Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 11, Cited by 52]

Supreme Court of India

Vedanta Limited vs Shenzhen Shandong Nuclear Power ... on 11 October, 2018

Equivalent citations: AIR 2018 SUPREME COURT 4773, 2019 (11) SCC 465, AIRONLINE 2018 SC 702, (2019) 1 CAL HN 26, (2018) 14 SCALE 3, (2018) 253 DLT 105, (2018) 4 BANKCAS 361, (2018) 4 CURCC 84, (2018) 4 KER LJ 712, (2018) 4 RECCIVR 770, (2018) 6 ARBILR 163, (2019) 1 CLR 322 (SC), (2019) 2 MAD LW 464, AIR 2019 SC (CIV) 145

Author: Indu Malhotra

Bench: Indu Malhotra, Rohinton Fali Nariman

                                                                             “REPORTABLE”

                                  IN THE SUPREME COURT OF INDIA
                                   CIVIL APPELLATE JURISDICTION


                                   CIVIL APPEAL NO.10394 OF 2018

                              (Arising out of SLP (Civil) No. 25819 of 2018)



         Vedanta Ltd.                                                                …Appellant


                                                     Versus


         Shenzen Shandong Nuclear
         Power Construction Co. Ltd.                                                  …Respondent




                                                 J U D G M E N T 


         INDU MALHOTRA, J.

Leave granted.

1. The   present   Special   Leave   Petition   has   been   filed   to Signature Not Verified Digitally signed by ANITA MALHOTRA challenge the judgment and order dated 30 th  August, Date: 2018.10.11 17:14:37 IST Reason: 2018 passed by the Delhi High Court in an Appeal filed 1 under Section 37 of the Arbitration & Conciliation Act, 1996 [hereinafter referred to as “the said Act”].

2. The factual matrix of the present case, briefly stated, is as under: 

2.1 On   22nd  May   2008,   the   Appellant   and   the Respondent­Company   entered   into   four   inter­ related   contracts   for   the   construction   of   a   210­ MW Co­Generation Power Plant, viz.: ­ i. Offshore Engineering and Technical Services Contract ii. Offshore Supply Contract iii. Onshore   Services   and   Construction Contract iv. Onshore Supply Contract These   contracts   are   hereinafter   collectively referred to as the ‘EPC Contracts’. 2.2 Each   of   the   four   contracts   contained   an Arbitration   Clause   which   is   identically   worded, which reads as under:
“Article 10 ARBITRATION  10.1 The   parties   hereto   shall endeavor   to   settle   all   disputes   and 2 difference relating to and/or arising out of the Contract amicably. 10.2 In   the   event   of   the   parties failing   to   resolve   any   dispute amicably the same shall be referred to Arbitration in accordance with the Arbitration   &   Conciliation   Act   1996 with   all   modifications   and   re­ enactments   thereto,   as   is   prevalent in India. Each party shall be entitled to   nominate   an   Arbitrator   and   the two   Arbitrators   so   nominated   shall jointly   nominate   a   third   presiding Arbitrator. The Arbitrators shall give a reasoned award. 
10.3 The place of arbitration shall be Mumbai   and   the   language   of   the arbitration shall be English. 10.4 The   parties   further   agree   that any arbitration award shall be final and binding upon the parties. 10.5 The   parties   hereto   agree   that the Supplier shall be obliged to carry out its obligations under the Contract even   in   the   event   a   dispute   is referred to Arbitration. It is clarified that   the   purchaser   shall   be   entitled to   retain   any   sum   or   portion   of Contract   Price   which   has   become due and payable, for any unfinished works   or   any   subject   matter   under arbitration.” 3 2.3 The Governing law of the Contracts is the Law of India. The relevant Clause is set out herein below for ready reference:
“ Article 12 GOVERNING   LAW   AND JURISDICTION  12.1 This contract shall be construed in accordance with and governed by the laws of India and in the event of any   litigation   the   courts   in   India shall be exclusive jurisdiction. ” 2.4 The   EPC   Contracts   contained   a   termination clause which reads as under :
“35.2.1­ The Purchaser may suspend the work in whole or in part at any time   by   giving   Supplier   notice   in writing   to   such   effect   stating   the nature, the date and the anticipated duration   of   such   suspension.   On receiving   the   notice   of   suspension, the Supplier shall stop all such work which the Purchaser has directed to be suspended with immediate effect. The   Supplier   shall   continue   to perform   other   work   in   terms   of   the Contract   which   the   Purchaser   has not   suspended.   The   Supplier   shall resume   the   suspended   work   as expeditiously   as   possible   after receipt   of   such   withdrawal   of suspension notice.
4
35.2.2­   During   suspension,   the Supplier   shall   be   entitled   to   receive from the Purchaser a Variation Order covering reasonable costs if any due to   suspension   and   appropriate adjustment for Completion Schedule, and   other   terms   and   conditions   of this Contract. 
35.2.3­ If such suspension continues for more than 180 (one hundred and eighty)   days,   at   the   end   of   the period,   the   Supplier   shall   be   by   a further   30   (thirty)   days   prior   notice, entitled   to   terminate   the   Contract and   Purchaser   shall   pay   to   the Supplier 105% (one hundred and five percent)   of   the   cost   incurred   by   the Supplier   till   the   date   of   termination as   compensation   after   adjusting payments   already   made   till   the termination.   No   consequential damages   shall   be   payable   by   the Purchaser to the Supplier in the event of such suspension.”  (Emphasis supplied) 2.5 The EPC Contracts are entered into between the Petitioner   herein   an   Indian   Company,   and   a company incorporated in the People’s Republic of China.   The   arbitration   between   these   parties   is an   international   commercial   arbitration,   having its seat in India, which would be governed by Part I   of   the   1996   Act.   The   termination   clause 5 provided   that   in   the   event   of   termination,   the Purchaser shall pay 105% of the cost incurred by the Supplier as compensation. The EPC contracts did   not   contain   any   provision   on   payment   of Interest.
2.6 Disputes   arose   between   the   parties,   which resulted in the termination of the EPC Contracts by the Respondent vide notice dated 25.02.2011.

