she is the owner in possession of 34.8 Ares of property comprised in Re.Sy.Nos. 205/2, 205/3 and 205/4 of Rayamangalam Village. The land is very fertile, cultivated with yielding and non-yielding trees. For the purpose of drawing 400 KV Kochi- Trichur electric line through her property, trees were cut and removed by the Power Grid Corporation of India 2025:KER:28971 CRP NO.580 OF 2018 & CONN. CASES 18 Limited. The Trial Court granted a sum of Rs.11,59,100/- as compensation with interest at the rate of 8% from the date of cutting of trees till the date of realisation.

6. I have heard the learned counsel for the claimants, the learned Standing Counsel appearing for the Power Grid Corporation of India Limited and the learned Government Pleader appearing for the Special Tahasildar.

7. The common grounds raised by the claimants are the following:-

(a)The compensation for diminution in land value granted is too low, in view of the fact that the value of the entire properties is affected by way of drawing the line.
(b) The land value determined by the District Court is too low.
(c) The properties of the claimants are situated in prominent places in the locality with road access.

2025:KER:28971 CRP NO.580 OF 2018 & CONN. CASES 19

(d) The situs of the land was not considered while awarding compensation.

8. The Power Grid Corporation of India Limited raised the following contentions:-

The land value fixed by the Trial Court for awarding compensation towards diminution in the land value is much higher than the fair value fixed by the Government. The claimants did not place any credible materials to establish the land value, and therefore, the Trial Court should have relied on the fair value fixed by the Government. The report of the Commissioner is not a valuable piece of evidence to enter into a conclusion regarding the land value. The Commissioner assessed the value of the properties long time after the lines were drawn. The claimants were sufficiently compensated even prior to the institution of the claim petitions. For fixation of the compensation towards cutting and removal of the trees, the Trial Court ignored the detailed valuation statement prepared by the Competent Authority at the time of cutting, but relied on the 2025:KER:28971 CRP NO.580 OF 2018 & CONN. CASES 20 assessment made by the Commissioner which is not at all relevant. The Corporation has not acquired the properties. It has only drawn electric lines over the properties, by which the value of the properties is not substantially diminished.

9. In KSEB v. Livisha [(2007) 6 SCC 792], the Supreme Court held that the proper multiplier to be used for fixation of compensation on the value of trees is 8. While dealing with the question of diminution in the land value in KSEB v. Livisha, the Supreme Court held thus:-

"10. The situs of the land, the distance between the high voltage electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small track of land or through the middle of the land and other similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used."

10. Now, I shall consider the impugned awards on the touchstone of the principles discussed above. CRP Nos.426 of 2019 and 139 of 2020

11. The affected area by way of drawing the line is estimated as 10.9 Ares. The Commissioner appointed by the 2025:KER:28971 CRP NO.580 OF 2018 & CONN. CASES 21 Trial Court prepared Ext.C1 report which has become part of evidence as per Order XXVI Rule 10 of the CPC. It has come out in evidence that the property abuts a Panchayat road. The claimant relied on Ext. A1 title deed dated 29.11.2007. Relying on Ext.C1 report and Ext.A1 title deed, the Trial Court fixed the market value as Rs.90,000/- per cent. When converted into cents the affected area is admittedly 26.9 cents. The Trial Court assessed the value towards diminution in the land value as Rs.24,21,000/-. The Court held that the claimant is entitled to half of the total value, which comes to Rs.12,10,500/-. The compensation for 8 plantains cut and removed was fixed by applying the following formula:

8 X 500 X 8 = 32,000/-

Therefore, the claimant was entitled to a total compensation of Rs.12,42,500/-. The Corporation had already paid Rs.25,263/- at the time of drawing the line. Therefore, the Court fixed the compensation as Rs.12,17,237/- with 6% interest from 04.07.2011 till the date of realisation.

2025:KER:28971 CRP NO.580 OF 2018 & CONN. CASES 22 Considering the assessment of compensation on the touchstone of the principles discussed above, this Court is of the view that the order impugned in CRP Nos.426/2019 and 139/2020 is liable to be confirmed. The Civil Revision Petitions filed by the claimant and the Corporation lack merits and stand dismissed. The order dated 11.03.2019 in O.P.(Ele) No.70/2014 stands confirmed. CRP No.474 of 2019 and 137 of 2020

12. The Commissioner reported that 17 coconut trees were cut and removed. The total coconuts obtained in an year from 1 coconut tree was assessed as 197 (after deducting droppings and expenditure). The market price of one coconut, as published in the newspaper was, Rs.8. Based on Livisha's case, 8 is taken as the multiplier. The Court applied the following formula to assess the value of coconut trees:-

197 X 17 X 8 X Rs.8 = Rs.2,14,336/-

13. The Commissioner reported that 100 rubber trees were cut and removed. The quantity of latex collected 2025:KER:28971 CRP NO.580 OF 2018 & CONN. CASES 23 from a rubber tree was fixed at 13Kg per year. The price of rubber at the relevant time was Rs.200/- per Kg. The Court applied the following formula for assessing the compensation towards cutting and removal of the rubber trees:

100 X 13 Kg X Rs.200 X 8 = Rs.20,80,000/-

- [25% of the income deducted towards expenditure and fixed the compensation at Rs.15,60,000/-].

