5. Our attention was also invited to a communication
dt. 16.05.2016. It was submitted by Mr Bora that the software IPR
with Source Code on Pen-drive was handed over to the official of the
University namely the Director of B.C.U.D. It was further the
submission of Mr Bora that, in view of the meeting of the
Management Council, the decision of the Purchase Committee and
communication dt. 16.05.2016, it was the reasonable expectation of
5 Sr20WP1413.2017
the petitioner that the respondent-University would place a purchase
order with the petitioner and accordingly the petitioner would be
entitled for his monetary benefits under the purchase order. But, to
the surprise of the petitioner, the respondent - University, by
communication dt. 18.05.2016, informed the petitioner that the
subject purchase order is kept in abeyance till further orders.