Document Fragment View
Fragment Information
Showing contexts for: procured document in Haryana Power Purchase Centre vs Sasan Power Ltd on 6 April, 2023Matching Fragments
1.3 The objective of the bidding process is to select a SuccessfulBidder for development of the Project as per the terms of the RFP. The Project will have a Contracted Capactiy of minimum of 3500 MW and maximum of 3800 MW in accordance witht he terms of the PPA. The Selected Bidder shall purchase the entire shareholding of the Authorised Representative CIVIL APPEAL NO. 11826 OF 2018 etc. from PFC and its nominees in accordance with Share Purchase Agreement and cause the Seller to enter into the RFP Project Documents. The Selected Bidder shall be responsible for ensuring that the Seller undertakes development, finance, ownership, design, engineering procurement, construction, commissioning, operation and maintenance of the Project as per the terms of the RFP Project Documents. The Selected Bidder shall also ensure:
12.5 After thoughtful consideration of the submissions made by the learned counsel for CIVIL APPEAL NO. 11826 OF 2018 etc. the Appellant and the Respondents and the findings of the Central Commission, we find that while the responsibility of carrying out due diligence before bidding and verifying the correctness of information provided in the bid documents rested with the bidders, at the same time, Respondent procurers cannot justify providing grossly erroneous report on Water Intake System taking shelter under the disclaimer in the bid document. As a matter of fact, the water availability for a thermal power station of this magnitude on regular, reliable and uninterrupted basis is essential and is a vital input for successful operation of the plant. It is noticed that the report of WAPCOS supplied to bidders at the time of bidding was deficient in ensuring adequate water supplies throughout the year uninterrupted and if the same would have been taken for construction and implementation, the same could have resulted into huge loss to the Respondent procurers being deprived of power supply for some period of the year due to less/ non-availability of water during the lean period. It is not in dispute that Sasan UMPP is supplying power to the Respondent procurer at one of the most competitive tariff in the country. It is noted from the contentions of the Respondent procurers that such an issue has not been dealt with either in the PPA or in the competitive bidding guidelines issued by Ministry of Power under Section 63 of the Act, however, in view of the criticality of such situation, we opine that the matter needs afresh re-look for suitable redressal. While the Central Commission has correctly concluded that it does not qualify as change in law under CIVIL APPEAL NO. 11826 OF 2018 etc. Articles 13.1.1 of the PPA, it, however, needs to be addressed on the basis of settled principles of law and equity also, in the light of the Hon’ble Supreme Court findings in its judgment at Para 19 in Energy Watchdog vs. CERC dated 11.04.2017. Thus, we are of the considered view that this issue involving substantial additional expenditure basically arising out of erroneous report of the consultants needs to be re-examined afresh by the Central Commission. Hence, this issue is answered in favour of the Appellant.” (18) In regard to the complaint relating to the O.M. dated 17.06.2011 forming change in law, we note the following findings: