Supreme Court of India

Ramzan vs Smt. Hussaini on 24 November, 1989

Equivalent citations: 1990 AIR 529, 1989 SCR SUPL. (2) 287, AIR 1990 SUPREME COURT 529, 1990 (1) SCC 104, 1990 ALL CJ 159, (1990) REVDEC 463, (1990) 1 CURLJ(CCR) 299, (1990) 1 CIVLJ 787, (1990) 1 APLJ 53.1, (1990) 1 SCJ 278

Author: L.M. Sharma

Bench: L.M. Sharma, T.K. Thommen

           PETITIONER:
RAMZAN

	Vs.

RESPONDENT:
SMT. HUSSAINI

DATE OF JUDGMENT24/11/1989

BENCH:
SHARMA, L.M. (J)
BENCH:
SHARMA, L.M. (J)
THOMMEN, T.K. (J)

CITATION:
 1990 AIR  529		  1989 SCR  Supl. (2) 287
 1990 SCC  (1) 104	  JT 1989  Supl.    354
 1989 SCALE  (2)1310


ACT:
    Limitation Act, 1963: Article 54 Specific performance of
contingent contract--Period of limitation--Determination of.



HEADNOTE:
    The	 period	 of limitation of three years  for  specific
performance  of	 a contract begins to run  under  the  third
column	of Article 54 of the Limitation Act, 1963  from	 the
date  fixed  for  the performance, or, if no  such  date  is
fixed,	when  the plaintiff has notice that  performance  is
refused.
    Under  an agreement dated June 23, 1965  the  plaintiff-
respondent, sister of the defendant-appellant, undertook  to
redeem	the disputed property under mortgage and the  appel-
lant agreed to execute the sale deed of the said property in
her  favour on the date she took papers of the	registry  in
her  possession.  She  redeemed the property  in  1970.	 The
appellant, however, failed to respect the agreement in spite
of repeated demands.
    The	 respondent served a notice in July  1984  demanding
specific  performance before filing the suit. The  appellant
pleaded	 limitation.  The trial court decided the  issue  in
favour	of the respondent. That order was confirmed  by	 the
High Court on the view that since the cause of action of the
suit was dependent on the redemption of the mortgage and  no
period	was  fixed  within which it was	 necessary  for	 the
respondent  to have redeemed the mortgage, it could  not  be
said  that  a date was ''fixed" within the  meaning  of	 the
third column of Article 54.
Allowing the appeal by special leave,
    HELD:  1.1 The requirement of Article 54 of the  Limita-
tion Act, 1963 is not that the actual day should necessarily
be ascertained upon the face of the deed, but that the basis
of  the calculation which was to make it certain  should  be
found therein. [291A-B]
    1.2	 In the instant case, under the agreement  the	date
for  the appellant to execute the sale deed was	 fixed,	 al-
though not by mentioning
288
a  certain  date but by a reference to the  happening  of  a
certain event, namely, the redemption of the mortgage;	and,
immediately  after  the redemption by  the  respondent,	 the
appellant  became liable to execute the sale deed which	 the
respondent was entitled to enforce. The period of limitation
thus started running on that date. The case, is,  therefore,
covered	 by the first part of Article 54 (third column)	 and
not the second part. [291B-C]
     R.	 Muniswami  Goundar & Anr. v.B.M. Shamanna  Gouda  &
Ors., AIR 1950 Madras 820 and Duncombe v. The Brighton	Club
JUDGMENT:

Sathula Venkanna v. Namuduri Venkatakrishnayya & Anr., AIR 1918 Madras 492; Kruttiventi Mallikharjuna Rao v. Vemuri Pardhasaradhirao, AIR 1944 Madras 218 and Kashi Prasad v. Chhabi Lal & Ors'., AIR 1933 Allahabad 410 (2) distin- guished-

2. The agreement in the instant case is a typical illustration of a contingent contract within the meaning of s. 31 of the Indian Contract Act, 1872 and became enforce- able as soon as the event of redemption happened. The doc- trine of id certum est quod certum reddi potest is clearly applicable to the case. [290D-E] & CIVIL APPELLATE JURISDICTION: Civil Appeal No. 4754 of 1989.

