Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 4, Cited by 0]

Bangalore District Court

M/S.Hindustan Aeronautics Limited vs ) M/S.Urc Construction Pvt.Ltd on 15 October, 2020

IN THE COURT OF THE VI ADDL.CITY CIVIL & SESSIONS JUDGE
                   BENGALURU CITY
                      CCCH. 11


      Dated this the 15th day of October, 2020

    PRESENT: Sri.Rama Naik, B.Com., LL.B.,
             VI Addl.City Civil & Sessions Judge,
             Bengaluru City.

                A.S.NO:100/2013


PLAINTIFF        M/S.HINDUSTAN AERONAUTICS LIMITED
                 Facilities Management Division,
                 Bengaluru - 560 017.
                 Reptd.by its General Manager.

                            [By Pleader Sri.S.V.Shastri]

                 /Vs/

DEFENDANTS       1) M/S.URC CONSTRUCTION PVT.LTD.
                    H-102, Periyar Nagar,
                    Erode - 638 001.
                    Reptd.by its Managing Director

                           [By Pleader Sri.P.B.Appiah]

                 2) SRI.N.NAGABUSHANAM
                    Sole Arbitrator,
                    Chief of Project (CH-CK),
                    Helicopter Division, HAL,
                    Bengaluru -560 017.

                              [ Arbitrator ]
                                                      AS.100/2013
                                 2

                     J U D G M E NT

       This suit is filed by Plaintiff under Section 34

of the Arbitration and Conciliation Act, 1996, for

setting aside the arbitral award, dated 17.09.2013

passed by sole Arbitrator/2nd Defendant in the

matter of contract for construction of Periodical

Service Hanger and Alpha Helipad.



2)     Plaintiff's case, in brief, is that, in response

to offer made by 1st Defendant vide letter dated

24.02.2007, two contracts dated 03.08.2007 were

entered into between Plaintiff and Defendant No.1

for construction of Periodical Service Hanger and

Alpha Helipad. 1st Defendant could not complete

the   work      as   per   schedule       time.    Work   was

completed       within     the       extended     time.   After

completion of the work, final bill was submitted and

same was paid to 1st Defendant, which came to be

accepted by 1st Defendant by producing 'No Claim

Certificate'.
                                                               AS.100/2013
                                       3

3)    It is stated that, after acceptance of final bill,

1st Defendant raised dispute and requested to refer

the dispute to sole Arbitrator, which came to be

referred    to        sole    Arbitrator,       who    passed        the

impugned award.


4)    Being aggrieved by the award, Plaintiff has

challenged the same on the following grounds :

      (1)        Learned Arbitrator, without referring
      the documents produced by the parties has
      passed the impugned award.

      (2)        Award passed is in contravention of
      Section 31 of the Arbitration and Conciliation
      Act, 1996.

      (3)        Award       is    passed      disregarding    the
      terms of Clause-33(a) of General and Special
      Conditions of Contract.

      (4)        Learned          Arbitrator    has   failed    to
      consider Clause-18.2 of Special Conditions
      of Contract.

      (5)        In    view       of   'No   Claim    Certificate'
      submitted by 1st Defendant, dispute raised
      by 1st Defendant is not maintainable. In spite
                                                    AS.100/2013
                             4

      of   specific   plea   taken   by   Plaintiff,   2 nd
      Defendant has failed to exercise the power
      vested in him while passing the impugned
      award.

       For these grounds, Plaintiff prays for setting

aside the award.


5)     Defendant No.1 marked appearance through

its Counsel and filed its written statement, stating

that, Plaintiff failed to hand over the entire site

immediately after entering into contract, hence, it

had become impossible to complete the work within

the contract period. Plaintiff breached the contract.

This aspect of the matter has not been considered,

while passing the award. Suit filed under Section 34

of the Arbitration and Conciliation Act, 1996, for

setting aside the award is wholly misconceived. It

lacks grounds and same is not maintainable. Hence,

prays for dismissal of the suit.


6)     Heard learned Counsels for Plaintiff and

Defendant No.1. Perused the written arguments
                                               AS.100/2013
                           5

filed by Plaintiff and Defendant No.1. Also perused

the records.

