Document Fragment View
Fragment Information
Showing contexts for: contract workers in Patta Rama Apparow vs Ministry Of Steel on 19 October, 2016Matching Fragments
CIC/CC/A/2014/000139-YA Information sought and background of the case:
Vide RTI application dated 19.02.2014, the appellant sought information under 5 points regarding an accident which took place at BF1 by loco motive no 8. The query was as follows:
No. of Contract workers injured in the accident took place by locomotive no. 8 on 11th February, 2014 along with their names, whether anybody has died, the name of the Contractor who has paid 6.5 lakhs to the deceased employee and the details of Safety Committee Report along with a copy.
CIC/CC/A/2014/000694-YA (Same as file number CIC/CC/A/2014/000139-YA) Information sought and background of the case:
Vide RTI application dated 19.02.2014, the appellant sought information under 5 points regarding an accident which took place at BF1 by loco motive no 8. The query was as follows:
No. of Contract workers injured in the accident took place by locomotive no. 8 on 11th February, 2014 along with their names, whether anybody has died, the name of the Contractor who has paid 6.5 lakhs to the deceased employee and the details of Safety Committee Report along with a copy.
CIC/CC/A/2014/002103-YA Information sought and background of the case:
Vide RTI application dated 26.02.2014, the appellant sought information under 6 points regarding 500 residential contract labour of VSP.
Reasons mentioned in the agreement entered between Management of Steel Plant with the leaders for recruitment of 5 hundred DP contract workers (while going on hunger strike) along with the copy of agreement, no. of DP Contract workers allotted to each department out of the above 5 hundred DP contract worker along with copy of Order, no. of DP Contract workers allotted to Traffic department among the above, list of contract workers out of the above DP Contract workers allotted to Traffic department along with their section and period for which they are working in the sections, list of contract workers allotted to Traffic department along with their section and working in the same section, whether the DP contract workers allotted to Traffic department will be transferred to other section without keeping them at one section.