From the Judgment and Order dated 17.5.1989 of the Rajasthan High Court in S.B. Civil Revision Petition No 450 of 1988.

V.M. Tarkunde, B.L. Kachhawan and Badridas Sharma for the Appelant.

Aruneshwar Gupta and S. Kumar for the Respondent. The Judgment of the Court was delivered by SHARMA, J. Special leave is granted.

2. This appeal arises out of a suit filed by the re- spondent against her brother, the appellant, for specific performance of an alleged contract of sale dated 23.6.1965 in respect of a house. The property was under a mortgage and according to the plaintiff's case, the defendant had agreed to execute a deed of sale on the redemption of the mort-

289

gage by her, which she did in 1970. In spite of her repeated demands the defendant failed to respect the agreement which necessitated the institution of the suit.

3. The defendant-appellant, besides pleading limitation, denied the agreement as also the plaintiff's allegation that she had redeemed the mortgage.

4. The question of limitation was taken up by the trial court as a preliminary issue and decided in favour of the plaintiff. The order has been confirmed by the High Court by the impugned judgment.

5. The plaintiff served a notice in July 1984 demanding specific performance before filing the suit. It has been contended on behalf of the appellant that since the alleged agreement is said to have been executed in June 1965, the suit is barred by limitation, and alternatively, even count- ing the period of limitation from the alleged redemption in 1970, the suit has been filed after more than 14 years, that is, long after the expiry of three years' period prescribed under Article 54 of the Limitation Act of 1963. The High Court has rejected the argument holding that since the cause of action of the suit was dependent on the redemption of the mortgage and no period was fixed within which it was neces- sary for the respondent to have redeemed the mortgage, it cannot be said that a date was 'fixed' within the meaning of the third column of Article 54, which reads thus:

Description	     period of	    Time from which
of suit		     limitation	    period begins to run
"54. For specific      three years   The date fixed for	 the
per-
performance.			      formance,	 or,  if  no
such
				     date is fixed, when the
				     plaintiff	has   notice
that
				     performance	  is
refused."

As the notice preceding the suit was admittedly served within three years, the defendant's plea of limitation was rejected.

6. The relevant provisions in the alleged agreement of sale as quoted in the judgment of the trial court reads as follows:

290
"This house is under mortgage with Jethmal Bastimal for Rs. 1000. When you will get this house, the description of which is given below, redeemed from M/s Jeth Mat Bastimal and take the papers of the registry in your pos- session, on that day I will have the sale deed of the said house, written, executed and registered in your favour."

