Showing contexts for: consumer judgments in Peeyush Kaushik vs Orris Infrastructre Pvt. Ltd. & Anr. on 16 August, 2022Matching Fragments
The present Execution Applications have been filed by the Complainants / Decree Holders against Orris Infrastructure Pvt. Ltd. and its Directors (hereinafter referred to as the Opposite Parties/Judgment Debtors).
Brief facts leading to filing the present Execution Applications are as under:-
EA No. 24 / 2020 in CC No. 2877 of 2017 The Complainant(s) was allotted Flat No. 903 Tower 8 in the Project Greenopolis Project launched by Opposite Party / Judgment Debtor Orris Infrastructure Pvt. Ltd.Despite making a payment of substantial amount of ₹74,07,793/-, the Opposite Parties / Judgment Debtors failed to deliver the possession of the flat within stipulated period.Consequently, alleging deficiency in service on the part of the Opposite Parties / Judgment Debtors, the Consumer Complaint was filed before this Commission.This Commission vide Order dated 19.08.2019 allowed the Consumer Complaint in following terms:-
EA No. 224 / 2020 in CC No. 562 / 2018 The Complainant(s) was initially allotted Apartment No. 1001, which was subsequently cancelled and another Apartment No. 1201 was allotted on 04.07.2016 in the Project Greenopolis Project launched by Opposite Party / Judgment Debtor Orris Infrastructure Pvt. Ltd.Despite making a payment of substantial amount of ₹74,94,106, the Opposite Parties / Judgment Debtors failed to deliver the possession of the flat within stipulated period.Consequently, alleging deficiency in service on the part of the Opposite Parties / Judgment Debtors, the Consumer Complaint No. 562 / 2018 was filed before this Commission.This Commission vide Order dated 20.07.2020 allowed the Consumer Complaint in following terms:-
This Order attained finality as the Opposite Party/Judgment Debtor did not file any Appeal before the Hon'ble Supreme Court.As the Opposite Parties/Judgment Debtors failed to satisfy the Decrees/Orders dated 20.07.2020, the Complainants had filed Execution Application No. 224 / 2020 seeking enforcement of the Decree/Order as well as penalties to be imposed upon Judgment Debtors, Orris Infrastructure Ltd. and its Directors for non-compliance with the Decree/Order dated 20.07.2020.
EA No. 227 / 2020 in CC No. 546 / 2018 The original allottee booked an Apartment in the Project Greenopolis Project launched by Opposite Party / Judgment Debtor Orris Infrastructure Pvt. Ltd. for total consideration of Rs.1,03,85,680/-. Through allotment letter dated 30.08.2012 Apartment no.103 on 1st floor in Tower 12A was allotted to initial buyer & later on 21.12.2012 the same was endorsed in favour of complainant. Despite making a payment of substantial amount of ₹85,72,435/-, the Opposite Parties / Judgment Debtors failed to deliver the possession of the flat within stipulated period.Consequently, alleging deficiency in service on the part of the Opposite Parties / Judgment Debtors, the Consumer Complaint was filed before this Commission.This Commission vide Order dated 20.07.2020 allowed the Consumer Complaint in following terms:-
This Order attained finality as the Opposite Party/Judgment Debtor did not file any Appeal before the Hon'ble Supreme Court.As the Opposite Parties/Judgment Debtors failed to satisfy the Decree/Order dated 20.07.2020, the Complainants had filed Execution Application No. 227 / 2020 seeking enforcement of the Decree/Order as well as penalties to be imposed upon Judgment Debtors, Orris Infrastructure Ltd. and its Directors for non-compliance with the Decree/Order dated 20.07.2020.
EA No. 229 / 2020 in CC No. 53 / 2018 The original allotee booked an apartment No. 306 in the Project "Greenopolis" launched by Opposite Party / Judgment Debtor Orris Infrastructure Pvt. Ltd. The Opposite Party / Judgment Debtors endorsed the said apartment in favour of the complainant on 05.09.2012 along with all documents. Despite making a payment of substantial amount of ₹73,23,899, the Opposite Parties / Judgment Debtors failed to deliver the possession of the flat within stipulated period.Consequently, alleging deficiency in service on the part of the Opposite Parties / Judgment Debtors, the Consumer Complaint was filed before this Commission.This Commission vide Order dated 20.07.2020 allowed the Consumer Complaint in following terms:-