Skip to main content
Indian Kanoon - Search engine for Indian Law
Document Fragment View
Matching Fragments
- 12 -
NC: 2024:KHC:3194
an admitted position that the borrower did not
make the payment due and payable under the
sanctioned OTS Scheme on or before the date
mentioned in the sanctioned letter. The prayer of
the borrower for extension of nine months came
to be rejected as far as back on 16.05.2018 and
the borrower was directed to make the payment
of Rs.2.52 crores by 21.05.2018, the borrower
failed to make the payment.
20. At this stage, it is required to be
noted that during the pendency of the writ
petition there were as many as three different
OTS floated by the Bank and the Bank offered the
Respondent-borrower to settle the outstanding
payment under the OTS Scheme. However, the
borrower did not opt for any of the scheme.
21. By the impugned Judgment and Order
the High Court has granted further six weeks'
time from 10.03.2022 which would be beyond
even the time prayed by the borrower in the year
2018. As observed above earlier period of 8 to 9
months was sought in the year 2018 and by the
impugned judgment and order the borrower has
got time upto May, 2022.
22. Even otherwise as rightly submitted
on behalf of the Bank directing the Bank to
reschedule the payment under OTS would
tantamount to modification of the contract which
can be done by mutual consent Under Section 62
of the Indian Contract Act. By the impugned
judgment and order rescheduling the payment
under the OTS Scheme and granting extension of
time would tantamount to rewriting the contract
which is not permissible while exercising the
powers Under Article 226 of the Constitution of
India.
23. It is required to be noted that under
the OTS Scheme which was originally sanctioned
in the year 2017 the borrower was required to
- 13 -
NC: 2024:KHC:3194
pay Rs. 10,53,75,069.74 against the outstanding
of Rs. 13,99,89,273.99. Therefore, under the
original sanctioned OTS Scheme the borrower was
getting the substantial relief of approximately 3
crores. The Bank agreed and accepted the OTS
offer on the terms and conditions mentioned in
the letter dated 21.11.2017. In the sanctioned
letter dated 21.11.2017 it was specifically
mentioned in Clause (iv) that the entire payment
under the OTS Scheme was to be made by
21.05.2018, otherwise OTS would be rendered
infructuous. Therefore, borrowers were bound to
make the payment as per the sanctioned OTS
Scheme. Therefore, the High Court ought not to
have granted further extension de hors the
sanctioned OTS Scheme while exercising the
powers Under Article 226 of the Constitution of
India.
24. The submissions on behalf of the
borrower that in case of some other borrowers
the time was extended is concerned, the same is
neither here nor there. The Bank mutually can
agree to extend the time which is permissible
Under Section 62 of the Indian Contract Act. The
borrower as a matter of right cannot claim that
though it has not made the payment as per the
sanctioned OTS Scheme still it be granted further
extension as a matter of right. There cannot be
any negative discrimination claimed. The
borrower has to establish any right in their favour
to claim the extension as a matter of right.