Document Fragment View
Fragment Information
Showing contexts for: revised layout in Ravikant Bhatt & Anr. vs M/S. Unitech Limited on 22 September, 2016Matching Fragments
2. The complaint has been resisted by the opposite party. It is alleged in the written version that the project Anthea Floors was a part of licensed plotted colony, namely, Nirvana Country III falling under License No.66 of 2011 dated 21.7.2011. Thus, the layout plan for the said colony had been approved on 21.7.2011. The opposite party applied for demarcation-cum-revised layout plan for Nirvana Country III on 19.9.2011. However, the said revised layout plan was not approved since Haryana Government was demanding charges, which the builders challenged before the Punjab and Haryana High Court by way of Writ Petition No.15537 of 2015.
3. As noted earlier, the opposite party had the requisite approval to the layout of the project in which the allotment was made to the complainants, the said approval having been granted way back on 21.7.2011. The opposite party submitted the revised layout plan on 19.9.2011. Despite a revised layout plan having already been submitted by that date, the opposite party did not disclose in the allotment letter issued to the complainant that they had submitted a revised layout plan for the project Anthea Floors on 19.9.2011 and the said revised plan was yet to be approved. If the opposite party wanted to develop the project only in accordance with the revised layout plan submitted on 19.9.2011, the aforesaid vital information ought to have been disclosed to the complainants at the time of booking of the flat.
The Buyer's Agreement with the complainants was executed on 20.3.2013. Even in the said Buyer's Agreement, it was not disclosed that the opposite party did not intend to act upon the previously approved layout plan and had submitted a revised layout plan to the TCPO, which was yet to be approved. Had that been disclosed to the complainants, it is quite possible that they would have not have entered into the said agreement with the opposite party since, they could not have been sure that the opposite party which was yet to receive approval to the revised layout plan, would be able to deliver possession of the flat within 36 months from the date of the Buyer's Agreement.
4. The revised layout plan, according to the opposite party could not be approved by Haryana Government since the External Development Charges (EDC) being demanded by the said Government were not acceptable to the opposite party which filed a Writ Petition before Punjab and Haryana High Court challenging the said charges. In my view, considering the contractual obligation incorporated in the Buyer's Agreement to deliver possession within 36 months from the date of the said agreement, the opposite party ought to have paid the EDC and obtained approval to the revised layout plan instead of waiting for the outcome of the Writ Petition challenging the said charges. The opposite party even after paying the EDC as demanded by the Haryana Government could have challenged the said charges and sought refund from the Government. Such a course of action, however, was not adopted by the opposite party.