Showing contexts for: Building deviation in Highness Hotel Private Limited vs Ahmedabad Municipal Corporation & ... on 5 June, 2017Matching Fragments
The procedure for obtaining a Development Permission is specified in Regulation No. 5.1.
3.8.2. Revising a Development Permission Changes or revisions in the sanctioned design and specification of a building may be made if a Revised Development Permission is obtained before construction is undertaken on the portion of the building that deviates from the Sanctioned Design Requirements.
Revision of Development Permission shall be mandatory in the following conditions:
1. Change in Ownership
2. Increase in utilised FSI
3. Reduction in Parking area
4. Change in Orientation of the Building HC-NIC Page 9 of 25 Created On Tue Jun 06 01:24:10 IST 2017
5. Change in size or location of the Common Plot
6. Change in use of Building or part thereof For any of the above mentioned changes in a building during the course of construction, the owner should apply for a Revised Development Permission for the Building‐unit or part of Building‐unit as the case may be. The modified Development Requirements may be examined by the Competent Authority for ensuring compliance of the building to these Development Regulations. No deviations in contravention of the provisions of the act, and/or these regulations shall be permitted.