Showing contexts for: construction defect in M/S.Subaya Constructions Company ... vs M/S.P & C Projects (P) Ltd on 29 April, 2024Matching Fragments
H – Programme Schedule :
39. Penalty for Defective Construction :
39.If any defect is noticed by the Employer in the construction of any portion of work/component, the Employer shall levy penalty upto 10% of te total value of the defective work as assessed by the Engineer in charge in addition to rectification of defective works at his cost.
https://www.mhc.tn.gov.in/judis
13. Clauses 39 & 42 in Part H – Programme Schedule in Section IV in Ex.C3 Main Contract between the TWAD Board and the petitioner dated 15.09.2003 reads as under:-
39.Penalty for Defective 42.Liquidated Damages Construction 39.1 If any defect is noticed by the 39.1 If any defect is noticed by the Employer in the construction of Employer in the construction of any portion of work/component, any portion of work/component, the Employer shall levy penalty the Employer shall levy penalty upto 10% of the total value of the upto 10% of the total value of the defective work as assessed by the defective work as assessed by the Engineer in charge, in addition to Engineer in charge, in addition to rectification of defective works at rectification of defective works at his cost. his cost.