Further to the reference cited, I am directed to inform you as follows on the matter of levy of 'Grid Support Charge' for affording parallel operation of captive generating units with TRANSCO's Grid.
2. By availing the facility of parallel operation, the consumer is enjoying the following benefits:
(a) The fluctuations in the load of consumer are instantaneously shared by the Grid, then reducing the strain on the Captive Generating unit and straining the TRANSCO's Grid.
(b) The variation in the capacity of Captive Generating unit due to the non-functioning malfunctioning of different auxiliaries etc. are reflected instantaneously to the Grid causing instantaneous strain on the TRANSCO system.