i) Interest @ 24% on materials valued at ₹25 7,50,000 lakhs lying at site for 457 days 5 Damages due to prolongation of contract from 14,00,000 27.08.2008 to 23.02.2011 6 Withheld amount 1,00,000 7 Reimbursement of testing charges 50,000 8 Reimbursement of core test charges 1,25,000 TOTAL 80,75,450

21 For Claim Nos. 7 and 8, the plaintiff submits that under Clause 17 of the Specifications and Conditions of Contract, the Digitally RICHA signed by RICHA GUSAIN defendant is liable to reimburse the testing and core test charges. GUSAIN SOLANKI SOLANKI Date:

2025.10.18 16:24:22 +0530 Reliance is also placed on the plaintiff's letter dated 23.03.2010 requesting the defendant to undertake the said tests.
r) Sanction order of 7th RA Bill dated 31.03.2010 as Ex. P-19,
s) Copy of letter dated 23.03.2010 as Ex. P-20,
t) Receipts dated 07.07.2008, 14.07.2008, 01.08.2008, 08.08.2008, 09.08.2008, 12.08.2008, 25.08.2008, 02.09.2008, 05.09.2008, 15.09.2008, 17.09.2008 and 22.09.2008 of payment CS DJ ADJ No. 515527/2016 Purna Nand vs Netaji Subhash Institute of Technology Page no. 14/36 made to Indian Testing Centre for testing charges by the plaintiff as Ex. P-21 to Ex. P-32, u) The receipt dated 27.01.2009 of payment made to Micro Engineering & Testing Laboratory for testing charges by the plaintiff as Ex. P-33,
62.9 (h) Claim No.8 - Reimbursement of core test charges of ₹1,25,000/-: The plaintiff has not produced any receipt evidencing the payment of core test charges. Conversely, the defendant has stated that it had paid ₹2,16,188/- (₹1,10,300/- to IIT, Delhi and ₹1,05,888/- to M/s. Cortex Construction Solution Private Limited) towards the core test. In the absence of documentary proof of payment by the plaintiff, no amount is payable under this head.