(emphasis supplied The question is whether a date was 'fixed' for the perform- ance of the agreement and in our view the answer is in the affirmative. It is true that a particular date from the calander was not mentioned in the document and the date was not ascertainable originally, but as soon as the plaintiff redeemed the mortgage, it became an ascertained date. If the plaintiff had, immediately after the redemption, flied the suit, could it be thrown out on the ground that she was not entitled to the specific performance asked for? We do not think so. She would have been within her rights to assert that she had performed her part of the contract and was entitled to insist that her brother should complete his part. The agreement is a typical illustration of a contin- gent contract within the meaning of s. 31 of the Indian Contract Act, 1872 and became enforceable as soon as the event of redemption (by the plaintiff hereself) happened. We agree with the view of the Madras High Court in R. Muniswami Goundar and Another v.B.M. Shamanna Gouda and Others, AIR 1950 Madras 820 expressed in slightly different circum- stances. The doctrine of id certurn est quod certum reddi potest is clearly applicable to the case before us which in the language of Herbert Broom (in his book dealing with legal maxims) is that certainty need not be ascertained at the time; for if, in the fluxion of time, a day will arrive which will make it certain, that is sufficient. A similar question had arisen in Duncombe v. The Brighton Club and Norfolk Hotel Company, [1875] 10 QB 371, relied upon in the Madras case. Under an agreement, the plaintiff had supplied some furniture to the defendant for which payment was made but after .some delay. He claimed interest. The rule at Common Law did not allow interest in such a case, and the plaintiff in support of his claim relied upon a statutory provision which could come to his aid only if the price was payable at a certain time. Blackburn, J. observed that he did not have the slightest hasitation in saying that the agreement contemplated a particular day, which, when the goods were delivered would be ascertained, and then the money would be payable at a certain time; but rejected the plaintiff's demand on the ground that the price did not become payable by the written instrument at a certain time. The other learned Judges did not agree with him, and held that the statute did 291 not require that the document should specify the time of payment by mentioning the day of payment. If it specified the event upon which the payment was to be made, and if the time of event was capable of being ascertained, the require- ments of the section were satisfied. The same is the posi- tion in the case before us. The requirement of Article 54 is not that the actual day should necessarily be ascertained upon the face of the deed, but that the basis of the calcu- lation which was to make it certain should be found therein. We, accordingly, hold that under the agreement the date for the defendant to execute -the sale deed was fixed, although not by mentioning a certain date but by a reference to the happening of a certain event, namely, the redemption of the mortgage; and, immediately after the redemption by the plaintiff, the defendant became liable to execute the sale deed which the plaintiff was entitled to enforce. The period of limitation thus started running on that date. The case is, therefore, covered by the first part of Article 54 (third column) and not the second part.

7. The learned counsel for the respondent relied on several decisions in support of the opinion of the High Court in the impugned judgment but they do not appear to help him. In Sathula Venkanna v. Namuduri Venkatakrishnayya and Another, AIR 1918 Madras 492, it was observed that in cases where a right to enforce specific performance vests in a third party to whom the ascertainment of the date on which performance becomes due need not necessarily be known, the doctrine certum est quod certum reddi potest does not apply. Without expressing their final opinion the learned Judges observed that it might be right to apply the doctrine be- tween the actual parties to the contract who would get the benefit and be subject to the liabilities under that con- tract; "but in cases where a person is entitled to bring a suit on the contract who may not and need not, and very likely may not be aware of the date becoming fixed", the doctrine could not apply. In Kruttiventi Mallikharjuna Rao v. Vemuri Pardhasaradhirao, AIR 1944 Madras 2 18, the vendor promised to execute the sale deed when both of his brothers, who were studying elsewhere, returned to the village. It was held that it was not a case where it could be said that a date was fixed for the performance of the contract as the event mentioned therein was too indefinite to be regarded as fixing a date. The performance was dependant on both the brothers of the vendor coming to the village, in which the intending purchaser had no say at all. Apart from the ques- tion of limitation, the defendant could not effectively rely upon such a clause to defeat the very contract. In Kashi Prasad v. Chhabi Lal and Others, AIR 1933 Allahabad 410(2), the plaintiff created two usufructuary mortgages and there- after a third mortgage in 292 favour of the defendants for a sum of Rs.8,500. Out of this sum an amount of Rs.6,000 was left with the mortgagees for payment to the earlier creditors. The suit was instituted on the allegation that the defendants had failed to redeem the earlier mortgages. The plaintiff prayed for a direction to the defendants to redeem the mortgages. The document did not indicate as to the time when the defendants were obliged to redeem the earlier mortgages, and a plea of limitation was taken on the ground that the date was fixed by necessary implication and could be ascertained by reference to the surrounding circumstances. In this background the court observed that the use of the word 'fixed' implies that it should be fixed definitely and should not be left to be gathered from surrounding circumstances of the case. All these cases are clearly distinguishable.

8. For the reasons mentioned above, the impugned judg- ments of the High Court and the trial court are set aside and the suit is dismissed. The appeal is accordingly al- lowed, but the parties are directed to bear their own costs throughout.

P.S.S.						      Appeal
allowed.
293