Showing contexts for: procured document in M/S. Gayatri-Dlf Consortium & Ors. vs National Highways Authority Of India & ... on 10 March, 2011Matching Fragments
(a) of clause 2.20.7 if the bid is a non-responsive bid, the damages are restricted to 5 per cent of the value of the bid security. The question, thus, arises whether in case of a non-
responsive bid could it be said that 5 per cent of the value of the bid security was the genuine pre-estimate of damages?
51. It must be borne in mind that the stage for submission of the RFP is the second stage in the tendering process. There is an earlier scrutiny in pursuance of the RFQ submitted by the parties in terms whereof certain parties are enlisted for submitting the RFP. At the stage of the RFP a sum of `3.00 lakh is paid to procure the documents. This amount cannot be the cost of the form but is really a pre-estimated cost of processing the RFP. A non-responsive bid is one where at the threshold on the opening of the bid it is found to be defective on one account or the other and is, thus, shut out from the process of scrutiny. This can have no co-relation with the value of the bid which would be the eventuality even if 5 per cent of the bid amount is encashed.