The Respondent called upon the Petitioner herein to pay the outstanding dues as mentioned in the said notice. 

2.7 The   Respondent­Claimants   invoked   the Arbitration Clause  vide  Notice dated 18.04.2012. The disputes emanating out of the EPC contracts were   referred   to   arbitration   by   a   three­member tribunal   in   terms  of  the  agreement   between   the parties. At the first sitting of the arbitral tribunal on 17.10.2012, the parties mutually agreed to a change   of   the   seat/place   of   arbitration   from Mumbai to New Delhi. 

6 2.8 The   Claimant­Respondent   herein   raised   various Claims   in   multiple   currencies   amounting  to   Rs. 4,472,106,315;   US   $   2,380,000;   and   EUR 121,723,214   along   with  pendent   lite  and   future Interest @ 18% p.a. 2.9 The   present   Appellant   filed   a   Counter   Claim amounting   to   Rs.   2458,34,89,367   along   with Interest   @18%   p.a.   for   determination   before   the arbitral tribunal.

2.10 The   arbitral   tribunal   passed   a   detailed   Award dated 09.11.2017, wherein the Tribunal awarded the following amounts:

“ 134. Thus, in light of the aforesaid, the   following  amounts   are   awarded in   favour   of   the   Claimant   and   the Respondent is liable to pay the same to   the   Claimant   within   a   period   of 120   days   from   the   date   of   this award:
I.  Under the First Claim:
a) Rs.   46,71,41,942/­   and   Euro 23,717,437; and
b) Rs. 12,19,69,047   II.  Under the Second claim:
a) Rs. 25,47,325/­; and
b) Rs. 6,06,707/­ 7
c) Rs. 1,31,10,990/­
135. The aforesaid amount shall be payable   along   with   interest   at   the rate of 9% from the date of institution of   the   present   arbitration proceedings   provided   the   amount   is paid/deposited   within   120   days   of the award.
136. In case the respondent fails to pay   the   aforesaid   amounts   within 120   days   from   the   date   of   the Award, the claimant shall be entitled to further interest at the rate of 15% till   the   date   of   realization   of   the amount.

