Showing contexts for: void contract arbitration in Swiss Timing Ltd vs Organizing Committee Commonwealth ... on 28 May, 2014Matching Fragments
23. In the aforesaid case, the designated Judge of the Punjab & Haryana High Court had refused to refer the disputes to arbitration. The High Court had accepted the plea that since the underlying contract was void, the arbitration clause perished with it. The judgment of the High Court was challenged in this Court, by filing a Special Leave Petition. Before this Court it was submitted by the appellant that the High Court treated the application under Section 11(6) of the Arbitration Act as if it was deciding a suit but without adducing evidence. Relying on SBP & Co. Vs. Patel Engineering Ltd., it was submitted that the High Court was only required to conduct a preliminary enquiry as to whether there was a valid arbitration agreement; or whether it was a stale claim. On the other hand, it was submitted by the respondents that once the High Court had found the main agreement to be void, the contents thereof including the arbitration clause are also rendered void.
25. Keeping in view the aforesaid observations made by this Court, I see no reason to accept the submission made by the learned counsel for the respondents that since a criminal case has been registered against the Chairman of the Organising Committee and some other officials of the petitioner, this Court would have no jurisdiction to make a reference to arbitration.
26. As noticed above, the concept of separability of the arbitration clause/agreement from the underlying contract has been statutorily recognised by this country under Section 16 of the Arbitration Act, 1996. Having provided for resolution of disputes through arbitration, parties can not be permitted to avoid arbitration, without satisfying the Court that it will be just and in the interest of all the parties not to proceed with the arbitration. Section 5 of the Arbitration Act provides that the Court shall not intervene in the arbitration process except in accordance with the provisions contained in Part I of the Arbitration Act. This policy of least interference in arbitration proceedings recognises the general principle that the function of Courts in matters relating to arbitration is to support arbitration process. A conjoint reading of Section 5 and Section 16 would make it clear that all matters including the issue as to whether the main contract was void/voidable can be referred to arbitration. Otherwise, it would be a handy tool available to the unscrupulous parties to avoid arbitration, by raising the bogey of the underlying contract being void.
(d) Similarly, Section 30 renders wagering contracts as void. The only exception to this is betting on horse racing. In the circumstances noted above, it may not be necessary for the Court to take any further evidence apart from reading the contract document itself. Therefore, whilst exercising jurisdiction under Section 11(6) of the Arbitration Act, the Court could decline to make a reference to arbitration as the contract would be patently void.
29. To shut out arbitration at the initial stage would destroy the very purpose for which the parties had entered into arbitration. Furthermore, there is no inherent risk of prejudice to any of the parties in permitting arbitration to proceed simultaneously to the criminal proceedings. In an eventuality where ultimately an award is rendered by arbitral tribunal, and the criminal proceedings result in conviction rendering the underlying contract void, necessary plea can be taken on the basis of the conviction to resist the execution/enforcement of the award. Conversely, if the matter is not referred to arbitration and the criminal proceedings result in an acquittal and thus leaving little or no ground for claiming that the underlying contract is void or voidable, it would have the wholly undesirable result of delaying the arbitration. Therefore, I am of the opinion that the Court ought to act with caution and circumspection whilst examining the plea that the main contract is void or voidable. The Court ought to decline reference to arbitration only where the Court can reach the conclusion that the contract is void on a meaningful reading of the contract document itself without the requirement of any further proof.