e) To operate the activity without valid consent to operate of the Board and applying after lapse of validity period.

Cost of Violation:-

Red Category- 5 times of one term consent fee X no. of years of violation* Orange Category- 3 times of one term consent fee X no. of years of violation* Green Category- 1 times of one term consent fee X no. of years of violation* * Calculations of number of years shall be calculated on the basis of number of days of non- compliance. Copy of the said circular is attached as Annexure- V. Considering the period when PP has started construction activities without obtaining CTE from MPCB i.e. as it is evident from the 1 st plinth checking certificate was issued vide, dated 25/05/2007 by PMC as per the first Layout Sanctioned vide no. DPO/2795/IV/322, dated 04/07/2006 for total potential FSI with TDR of 20,101.5 sq- m, which is beyond 20,000 sq-m issued by PMC till the date of obtaining CTE from MPCB i.e. till 02/12/2009. Besides considering the aforesaid period of violation for starting the construction activities without obtaining CTE from MPCB, the joint committee recommends considering the period of violation for not obtaining valid CTO i.e. when PP has not applied and obtained renewal of CTO from time to time from MPCB. Accordingly, the total period of violation is tabulated as below:
S. Period of violation No. of Remarks Capital Penal fees Penal fees no days of investmen calculatio . violatio t (CI) in n n Crore & consent fees 1 25/05/2007 31/07/200 433 Starting CI- 38 Orange 1,77,945.2 (date of 8 constructio crore category = 0 1st plinth (till date of n activities Consen 3 times of checking application without t Fees- one term certificate for CTE). obtaining 50000/ consent PCC Whereas CTE from - fee X no.
     obtained      CTE was              MPCB.                      of years of
     from PMC)     granted on                                      violation
                   02/12/2009                                      =3 X50000


  2    01-01-2012     11/10/201 649         Operation of     CI- 38.19    Orange         4,00,068.4

       (starting     (till date of         the              crore        category =
       date of       application           residential      consent      3 times of
       lapse of      for renewal           building         Fees-        one term
       CTO,          of CTO).              project          75000/-      consent
       which was Whereas                   without valid                 fee X no.
       valid till    renewal of            CTO from                      Of years of
       31/12/2011 CTO was                  MPCB.                         violation
       )             granted on                                          =3 X75000


                     and valid
                     up to
                     31/12/201

                     .
3    01-01-2015      04/04/201 93         Operation of     CI- 61.22    Orange         76,438.35

     (starting       (till date of        the              crore        category =
     date of         application          residential      Fees-        3 times of
     lapse of        for renewal          building         100000/-     one term
     CTO,            of CTO).             project                       consent
     which was       Whereas              without valid                 fee X no.
     valid till      renewal of           CTO from                      Of years of
     31/12/2014      CTO was              MPCB.                         violation
     )               granted on                                         =3
                     09/11/201                                          X100000


                     up to
                     31/12/201

                     .
 Total no. of days of violation: 1,175                                   Total          6,54,452.04
                                                                         Penal fees
 4    01-01-2017 06/07/202        1,647    Operation of     CI- 61.22    Red            22,56,164.3

      (starting  (till date of             the           crore           category =     8
      date of    Hon‟ble                   residential   Fees-           5 times of
      lapse of   NGT                       building      100000/-        one term
      CTO,       order                     project                       consent
      which was dated,                     without valid                 fee X no.
      valid till 06/07/202                 CTO from                      Of years of

      31/12/2016 )                         MPCB.                         violation
      )                                                                  =5
                                                                         X100000

 Total no. of days of violation: 1,647                                   Grand      29,10,616.4
                                                                         Total      2
                                                                         Penal fees
Thus, the total Penal charges as above as per provisions of penal fees for occupiers violating consent regime prescribed under the Water (Prevention and Control of Pollution) Act, 1974 and the Air (Prevention and Control of Pollution) Act, 1981 i.e. without obtaining CTE & CTO from MPCB works out to be Rs.

29,10,616/- (Rupees Twenty-nine lakh- Ten Thousand Six Hundred Sixteen Only).