137.   Considering   the   overall   facts and   circumstances   of   the   case   and the   expenditure   incurred   in   the arbitration proceedings, we consider it   appropriate   to   award   Rs.

50,00,000.00/­   (Rupees   Fifty   Lakh) towards costs and legal expenses to the claimant, which according to us would meet the ends of justice. The claim   of   payment   of   cost   of   the Respondent is rejected.” The   arbitral   tribunal   in   the   Award   granted   a part   of   the   First   Claim   in   INR,   while   the   other component was awarded in EUR. The claim made in   US   $   was   rejected.   The   arbitral   tribunal adopted   a   dual   rate   of   Interest.   If   the   amounts awarded   were   paid   within   120   days’   from   the 8 passing   of   the   Award,   the   awarded   sum   would carry   a   9%   rate   of   Interest   on   both   the components   of   the   Award   i.e.   the   amounts payable in INR and EUR. However, if the awarded amounts   were   not   paid   within   120   days’,   the arbitral tribunal imposed a higher rate of further Interest @ 15% till the date of realization of the amount.

The   arbitral   tribunal   also   awarded   Rs. 50,00,000   (Fifty   Lakhs   Rupees)   towards   Costs and Legal Expenses to the Claimant/Respondent herein.

The   arbitral   tribunal   rejected   the   Counter­ Claims filed by the Appellant/Award­Debtor. 2.11 Aggrieved   by   the   said   Award,   the   present Appellant   filed   Objections   under   Section   34 before   the   Delhi   High   Court   which   came   to   be rejected vide Order dt. 12.02.2018. 2.12 Aggrieved   by   the   judgment   of   the   Single   Judge, the Appellant award­debtor filed an Appeal before 9 a Division Bench of the Delhi High Court under Section   37   of   the   said   Act.   The   Division   Bench dismissed the Appeal vide Order dt. 30.08.2018.  2.13 Aggrieved by the judgment of the Division Bench, the   Appellant   has   preferred   the   present   Special Leave Petition. 

At   the   time   of   arguments,   the   Appellant restricted   the   challenge   to   the   rate   of   Interest awarded by the arbitral tribunal.

The challenge on the Interest awarded by the Tribunal is being considered in the peculiar facts and  circumstances of the present case, and the specific clauses of the Contracts in question. 

3. ‘Interest’ is defined as “the return or compensation for the use or retention by one person for a sum of money belonging to or owned by any reason to another” 1. In essence, an award of Interest compensates a party for its   forgone   return   on   investment,   or   for   money withheld without a justifiable cause.  The   current   practice   of   awarding   Interest   in international   commercial   arbitrations   is   riddled   with 1 32 HALSBURY’S LAWS OF ENGLAND para 106 (4th Ed., 1980) 10 inconsistencies, and is criticized for lack of uniformity In   international  contracts,   there   is   no   consensus   on the method or rate of awarding Interest. 

4. In   an   international   commercial   arbitration,   in   the absence   of   an   agreement   between   the   parties   on Interest,   the   rate   of   Interest   awarded   would   be governed by the law of the Seat of arbitration. 

The rate of interest awarded must correspond to the currency in which the award is given, and must be in conformity with the laws in force in the lex fori.

5. In   the   present   case,   the   international   commercial arbitration having its seat in India, the rate of interest to   be   awarded   must   be   in   accordance   with   the Arbitration and Conciliation Act, 1996Section   31(7)   of   the   1996   Act   which   provides   for Interest, is set out herein below for ready reference:

“31. Form and content of arbitral award— (7)…
(a)  Unless   otherwise   agreed   by   the parties,   where   and   in   so   far   as   an arbitral award is for the payment of 11 money,   the   arbitral   tribunal   may include   in   the   sum   for   which   the award is made interest, at such rate as it deems reasonable, on the whole or   any   part   of   the   money,   for   the whole   or   any   part   of   the  period between the date on which the cause of   action   arose   and   the   date   on which the award is made.

