Skip to main content
Indian Kanoon - Search engine for Indian Law
Document Fragment View
Matching Fragments
document appended with e-procurement notice has been
referred to copiously by the learned counsel for the petitioner
more specifically clause 4.5(A) which spells out the
conditions/qualifications, which are to be fulfilled by the bidder.
Learned counsel while referring to clause 4.5(A) has submitted
that respondent no. 6 was awarded the work in utter disregard
and violation of the said clause as well as the other conditions,
which have subsequently been referred to by him. Mr. Gadodia
has referred to appendix-2-"Instruction to Bidders", which deals
with the work of construction of Jharkhand High Court Building
and the value of the work has been ascertained to be Rs. 133,
83,15,000/- and the quantity of work has also been enumerated
therein. It has been submitted that during the pre-bid-meeting
with respect to answering of queries, it was questioned by M/s
Ramki Infrastructure Ltd. with respect to clause 4.5 (b) of the
ITB, wherein a query was put with respect to "some works" as
any RCC Framed Building Structure to which a reply was given
that the same has to be read as any RCC Framed Government
Building Structure. It was also decided on the query made by
Ramky Infrastructure Ltd. that the pre qualification criteria of
building works executed under the private clients towards
similar work experience will not be considered. It has been
submitted that the answer to the queries made in the pre-bid-
meeting had virtually shut out the respondent no. 6 in its bid to
qualify for the work but as would be evident, the respondent no.
6 was favoured by the State ignoring the actual
requirements/qualifications and giving a complete go-bye to the
norms and procedures generally adopted and the entire
exercise goes to show the ineligibility of respondent no. 6 in
bidding for the work in question. Mr. Gadodia, learned counsel,
has in the context of pre-bid-meeting referred to clause 9.2.4 of
I.T.B and has submitted that the said clause is virtually divided
into two parts. The first is circulation/transmission of the
minutes of meetings including the text of questions raised and
response given to all the purchasers of the bidding document.
The second part of the same clause is concerned with any
modification of the bidding documents which may occur as a
result of pre-bid-meeting and which can be made through the
issue of an addendum. In reference to the said clause, it has
been submitted by the learned counsel for the petitioner that a
corrigendum was issued, in which a mention had been made
that the reply of pre-bid-query were uploaded and the other
terms and conditions remain unchanged. Learned counsel
submits that the pre-bid-meeting does not amend any terms
and conditions of the ITB but it only clarifies certain issues and
certain queries, about which there was some confusion but
which was erased during the meeting. It has been submitted
that the clarifications, which were made by the respondents-
State in the pre-bid-meeting had considerable weight as the
basic purpose of pre-bid-meeting was to clear the air about
certain misconceptions arising out of the same ITB document.
Learned counsel has also submitted that the respondent no. 6
does not qualify as it has not carried out at least one similar
work. Submission has been advanced that the term "at least
one similar work" either can be construed in a very narrow term
or be wide in its amplitude. It has been submitted that the
respondents-State has been very careful in coining the said
term to shower favoritism. Advancing his arguments, Mr.
Gadodia has submitted that prior to making a bid for
construction of Jharkhand High Court Building, the petitioner
has claimed to have constructed the International Cricket
Stadium at Dhurwa, Ranchi but the same was never a
government structure as has been clarified as one of the prime
requirements in the pre-bid-meeting. Even from the completion
certificate of International Cricket Stadium, the name of the
employer has been shown as Jharkhand State Cricket
Association, which is dehors the terms and conditions of the
bidding instruction but in spite of the apparent ineligibility of
respondent no. 6, the work was still given to respondent no. 6.
Attacking the counter affidavit filed by the respondent nos. 1 to
5, it has been submitted that paragraph 21 of the counter
affidavit does not contain any reply with respect to contention
of the petitioner on the minutes of the pre-bid-meeting and the
other clarifications which had been made. Even para 22 of the
counter affidavit does not contain any specific reply to the
averments made by the petitioner in the writ application and
merely an evasive reply has been given by the state
authorities, which goes to show their inability to defend their
illegal action in declaring the respondent no. 6 as a successful
bidder. So far as the averments made in para 33 of the counter
affidavit filed by the respondent nos. 1 to 5 is concerned, it has
been submitted that it is wrong to say on the part of the
respondents-State Authority that the clarifications, which had
been given in pre-bid-meeting does not have any overriding
effect. If that was the position, there was no necessity of
holding any pre-bid-meeting as the sole purpose of the meeting
was to clarify any misgiving any of the participants might have
had in ITB or in the bidding process. Concluding his argument
with respect to his limb of submission about non qualification of
respondent no. 6, learned counsel sums up by stating that
when the respondent no. 6 did not even fulfill the basic
eligibility criteria for participating in the technical bid, it's being
successful in the backdrop of the instances referred do suggest
that the respondent no. 6 was given the work in violation of the
terms and conditions of ITB.