Skip to main content
Indian Kanoon - Search engine for Indian Law
Document Fragment View
Matching Fragments
- economic viability of these units vis - a -vis carrying out
essential maintenance works to sustain the operation of the
units for some more years.
HPGCL has proposed PLFs of 52.59%, 59.34%, 69.95% &
64.86% for PTPS units 1 to 4 respectively (overall 59.88%)
based on the average of actual PLF during the preceding three
complete years of operation. This was objected to by the
Discoms on the plea that the PLF proposed by HPGCL is not in
line with HERC Generation Tariff Regulations, 2008 and in the
past the Commission has also expressed its concern the
deterioration in PLF of HPGCL's power stations. The
Commission observes that the petitioner has quoted the order
of Jharkhand ERC in which the norms of operational
parameters have been relaxed for Patratu TPS units as the
same are 35-40 years old. The comparison is not valid as
Patratu TPS units are much older than Panipat TPS units with
derated capacity of 4x40 MW, 2x90 MW 2x105 MW &
2x110MW. It is learnt that Central Electricity Authority has
suggested to JSEB to retire six out of ten units of this plant after
finding them obsolete and mentioning any further investment on
them for revival as unviable. Moreover, Panipat TPS units 1&2
have already demonstrated PLFs of 80% & above in the
months of June to October during FY 2011-12 and PLFs of
nearly 70% can be expected from units 3 &4 as already
proposed by HPGCL for FY 2012-13. The average of PLFs of
last three years has been low due to certain forced outages of
long durations which are not expected or desired to be
repeated in future.
Page 10
Judgment in Appeal No. 108 of 2012
e. In fact, while responding to the objections raised by the
DISCOMS during the hearing before the Commission, the
Appellant had submitted as follows:
"Consideration of CERC Regulations:-
HPGCL has adhered to the Hon'ble HERC norms and the
principles adopted by the Hon'ble Commission in previous
tariff orders, in the most of the cases. Only in the cases
where the HERC norms are silent or HPGCL finds CERC
norms to be achievable even though they are more
stringent, HPGCL has referred to the norms adopted by
the Central Commission. It would be grossly inappropriate
to suggest that HPGCL has followed CERC Regulations
when they are more beneficial to HPGCL, as HPGCL has
proposed certain technical parameters in line with CERC
norms, which are more stringent than the State
Commission's norms, for instance:
"HERC has not been averse to allowing relaxed norms for the
old units provided there is a road map for improving the
parameters in a reasonable period of time. HPGCL has
proposed SHR of 3336.63 Kcal/Kwh for 110 MW PTPS units- 1
to 4 (24 to 32 years old) and 2935.19/2954.60 Kcal/Kwh for 210
MW PTPS units-5 &6 ( 10 to 22 years old). In comparison, SHR
achieved is 3035.88 at 110 MW Bhatinda TPS (33 to 37 years
old), 2472.62 at 210 MW Ropar TPS (19 to 25 years old) and
2493 at 110/195/210 MW Kota TPS (3 to 37 years old). The
proposal of the petitioner with regard to SHR of PTPS Unit 1 to
6 was objected to by the Discoms on the grounds that they are
not in line with HERC Generation Tariff Regulations, 2008. The
Discoms also referred to the observations of the Commission in
Page 19
Judgment in Appeal No. 108 of 2012
its FY 2011-12 order that 'if recommendations contained in
energy audit report of PTPS Unit 1 - 6 are implemented by
HPGCL, there is considerable scope for reduction in SHR and
bringing the same within 10% of the design heat rate. The
Commission has considered the objections of Discoms as well
as response of HPGCL on the same. As per HERC Regulation
dated 19.12.2008, the target Station Heat Rate (Kcal/kWh) has
been fixed at 2450/2410 for 300 MW & above sets with
stream/electric driven BFPs respectively and a trajectory has
been fixed for PTPS units 1-6 as under:-
With reference to section 5.3 (f & h) of National Tariff Policy
referred to by HPGCL, the Commission has been relaxing the
operating norms in the past wherever considered appropriate
and drawing a transition path over the time for achieving the
norms, but HPGCL has not taken enough steps to follow the
same. HPGCL was requested to indicate the year wise
trajectory in case of all the performance parameters wherever
they are lagging behind the approved norms so as to achieve
the operating norms as soon as possible, but HPGCL has not
given the desired trajectory and again prayed to the
Page 20
Judgment in Appeal No. 108 of 2012
Commission to appreciate the efforts taken by the HPGCL in
the past and its commitment towards the improvement of
operating performance from the existing level, considering the
vintage of the Units for which certain deviations from the norms
have been sought.