[(b) A sum directed to be paid by an arbitral   award   shall,   unless   the award   otherwise   directs,   carry interest  at  the rate  of two per cent, higher   than   the   current   rate   of interest   prevalent   on   the   date   of award, from the date of award to the date of payment. 

Explanation   –   The   expression “current   rate   of   interest”   shall   have the same meaning as assigned to it under   clause   (b)   of   section   2   of   the Interest Act, 1978 (14 of 1978).] (Emphasis supplied) Section   31(7)   is   in   two   parts:   sub­section   (a) pertains to the award of Interest for the  pre­reference and  pendente   lite  period,   which   is   subject   to   the agreement between the parties. This would be evident from   the   opening   words   of   Section   31(7)(a)   –   ‘unless otherwise agreed by the parties’. Absent an agreement between   the   parties,   the   arbitral   tribunal   has   the discretion   to   award   interest;   as   it   deems   reasonable. 12 Interest may be awarded either on the whole, or any part of the sum awarded.

Section   31(7)(b)   pertains   to   the   post­award   period i.e.   from   the   date   of   the   award   to   the   date   of realization, and is not subject to party autonomy or an agreement   between   the   parties.   This   would   be apparent   from   the   manner   in   which   clause   (b)   of   S. 31(7) is framed. The phrase “unless otherwise agreed by   the   parties”   is   absent   from   this   provision.   The statutory rate of Interest is 2% higher than the current rate of Interest prevalent on the date of the award.

6. The discretion of the arbitrator to award interest must be   exercised   reasonably.   An   arbitral   tribunal   while making   an   award   for   Interest   must   take   into consideration a host of factors, such as: (i) the ‘loss of use’  of   the   principal   sum;   (ii)   the   types   of   sums   to which the Interest must apply; (iii) the time period over which   interest   should   be   awarded;   (iv)   the internationally prevailing rates of interest; (v) whether simple or compound rate of interest is to be applied; 13

(vi)   whether   the   rate   of   interest   awarded   is commercially   prudent  from  an  economic  stand­point;

(vii)   the   rates   of   inflation,   (viii)   proportionality   of   the count   awarded   as   Interest   to   the   principal   sums awarded.

On   the   one   hand,   the   rate   of   Interest   must   be compensatory as it is a form of reparation granted to the   award­holder;   while   on   the   other   it   must   not   be punitive, unconscionable or usurious in nature.  Courts may reduce the Interest rate awarded by an arbitral   tribunal   where   such   Interest   rate   does   not reflect the prevailing economic conditions 2  or where it is nor found reasonable3, or promotes the interests of justice4.

7. During the course of hearing, a suggestion was made to   apply   Interest   in   accordance   with   LIBOR   plus   a margin (between 1 to 3%). 

2 IOC v. Lloyds Steel Industries Ltd 2007­ (4) Arb LR 84 (Delhi) @ Pg. 103 3 (2009) 17 SCC 296  4 FCI v. AM Ahmed AIR 2007 SC 829 14 LIBOR   is   an   average   interest   rate   calculated   from time to time, based on inputs given by major banks in London   as   to   their   interest   rates.   Under   the   LIBOR regime, banks give details vis­a­vis actual interest rate that they are paying, or would be required to pay for borrowing from other banks. LIBOR is a 3­month rate which has been adopted in some cases of a breach of contract (or other obligation)5. 

8. In the present case, the arbitral tribunal has adopted a dual rate of Interest in the Award. The Award directs payment of Interest @ 9% for 120 days post award; if the amount awarded is not paid within 120 days’, the rate   of   Interest   is   scaled   up   to   15%   on   the   sum awarded. 