7)     Point that arises for consideration is that :

          " Whether Plaintiff has made out
            any    of   the    grounds    as
            enumerated in Section 34 of the
            Arbitration and Conciliation Act,
            1996 to set aside the award?"


8)     My answer to above point is in the negative

for the following :

                      REASONS

9)     By this suit, Plaintiff [Respondent before the

learned Arbitrator] has sought for setting aside the

arbitral award dated 17.09.2013 made by sole

Arbitrator/2nd    Defendant,      whereby,      learned

Arbitrator was pleased to make an award for

Rs.45,73,775/- in favour of 1st Defendant and

against Plaintiff by allowing Claims No.1 and 2 in full

and in the award, claim with respect to interest

under Claim No.3 and Counter Claim of Plaintiff

were disallowed by learned Arbitrator.
                                                   AS.100/2013
                            6

10)   1st Defendant made 3 Claims before the

learned Arbitrator, in which, Claims No.1 and 2 were

allowed in full and Claim No.3 was disallowed.

Claims No.1 to 3 are as follows :

         " The Claimant submitted their Claim
        Statement dated 29.05.2012 praying the
        arbitrator to pass an award for balance in
        price adjustment bill for periodic service
        hangar of Rs.37,75,725.23 and for a sum of
        Rs.7,98,050.00 for the work of Alpha Helipad
        and also for interest @ 18% p.a. from
        01.01.2011 on Rs.37,75,725.23 in respect of
        periodical service hangar and to pay interest
        at    18%     p.a.  from    21.07.2009    on
        Rs.7,98,050.00 in respect of Alpha Helipad.
        In their statement of claim submitted to the
        Arbitrator, M/s.URC Construction (P) Ltd.
        Submitted      2   claims    amounting     to
        Rs.45,73,775.23 and interest thereon at 18%
        p.a."




11)   Learned     Arbitrator     made      an    award    of

Rs.37,75,725.23      towards       Claim        No.1     and

Rs.7,98,050/- towards Claim No.2.


12)   Facts, which are not in dispute, are that, work

was fully completed by 1st Defendant and on

completion of the work, final bill was submitted by

1st Defendant, which was paid to 1st Defendant.
                                                   AS.100/2013
                            7

13)   Plaintiff's contention is that, contracts dated

03.08.2007 were executed between Plaintiff and

Defendant    No.1   for    construction      of   Periodical

Service   Hangar    and     Alpha     Helipad.    Work   for

construction of Periodical Service Hangar was to be

completed by 1st Defendant within 19.04.2008 and

work for construction of Alpha Helipad to be

completed on 19.02.2008. It is contended that, 1 st

Defendant failed to complete the work as agreed

and as per the request of 1st Defendant, time was

extended till 31.08.2008. It is contended that in

view of Clause-33(a) of General Conditions of

Contract, price variation up to 20% should be borne

by 1st Defendant.


14)   On the other hand, Defendant No.1 contends

that, site was handed over to 1 st Defendant in

piecemeal,   hence,       extension    was    granted    to

complete the work without levying any penalty. It is

contended that, the delay of handing over the site

by Plaintiff made the Defendant No.1 not only to
                                             AS.100/2013
                          8

unable to keep up the requisite rate of progress, but

also pushed it to face escalation in the rate of

materials in the open market. It is contended that,

plea that has been taken by Plaintiff that no price

variation is allowed for the extended period of

contract will be legitimately applicable to cases

where extension of period of contract is allowed for

reasons attributable to the contractor.


15)   In the award, learned Arbitrator has come to

the specific conclusion that, there was delay in

handing over the site to 1st Defendant and 1st

Defendant is entitled to claim for price adjustment

for the works done during the extended period of

contract. It is relevant to mention the findings of

learned Arbitrator regarding Claims No.1 and 2.

They read thus :

      " CLAIM NO. -1

          Whether the claimant is entitled to a
      sum of Rs.37,75,725.23 being the
      balance in escalation bill for Periodical
      Service Hangar.
                                             AS.100/2013
                       9

       The Clause No.33 (a) of General and
Special Conditions of the Contract provides
that all contracts up to 24 months shall be on
fixed prices and are not subject for payment
of any variation of prices whatsoever.
However, if there is any abnormal variation in
the basic prices of major construction
materials like, cement, reinforcement steel,
structural steel & Bitumen and the variation
exceeds 20% of the basic prices of the
materials, then the price variation shall be
applicable during the currency of the
contract. No price variation is allowed for the
extended period of contract.

