Document Fragment View

Matching Fragments

15. Learned counsel further submits that while dealing with Section 11(6), the Chief Justice/his designate can even overlook the qualification of the arbitrator under the agreement but arbitration agreement in the instant case does not contain any specific qualification of the arbitrator under Clause 64(3) of the GCC and since the appellants failed to appoint an arbitrator until the application was filed, Section 11(6) empowers the Court to deviate from the agreed terms if required by appointing an independent arbitrator and by virtue of operation of Section 12(5) of the Amendment Act, 2015, the employee of the railway establishment became ineligible to be appointed as arbitrator. In the given circumstances, the authority is vested with the Chief Justice or his designate to appoint an independent arbitrator under Section 11(6) of the Act and the same has been held by this Court in North Eastern Railway and Others Vs. Tripple Engineering Works 2014(9) SCC 288 and Union of India and Others Vs. Uttar Pradesh State Bridge Corporation Limited 2015(2) SCC 52.

38. Clause (c) of sub­section (6) of Section 11 relates to failure to perform any function entrusted to a person including an institution and also failure to act under the procedure agreed upon by the parties. In other words, clause(a) refers to the party failing to act as required under that procedure; clause(b) refers to the agreement where the parties fails to reach to an agreement expected of them under that procedure and clause (c ) relates to a person which may not be a party to the agreement but has given his consent to the agreement and what further transpires is that before any other alternative is resorted to, agreed procedure has to be given its precedence and the terms of the agreement has to be given its due effect as agreed by the parties to the extent possible. The corrective measures have to be taken first and the Court is the last resort. It is also to be noticed that by appointing an arbitrator in terms of sub­section (8) of Section 11 of Act, 1996, due regard has to be given to the qualification required for the arbitrator by the agreement of the parties and also the other considerations such as to secure an independent and impartial arbitrator. To fulfil the object with terms and conditions which are cumulative in nature, it is advisable for the Court to ensure that the remedy provided as agreed between the parties in terms of the contract is first exhausted.

6. It is also pointed out that while appointing an arbitrator in terms of sub­section (8) of Section 11, the Court has to give due regard to any qualification required for the arbitrator by the agreement of the parties and other considerations as are likely to secure the appointment of an independent and impartial arbitrator. It is pointed out that both these conditions are cumulative in nature. Therefore, the Court should not directly make an appointment. It has to ensure first that the provided remedy is exhausted and the Court may ask to do what has not been done.

43. In the present batch of appeals, independence and impartiality of the arbitrator has never been doubted but where the impartiality of the arbitrator in terms of the arbitration agreement is in doubt or where the Arbitral Tribunal appointed in terms of the arbitration agreement has not functioned, or has failed to conclude the proceedings or to pass an award without assigning any reason and it became necessary to make a fresh appointment, Chief Justice or his designate in the given circumstances after assigning cogent reasons in appropriate cases may resort to an alternative arrangement to give effect to the appointment of independent arbitrator under Section 11(6) of the Act. In North Eastern Railway and Others Vs. Tripple Engineering Works (supra), though the panel of arbitrators as per clause 64(3)(a)(ii) and (iii) of the general conditions of contract under GCC was appointed in the year 1996 but for two decades, the arbitrator failed to pass the award and no explanation came forward. In the given situation, this Court observed that general conditions of the contract do not prescribe any specific qualification of the arbitrators to be appointed under the agreement except that they should be railway officers further held that even if the arbitration agreement was to specifically provide for any particular qualification(s) of an arbitrator the same would not denude the power of the Court acting under Section 11(6) to depart therefrom and accordingly, confirmed the appointment of an independent arbitrator appointed by the High Court in exercise of Section 11(6) of the Act, 1996. Almost the same situation was examined by this Court in Union of India and Others Vs. Uttar Pradesh State Bridge Corporation Ltd. (supra) and after placing reliance on North Eastern Railway and Others Vs. Tripple Engineering works(supra) held that since Arbitral Tribunal has failed to perform and to conclude the proceedings, appointed an independent arbitrator in exercise of power under Section 11(6) of the Act, 1996. In the given circumstances, it was the duty of the High Court to first resort to the mechanism in appointment of an arbitrator as per the terms of contract as agreed by the parties and the default procedure was opened to be resorted to if the arbitrator appointed in terms of the agreement failed to discharge its obligations or to arbitrate the dispute which was not the case set up by either of the parties.