Skip to main content
Indian Kanoon - Search engine for Indian Law
Document Fragment View
Matching Fragments
i. To answer these questions, we need to analyse the
MSPGCL Judgement, Impugned Order, Tariff Regulations
2009 and other relevant material placed on record before
this Tribunal. Let us first examine the findings of this
Tribunal in the MSPGCL Judgement. The relevant extract
of the same is reproduced below:
"7.3. The Tariff Regulations of the State Commission do
not specify any benchmark norms for prudence check of
the capital cost. The Central Commission Tariff
Regulations, 2009 for prudence check of capital cost
provide for the following:
"(2) The capital cost admitted by the Commission
after prudence check shall form the basis for
determination of tariff:
Provided that in case of the thermal generating
station and the transmission system, prudence
check of capital cost may be carried out based
on the benchmark norms to be specified by the
Commission from time to time:
Page 16 of 52
A. No. 175 of 2015 & IA No. 647 of 2017
Provided further that in cases where benchmark
norms have not been specified, prudence check
may include scrutiny of the reasonableness of
the capital expenditure, financing plan, interest
during construction, use of efficient technology,
cost over-run and time over-run, and such other
matters as may be considered appropriate by the
Commission for determination of tariff".
The Central Commission has also not laid down any
benchmark norms for prudence check, but its
Regulations only indicate the area of prudence check
including cost overrun and time overrun. The State
Commission has not examined the reasons for delay in
commissioning of the project and attributed the entire
time overrun related cost with respect to the
contractual schedule agreed with BHEL to the
Appellant. In our view, this is not prudence check. In
the absence of specific regulations, we will now find
answer to the question raised by us relating prudence
check of time overrun related costs.