Document Fragment View
Fragment Information
Showing contexts for: Imperia Structure in Baljor Singh Jakhar vs M/S. Imperia Structure Ltd. on 11 October, 2021Matching Fragments
36. All the Complainants are entitled to execute the orders passed by the Commission in their favour, in accordance with law."
Respectfully following the ratio of the Judgment passed by the Hon'ble Supreme Court in the case of M/s. Imperia Structures Ltd. (supra), the Opposite Party Developer is directed to refund the entire amounts deposited by the Complainants alongwith simple interest @9% p.a. from the respective dates of deposits till the date of actual payment together with costs of ₹50,000/- to be paid to each of the Complainants. Consequently, all the Consumer Complaints are partly allowed in following terms:-