14. 100 nutmeg trees were also cut and removed from the property. The Court fixed the total number of nutmegs obtained in one year from a tree as 3,000. The Court calculated the rate of premature fall at 25% and 25% towards expenditure. Therefore, the number of nutmegs was assessed as 1,688. The dried nutmegs obtained was assessed as 12Kg. The Trial Court assessed that from 1 nutmeg 2 gms of Jathipathri is obtained. The Commissioner reported that the price of Jathi was Rs.200/- and Jathipathri was Rs.800/-. The value of Jathi was assessed at 2025:KER:28971 CRP NO.580 OF 2018 & CONN. CASES 24 Rs.19,20,000/- (100 X 12 X 200 X 8). The value of Jathipathri was assessed at Rs.21,12,000/- (100 X 3.3 X 800 X 8). Therefore, the total amount towards loss of nutmeg trees was assessed at Rs.40,32,000/-

15. The Commissioner reported that 18 arecanut trees were cut and removed from the property. The price of dried arecanut is Rs.110/-. Based on the assessment that 8 Kgs of arecanuts are obtained per year from 1 arecanut tree, the value of arecanut was assessed at Rs.1,26,720/- (110 X 18 X 8 X 8). The claimants were found to be entitled to Rs.59,33,056/- as value of improvements. The affected area of land due to the drawing of electric line was fixed as 26.30 Ares (64.99 cents). The land value was fixed at Rs.1,00,000/- per cent. So the value of the land affected was assessed at Rs.64,99,000/- (64.99 X 1,00,000/-). Out of this, 50% was deducted towards diminution of land value, and hence, the value of land injuriously affected was assessed at Rs.32,49,500/-. An extent of 1.47 Ares of land was used for the erection of tower. The land value at the place where the tower was erected was fixed at Rs.40,000/- per cent. So, the 2025:KER:28971 CRP NO.580 OF 2018 & CONN. CASES 25 value was fixed at Rs.1,45,200/- (3.63 cents X 40,000). Therefore, the total compensation entitled to the claimants was assessed in the following manner:-

Value of trees cut and removed = Rs.59,33,056/-
       Value of land                      = Rs.33,94,700/-

       Total                              = Rs.93,27,756/-



16. The Corporation had already paid Rs.7,12,170/-

towards compensation. The balance compensation to which the claimants were entitled was assessed at Rs. 86,15,586/- which is rounded to Rs.86,15,600/- with 8% interest from the date of cutting of trees till the date of realisation. The compensation fixed by the District Court is fair and reasonable. The compensation is in tune with the guidelines issued by the Supreme Court in Livisha's case. I find no reason to interfere with the impugned order. Therefore, the impugned order in CRP Nos.474/2019 and 137/2020 is liable to be confirmed. Civil Revision Petitions filed by the claimant and the Corporation lack merits and stand dismissed. The 2025:KER:28971 CRP NO.580 OF 2018 & CONN. CASES 26 order dated 05.03.2019 in O.P.(Ele) No.126/2015 stands confirmed.

CRP No.580 of 2018 and 44 of 2020

17. The Commissioner reported that 32 coconut trees were cut and removed. The Trial Court followed the assessment of value made in O.P.(C)No.10/2012 and the value of the coconuts was fixed at Rs.4,03,456/- (197 X 32 X 8 X Rs.8). In Ext.C1 report, the Commissioner stated that 40 numbers of pepper plants were cut and removed. Yield of 1 pepper plant was fixed as 3 Kgs per year, out of which 25% was deducted towards expenses. Net yield of 1 pepper plant therefore, was fixed at 2.250 Kgs. The value of 1 Kg of pepper was Rs.250/- at the relevant time. The Court fixed the compensation as Rs.1,80,000/- (2.25 X Rs.250 X 8 X 40 Nos.).

18. The Commissioner reported that 44 nutmeg trees were cut and removed. The Trial Court followed the assessment of value applied in O.P.(C) No.10/2012 and other cases. The Trial Court assessed the value of Jathi at 2025:KER:28971 CRP NO.580 OF 2018 & CONN. CASES 27 Rs.8,44,800/- (44 X 12 X 200 X 8) and the value of Jathipathri at Rs.9,29,280/- (44 X 3.3 X 800 X 8). Thereby, the total income obtained from the nutmeg trees is assessed at Rs.17,74,080/-.