The Claimant claimed for payment of a sum
of Rs.37,75,725.23 being the balance in
escalation bill for Periodical Service Hanger.

The Claimant submitted that the reading of
whole clause as extracted hereinbefore does
not support even implicitly the restriction of
escalation bill to the quantum of variation
only between 20% and above, thereby
denying a flat 20% benefit of escalation to
the claimant. The words, I.e, the variation
exceeds 20% of the basic price of
materials mentioned below, the price
variation shall be applicable during the
currency of contract ..., contained under
the price escalation clause of the contract
connotes that the Claimant is entitled to the
full benefit of price variation up to the market
rate and not merely an amount over and
above 20% of the basic prices of materials.
The Claimant is, therefor,e entitled to the full
benefit of price variation up to the market
rate as against the action of the Respondent
in having excluded a flat rate of 20% of the
benefits of escalation for the materials for
which price materials exceeds 20% of the
basic prices.

Moreover, the contract No.HAL-C/289A/05-06
regarding     construction  of    Periodical
Servicing/Inspection Hangar at Helicopter
Division, HAL (DC) was scheduled to
                                             AS.100/2013
                      10

terminate on 13th April, 2008. The Claimant,
however, actually finished the work on 31 st
March, 2009. It was found that there were
delay on the part of the Respondent in
handing over of sites to the Claimant and
consequently, the Respondent extended the
contract period up to 31st March, 2009, i.e.,
date of actual completion of work under the
contract, without levy of penalty.       The
Claimant, therefore, is entitled to claim for
price adjustment for the works done during
the extended period of contract.

Hence, I hereby award a sum of
Rs.37,75,725.23 being the balance in
escalation bill for Periodical Service
Hangar to be paid to the Claimant on
this account.

CLAIM NO. - 2

Whether the Claimant is entitled to a
sum   of  Rs.7,98,050.00  being   the
balance in escalation bill for Alpha
Helipad Work.

The Claimant demanded for payment of a
sum of Rs.7,98,050.00 being the balance in
escalation bill for Alpha Helipad Work. The
Claimant submitted that price variation shall
be applicable during the currency of the
contract without limiting the payment to the
quantum of excess percentage variation over
and above 20%.

The plain reading of price escalation clause
of the contract unambiguously connotes that
the Claimant is entitled to the full benefit of
price variation up to the market rate
containing an amount to the extent of 20% of
the basic prices of materials and also an
amount over and above 20% of the basic
prices of materials.

For the aforesaid reasons, the Claimant is
entitled to the full benefit of price variation
up to the market rate as against the action of
                                                  AS.100/2013
                           11

      the respondent in having excluded a flat rate
      of 20% of the benefits of escalation for the
      materials for which price materials exceeds
      20% of the basic prices.

      Furthermore, contract no.HAL-C/199A/05-06
      of Construction of Alpha Helipad at Helicopter
      Division (HC) was due to finish 19th February,
      2008.     The Claimant, however, actually
      completed the contractual task on 31st
      August, 2008. It was found that there were
      delay on the part of the Respondent in
      handing over of sites to the Claimant and
      consequently, the Respondent extended the
      contract period up to 31st August, 2008, i.e.,
      date of actual completion of work under the
      contract, without levy of penalty.        The
      Claimant, therefore, is entitled to claim for
      price adjustment for the works done during
      the extended period of contract.

      Hence, I hereby award a sum of
      Rs.7,98,050.00 being the balance in
      escalation bill for Periodical Service
      Hangar to be paid to the Claimant on
      this account."




16)   From the above findings, it has been clear

that, having regard to the delay in handing over the

site by Plaintiff, learned Arbitrator made an award

for balance escalation bill. Award is required to be

looked into in that context. Plaintiff never denied

that there was no delay on its part in handing over

the site and it is not the contention of the Plaintiff
                                                   AS.100/2013
                            12

that, learned Arbitrator's conclusion regarding delay

is wrong.