The   dual   rate   of   Interest   awarded   seems   to   be unjustified.   The   award   of   a   much   higher   rate   of Interest after 120 days’ is arbitrary, since the Award­ debtor   is   entitled   to   challenge   the   award   within   a maximum period of 120 days’ as provided by Section 5  Gisele Stephens–Chu & Joshua Kelly, Awards of Interest in International Arbitration: 

Achieving Coherence Through Purpose, Indian Journal of Arbitration Law, Volume 7, Issue  1 (July 2018) 15 34(3)   of   the   1996   Act6.   If   the   award­debtor   is   made liable to pay a higher rate of Interest after 120 days, it would foreclose or seriously affect his statutory right to challenge the Award by filing objections under Section 34 of the said Act. 
9. The imposition of a high rate of interest @ 15% post­ 120 days is exorbitant, from an economic standpoint, and   has   no   co­relation   with   the   prevailing contemporary   international   rates   of   Interest.   The Award­debtor   cannot   be  subjected   to   a   penal   rate   of interest, either during the period when he is entitled to exercise   the   statutory   right   to   challenge   the   Award, before   a   Court   of   law,   or   later.   Furthermore,   the arbitral tribunal has not given any reason for imposing a 15% rate of Interest post 120­days. 
10. The Petitioner in his Written Submissions submitted a chart which shows that the Interest component of the

6  Section 34 (3) –   An application for setting aside may not be made after three months have elapsed from the date on which the party making that application had received the arbitral award or, if a request had been made under section 33, from the date on which that request had been disposed of by the arbitral tribunal: Provided that if the Court is satisfied   that   the   applicant   was   prevented   by   sufficient   cause   from   making   the application within the said period of three months it may entertain the application within a further period of thirty days, but not thereafter. 16 Award   amounts   to   almost   50%   of   the   sum   awarded.

The grant of 15% Interest is excessive and contrary to the principle of proportionality and reasonableness. 

11. It   is   also   relevant   to   note   that   as   per   Clause   35.2.3 (supra) of the Conditions of Contract, it was expressly provided   that   there   would   be   no   consequential damages payable by the Purchaser to the Supplier in the   event   of   termination   of   the   contract,   as   the supplier would get 105% of the costs incurred.

The   Claimant/Respondent   has,   in   fact   been awarded   105%   of   the   costs   incurred   under   the   EPC Contracts by the arbitral tribunal. 

The   award   of   Interest   @   9%   on   the   Euro component   of   the   Claim   is   unjustified   and unwarranted. The levy of such a high rate of Interest on a claim made in a foreign currency, would result in the Claimant being awarded compensation, contrary to the conditions stipulated in the Contract. 17

12. The Award has granted a uniform rate of 9% S.I. on both the INR and the EUR component. However, when the parties do not operate in the same currency, it is necessary   to   take   into   account   the   complications caused   by   differential   interest   rates.   Interest   rates differ depending upon the currency. It is necessary for the   arbitral   tribunal   to   co­ordinate   the   choice   of currency   with   the   interest   rate.   A   uniform   rate   of Interest   for   INR   and   EUR   would   therefore   not   be justified. The rate of 9% Interest on the INR component awarded   by   the   arbitral   tribunal   will   remain undisturbed.   However,   with   respect   to   the   EUR component,   the   award­debtor   will   be   liable   to   pay Interest   at   the   LIBOR   rate   +   3   percentage   points, prevailing on the date of the Award.

13. In light of the above­mentioned discussion, the Interest awarded by the arbitral tribunal is modified only to the extent mentioned hereinbelow :­ 

(i) The  Interest rate of 15% post 120 days granted on the entire sum awarded stands deleted.  18 A   uniform   rate   of   Interest   @   9%   will   be applicable for the INR component in entirety till the date of realization. 

(ii) The   Interest   payable   on   the   EUR   component   of the   Award  will be as per LIBOR + 3 percentage points   on   the   date   of   Award,   till   the   date   of realization.

The Appeal is disposed of accordingly. 

…………….........................J. (ROHINTON FALI NARIMAN) .……………………J. (INDU MALHOTRA) New Delhi, October 11, 2018 19