Showing contexts for: conditional stay in Power Mech Projects Ltd. vs Sepco Electric Power Construction ... on 17 February, 2020Matching Fragments
(2) Where an application to set aside the arbitral award has been under section 34, the filing of such an application shall not by itself render that award unenforceable, unless the Court grants an order of stay of the operation of the said arbitral award in accordance with the provisions of sub-section (3), on a separate application made for that purpose.
(3) Upon filing of an application under subsection (2) for stay of the operation of the arbitral award, the Court may, subject to such conditions as it may deem fit, grant stay of the operation of such award for reasons to be recorded in writing:
XXX XXX XXX
56....The anomaly, therefore, of Order XLI Rule 5 of the CPC applying in the case of full-blown appeals, and not being OMP(I)(COMM) 523/2017 applicable by reason of Section 36 of the Arbitration Act, 1996 when it comes to review of arbitral awards, (where an appeal is in the nature of a rehearing of the original proceeding, where the chance of succeeding is far greater than in a restricted review of arbitral awards under Section 34), is itself a circumstance which militates against the enactment of Section 87, placing the amendments made in the 2015 Amendment Act, in particular Section 36, on a backburner. For this reason also, Section 87 must be struck down as manifestly arbitrary under Article 14. The petitioners are also correct in stating that when the mischief of the misconstruction of Section 36 was corrected after a period of more than 19 years by legislative intervention in 2015, to now work in the reverse direction and bring back the aforesaid mischief itself results in manifest arbitrariness. The retrospective resurrection of an automatic-stay not only turns the clock backwards contrary to the object of the Arbitration Act, 1996 and the 2015 Amendment Act, but also results in payments already made under the amended Section 36 to award-holders in a situation of no-stay or conditional-stay now being reversed. In fact, refund applications have been filed in some of the cases before us, praying that monies that have been released for payment as a result of conditional stay orders be returned to the judgment-debtor.
57. Also, it is important to notice that the Srikrishna Committee Report did not refer to the provisions of the Insolvency Code. After the advent of the Insolvency Code on 01.12.2016, the consequence of applying Section 87 is that due to the automatic-stay doctrine laid down by judgments of this Court - which have only been reversed today by the present judgment - the award-holder may become insolvent by defaulting on its payment to its suppliers, when such payments would be forthcoming from arbitral awards in cases where there is no stay, or even in cases where conditional stays are granted. Also, an arbitral award-holder is deprived of the fruits of its award - which is usually obtained after several years of litigating - as a result of the automatic-stay, whereas it would be faced with immediate payment to its operational OMP(I)(COMM) 523/2017 creditors, which payments may not be forthcoming due to monies not being released on account of automatic-stays of arbitral awards, exposing such award-holders to the rigors of the Insolvency Code...."