17)   At this stage, it is relevant to take notice of

Clauses-18.2 and 33(a) of General and Special

Conditions of Contract. Clauses-18(2) and 33(a)

read thus :


        "18.2. IF THE WORKS BE DELAYED

              a) by force majeure, or

            b) by reasons        of   abnormally bad
        weather, or

            c) by reasons of civil commotion, local
        combinations of workmen strike or lockout,
        affecting any of the tradesmen employed
        on the work, or

            d) by reasons of delay on the part of
        nominated suppliers which the Contractors
        has in the opinion of Engineer-in-Charge
        taken all practical steps to avoid or reduce,
        or

             e) by reasons of delay on the part of
        the Contractors or tradesmen engaged by
        HAL in executing works not forming the
        part of contract, or

             f) by reason if any other cause, which
        in the absolute discretion of Accepting
        Officer is beyond the control.

        Then in such case the Accepting Officer
        may grant fair and reasonable extension in
        the completion dates of individual items or
                                                 AS.100/2013
                           13

        work for which the separate period of
        completion is mentioned in the contract
        documents or work order as applicable.
        Upon the happening of any such event
        causing delay, the Contractor shall
        immediately give notice thereof in writing
        to     Engineer-in-Charge     but     shall
        nevertheless use constantly his best
        endeavor to prevent or make good the
        delay and shall do all that may reasonably
        be extension of time as granted above
        shall be communicated to the Contractor
        by the Engineer-in-Charge in writing and
        shall be final and binding.

        No claims in respect of compensation or
        otherwise, however, arising as a result of
        extension granted shall be admitted."


        "33(a) PRICE ADJUSTMENT CLAUSE :

             All contracts upto 24 months shall be
        on fixed prices and are not subject for
        payment of any variation of Prices
        whatsoever.     However, if there is any
        abnormal variation in the basic prices of
        major construction Materials like Cement,
        Reinforcement Steel, Structural Steel &
        Bitumen and the variation exceeds 20% of
        the basic price of materials mentioned
        below, then Price Variation shall be
        Applicable during the currency of the
        Contract. No Price variation is allowed for
        the extended period of contract. "



18)   A bare reading of Clause-18.2 makes it clear

that, for the reasons mentioned in sub-clauses (a)

to (f), no claim for compensation shall be admitted

as a result of extension granted. Under sub-clause
                                              AS.100/2013
                         14

(e), if the work is delayed on the part of the

contractor, no claim shall be admitted as a result of

extension granted. Nowhere, it is mentioned in

Clause 18.2 that, no claim for compensation shall

be admitted as a result of extension granted on

account of delay in handing over the site by

Plaintiff. Thus, it is clear that, Clause-18.2 does not

bar the Contractor to claim compensation for the

delay in execution of the work caused by Plaintiff

due to Plaintiff's failure to hand over the site within

the contract period. In this circumstance, there is no

reason to hold that, learned Arbitrator has passed

the award in violation of the terms of contract.


19)    Clause-33(a) makes it clear that, variation

exceeds 20% of the basic price of materials then

price variation shall be applicable during the

currency of the contract. In the instant case,

learned Arbitrator has come to the conclusion that,

delay in completion of the work is caused by not
                                           AS.100/2013
                        15

handing over site during the currency of contract

and for that reason, the currency of contract was

extended till 31.03.2009 and 31.08.2008 in respect

of Periodical Service Hangar and Alpha Helipad

works and same was completed by Defendant No.1

during the currency of extended period. In this

circumstance, Plaintiff cannot say that, no price

variation is allowed for the extended period of

contract. If the currency of contract was extended

at the instance of Defendant No.1, then, it would be

proper to contend that, no price variation clause is

allowed for the extended period of contract. Award

makes it clear that, learned Arbitrator has viewed

Clause-33(a) in a perspective manner.



