Showing contexts for: dredging in M/S.Tuticorin Port Trust vs Jan De Nul Dredging India Pvt.Ltd on 10 September, 2019Matching Fragments
e. Whether the Claimant dredged the area in front of berth No.9 from the level - 7.30 to -11.90 m or whether Dharti Dredging Infrastructure dredged that area from -7.30 m to
-11.90 m?
5 Contractor’s Equipment Idle due to Traffic within Port Entrance.
5 Whether the Claimant is entitled to its claim for idling for contractor’s equipment due to traffic outside port entrance?
30. According to the 1strespondentas per the intimation given to the appellant on 21.11.2010, the following equipment’s were to be used and employed for dredging purpose.
I. Cutter Suction Dredger: For dredging of the New Basin and the Existing Basin;
II. Cutter Suction Dredger and Split Open Barge: For Dredging of Navigational Channel;
III. Back Hoe Dredger: For dredging the areas alongside the berths.
31. It is submitted that as per Clause 42 of Section II of the License ____________ https://www.mhc.tn.gov.in/judis/ Page No 37 of 87 Agreement, the whole work including pre-dredge survey, mobilisation, post-dredge survey and demobilisation has to be completed within a period of 14 months from the 60th day of the work order/letter of acceptance or actual date of commencement of work whichever is earlier as stated in the Instruction to Tender and in accordance with provisions of Clause 47 with the time stated in the Appendix to Tender for the whole of the Works calculated from the Commencement Date, or such extended time as may be allowed under Clause 43.1.
77. As per clause 44.1, Section III-Particular Specification, before any plant is brought to the site, a detailed Dredging programme with details of Dredging Zones and dredger workplans, time period for each zone, particulars of dredger’s, and other equipment which the 1strespondent proposed to use was to be submitted to the Engineer for approval.
78. Clause 44.2, Section-III stipulated the Method of Execution. It stipulates that before the commencement of the Dredging work, the 1strespondent shall submit a detailed method statement to the engineer of the appellant for approval.