13. The informant is essentially aggrieved of the changes effected by KMRL in its tender document for procurement of standard gauge cars vide an addendum dated 17.04.2014 to the tender.

14. At the outset, it may be mentioned that the informant has directed its grievance against DMRC and has also, accordingly, alleged dominance and its abuse by DMRC in the relevant market. In this connection, it may be pointed out that as per the averments made by the informant itself the opposite party No. 2 is the project owner whereas the opposite party No. 1 is just the executing agency. In these circumstances, the entire edifice of the challenge of the informant in laying its grievance against DMRC is misconceived.