7.3 Implementation Arrangement The MOR and the JICA Consultant(s) will be responsible in the following manner for completing the Study in order to ensure a smooth procurement procedure of the Protect.
(1) The JICA Consultant(s) will prepare the Draft Design Documents and technical specification and standards as required under this study and submit them to the MOR.
(2) The MOR will review the Draft Design Documents as well as technical specification and standards. It will give comments, if any, within 15 days of submission of the Draft Design Documents by the JICA Consultant(s). The JICA Consultant(s) will consider these comments and incorporate them appropriately, wherever the JICA Consultant(s) consider it necessary. If no comments are submitted by the MOR by the said deadline, it will be deemed that the MOR has no comments to offer.
(10) Review and update of the Resettlement Action Plan, Environment Impact Assessment and Environmental management Plan, which were prepared under the Joint F/S. It is the MOR’s responsibility to provide necessary, accurate and appropriate data/information to JICA and the JICA Consultant(s), so as to finalize the documents listed at (2) to (4), (hereinafter collectively referred to as ''the Draft Design Documents”) and (1), (5) to (7) and (9) to (10) so that they can be utilized only for the procurement (bidding) process and construction work of the Project.
8.2 Adoption by the MOR Upon request from the relevant government authorities of Japan, JICA will set up a committee composed of experts of Japanese high speed railway (hereinafter referred to as "the Committee") to review the organization structure, the process and the GC's work for the Draft Design Documents, technical specification and standards which are developed through the Fellow-up Study and the Study. The Committee offer its review may require the JICA Consultant(s) to revise the documents. The JICA Consultant(s) will revise the documents as advised by the committee and resubmit them for the Committee's review. The Committee, when satisfied, will issue a letter to the MOR recommending the Draft Design Documents for adoption by the MOR.
“2.8 Preparation of Bidding Documents The JICA Consultant(s) will prepare the Draft Bidding Documents for each contract package in accordance with the latest version of Standard Bidding Documents under Japanese ODA Loans together with all relevant specifications, drawings and other documents, which are consisting of the following documents:-
a. Instruction to Bidders;39
b. Bid Form;
c. General Conditions of Contract;