Document Fragment View

Matching Fragments

CAPITAL COST

7. Clause 17 of the 2004 regulations relating to the capital cost provide as under:

17. Capital Cost: Subject to prudence check by the Commission, the actual expenditure incurred on completion of the project shall form the basis for determination of final tariff. The final tariff shall be determined based on the admitted capital expenditure actually incurred up to the date of commercial operation of the generating station and shall include capitalised initial spares subject to following ceiling norms as a percentage of the original project cost as on the cut off date:
(i) Coal-based/lignite-fired generating stations - 2.5%
(ii) Gas Turbine/Combined Cycle generating stations - 4.0% Provided that where the power purchase agreement entered into between the generating company and the beneficiaries provides a ceiling of actual expenditure, the capital expenditure shall not exceed such ceiling for determination of tariff;

[Provided further that any person intending to establish, operate and maintain a generating station may make an application before the Commission for ' in principle' acceptance of the project capital cost and financing plan before taking up a project through a petition in accordance with the procedure specified in the Central Electricity Regulatory Commission (Procedure for making application for determination of tariff, publication of the application and other related matters) Regulations, 2004, as applicable from time to time. The petition shall contain information regarding salient features of the project including capacity, location, site specific features, fuel, beneficiaries, break up of capital cost estimates, financial package, schedule of commissioning, reference price level, estimated completion cost including foreign exchange component, if any, consent of beneficiary licensees to whom the electricity is proposed to be sold etc. Provided further that where the Commission has given 'in principle' acceptance to the estimates of project capital cost and financing plan, the same shall be the guiding factor for applying prudence check on the actual capital expenditure:

18. Additional capitalisation: (1) The following capital expenditure within the original scope of work actually incurred after the date of commercial operation and up to the cut off date may be admitted by the Commission, subject to prudence check:
(i) Deferred liabilities;
(ii) Works deferred for execution;
(iii) Procurement of initial capital spares in the original scope of work, subject to ceiling specified in regulation 17;
(iv) Liabilities to meet award of arbitration or for compliance of the order or decree of a court; and
(v) On account of change in law.

Provided that original scope of work along with estimates of expenditure shall be submitted along with the application for provisional tariff.

Provided further that a list of the deferred liabilities and works deferred for execution shall be submitted along with the application for final tariff after the date of commercial operation of the generating station.

(2) Subject to the provisions of clause (3) of this regulation, the capital expenditure of the following nature actually incurred after the cut off date may be admitted by the Commission, subject to prudence check: