Document Fragment View

Matching Fragments

2. The Petitioner No.1 of the Revision as at (A) is the Company namely, M/s. Jindal India Thermal Power Plant Limited (shortly, stated as "M/s.JITPL") arraigned as accused no.1 in the complaint filed by the Opposite Party-Company namely, M/s. Quartz Infra and Engineering Limited (shortly stated as M/s.QIEL); whereas the Petitioner Nos.2 to 5 are the Liaison Officer and Ex-Director, Director, General Manager (Accounts) and the Legal Coordinator / General Manager (Commercial & Purchasing) of the Petitioner No.1-Company who too have been arraigned as accused persons in the said complaint numbered as 1CC Case No.57 of 2018.