"The performace of L-I in HUDA allotted works is extremely
unsatisfactory. In fact, in work pertaining to providing Master
Water Supply Scheme (SWD), Sector 75-89, Faridabad, it has
already been imposed 2% penalty under Clause-II. The work
CWP No. 20209 of 2014 [ 13 ]
was supposed to have been completed on 11.4.2014 but till
7.8.2014, only 40% work has been completed. Moreover, in
respect of other major work costing Rs.124.70 crores
pertaining to Master Sewerage Scheme of Sector 77 to 115,
Gurgaon, the performance is less than 10% even though time
limit for completion work has expired. In the reasons for delay,
third party insepction agency M/s Sri Ram Test House has
been blamed for delay in inspection of material. Delay has also
been attributed to delay in finalization of technical scheme but
there is some delay on the part of this L-I contractor also for
which it has been issued notice. Then there is gray area
whether its experience certificate given by Ramky
Infrastructure, who is the contractor of the HSIIDC, can be
given any credence. It also needed to be ascertained by HUDA
whether Ramky Infrastructure was allowed as per terms of
contract to sublet this work to any other contractor or not but
while evaluating the eligibility of L-I, same was no done by
XEN, HUDA."