19. 40 arecanut trees were cut and removed. The valuation arrived towards cutting and removal of 40 arecanut trees is as follows:-

110 X 8Kg X 8 X 40 = Rs.2,81,600/-

20. 3 jack fruit trees were also cut and removed. The Trial Court fixed Rs.20,000/- for the various trees cut and removed. For various other trees including 88 anjili trees, 4 mango trees, 88 timber trees, mahagony trees etc. the Trial Court fixed a compensation of Rs.80,000/-. The claimant was found to be entitled to a total compensation of Rs.27,39,136/- towards the value of trees cut and removed.

21. Relying on Ext.B4 fair value notification and Ext.C1(a) report, wherein it is mentioned that the land has road frontage on two sides, the Trial Court fixed the value of land at Rs.2,00,000/- per cent. The Trial Court found that the 2025:KER:28971 CRP NO.580 OF 2018 & CONN. CASES 28 area of the land injuriously affected is 26.15 Ares (64.59 cents). The value of total affected area is fixed as 64.59 X Rs.2,00,000/- which is equal to Rs.1,29,18,000/-. The District Court assessed 50% as deduction towards diminution of land value due to the drawing of electric line. Hence, the value of the land injuriously affected was assessed at Rs.64,59,000/-. The total compensation entitled to the claimant was assessed as follows:-

Value of trees cut and removed = Rs.27,39,136/- Value of land injuriously affected = Rs.64,59,000/-
Total compensation = Rs.91,98,136/-
22. The claimant had already received Rs.6,84,726/-

towards compensation. The balance compensation entitled to the claimant is found to be Rs.85,13,410/- which is rounded to Rs.85,13,500/- with 8% interest from the date of cutting of trees till the date of realisation. The compensation fixed by the District Court is fair and reasonable. The compensation is in tune with the guidelines 2025:KER:28971 CRP NO.580 OF 2018 & CONN. CASES 29 issued by the Supreme Court in Livisha's case. I find no reason to interfere with the impugned order.

CRP Nos.580 of 2018 and 44 of 2020 lack merits and stand dismissed. The order dated 16.12.2017 in O.P.(Ele) No.11/2012 stands confirmed.

CRP No.533 of 2018 and 664 of 2019

23. 6 coconut trees were cut and removed. The Trial Court followed the method of calculation adopted in O.P.(C) No.10 of 2012. So, the compensation towards cutting of coconut trees was assessed at Rs.75,648/- (197 X 6 X 8 X Rs. 8)

24. Three Pepper plants were cut and removed. The compensation was assessed at Rs.13,500/- (2.25 X 250 X 8 X 3 Nos). For various other trees, the Trial Court fixed the compensation at Rs.20,000/-. So, the total compensation entitled to the claimant towards cutting and removal of the trees was assessed by the Court at Rs.1,09,148/-.

25. The Court assessed the area injuriously affected by way of drawing electric line as 29.90 Ares (73.85 cents).

2025:KER:28971 CRP NO.580 OF 2018 & CONN. CASES 30 Relying on Ext.B16 fair value notification and Ext.C1(e) plan, the Court fixed the value of the property at the relevant time at Rs.60,000/- per cent. The value of the land injuriously affected was assessed at Rs.44,31,000/- (73.85 X 60,000) out of which 75% was deducted towards diminution of land value, and hence, the value of the land injuriously affected was assessed at Rs.11,07,750/-. The claimant was awarded a sum of Rs.1,09,148/- towards the value of trees cut and removed. The total compensation entitled to the claimant was assessed as follows:-

Value of trees cut and removed = Rs. 1,09,148/- Value of land injuriously affected = Rs.11,07,750/-
                                           _________________

       Total compensation                = Rs.12,16,898/-

26. The claimant had already received Rs.57,801/-

towards compensation. The balance compensation entitled to the claimant is found to be Rs.11,59,100/- with 8% interest from the date of cutting of trees till the date of realisation. The compensation fixed by the District Court is fair and reasonable. The compensation is in tune with the 2025:KER:28971 CRP NO.580 OF 2018 & CONN. CASES 31 guidelines issued by the Supreme Court in Livisha's case. I find no reason to interfere with the impugned order.

CRP Nos.533 of 2018 and 664 of 2019 filed by the claimant and the Corporation lack merits and stand dismissed. The order dated 16.12.2017 in O.P.(Ele) No.12/2012 stands confirmed.

Sd/-

K.BABU JUDGE VPK