20)   Further, Plaintiff has failed to bring to the

notice of the Court as to what were the documents

to be relied upon by learned Arbitrator and that the

award would have been different, had the said

documents been relied upon. In the backdrop of
                                                     AS.100/2013
                             16

Plaintiff's failure to substantiate its case, there

could be no occasion for this Court to go into the

merits of the award passed by learned Arbitrator on

facts and materials placed before him. Admittedly,

in Section 34 petition, there is no scope for re-

assessing or re-appreciating the evidence, which

learned Arbitrator had come across. In Section 34

petition, what this Court can do is that, it has to

consider whether any of the grounds mentioned in

Section 34 of the Act, are made out by Plaintiff? If it

is so, then only, this Court can set aside the award.

Even if it is found that, there exists errors of facts in

arriving at the conclusion by learned Arbitrator, this

Court has no power to correct the errors of fact. In

P.R. Shah, Shares and Stock Broker (P) Ltd.

vs. B.H.H. Securities (P) Ltd. And Ors. [AIR

2012 SC 1866], the Hon'ble Supreme Court was

pleased to hold that :

       "14. A court does not sit in appeal over the
       award of an arbitral tribunal by re-assessing or
       re-appreciating the evidence. An award can be
       challenged only under the grounds mentioned
       in section 34(2) of the Act..."
                                                         AS.100/2013
                               17

21)   In       Associate         Builders         vs.        Delhi

Development Authority [(2015) 3 SCC 49], the

Hon'ble Supreme Court was pleased to hold that :

           "33. When a court is applying the "public
           policy" test to an arbitration award, it does
           not act as a court of appeal and consequently
           errors of fact cannot be corrected. A possible
           view by the arbitrator on facts has
           necessarily to pass muster as the arbitrator is
           the ultimate master of the quantity and
           quality of evidence to be relied upon when he
           delivers his arbitral award. Thus an award on
           little evidence or on evidence which does not
           measure up in quality to a trained mind
           would not be held to be invalid on this score.
           Once it is found that the arbitrators approach
           is not arbitrary or capricious, then he is the
           last word on facts."



      When such is the position, there is no reason

to interfere with the award in Plaintiff's failure to

substantiate the contention that, learned Arbitrator

failed to consider the documents relied upon by the

parties and evidence adduced by them. It is a mere

contention without any substantiation.


22)   Plaintiff's      main     contention       is     that,   1 st

Defendant submitted final bill along with 'No Claim

Certificate'. Having regard to 'No Claim Certificate',
                                                      AS.100/2013
                             18

final bill was paid. Once the 'No Claim Certificate' is

produced and final bill was accepted, there exists

no dispute between the parties to invoke the

arbitration clause and it is contended that, even

this aspect of the matter was argued before the

learned Arbitrator, but he failed to consider the

same. Both Plaintiff and Defendant No.1 have

placed reliance on the judgment in National

Insurance Company Ltd. vs. Boghara Polyfab

Private Limited, [(2009) 1 Supreme Court

Cases 267].


       Principles    laid     down       in    National
    Insurance       Company         Limited      are       as
    follows :
         "22. Where the intervention of the court is
         sought for appointment of an Arbitral
         Tribunal under Section 11, the duty of the
         Chief Justice or his designate is defined in
         SBP & Co. This Court identified and
         segregated the preliminary issues that may
         arise for consideration in an application
         under Section 11 of the Act into three
         categories, that is, (i) issues which the Chief
         Justice or his designate is bound to decide;
         (ii) issues which he can also decide, that is,
         issues which he may choose to decide; and
         (iii) issues which should be left to the
         Arbitral Tribunal to decide.
                                           AS.100/2013
                   19

22.1. The issues (first category) which the
Chief Justice/his designate will have to
decide are :

   (a) Whether the party making the
application has approached the appropriate
High Court.

    (b) Whether there is an arbitration
agreement and whether the party who has
applied under Section 11 of the Act, is a
party to such an agreement.

22.2. The issues (second category) which
the Chief Justice/his designate may choose
to decide (or leave them to the decision of
the Arbitral Tribunal) are :
    (a) Whether the claim is a dead (long-
barred) claim or a live claim.

    (b) Whether the parties have concluded
the    contract/transaction   by    recording
satisfaction of their mutual rights and
obligation or by receiving the final payment
without objection.

22.3. The issues (third category) which the
Chief Justice/his designate should leave
exclusively to the Arbitral Tribunal are :

(i) Whether a claim made falls within the
arbitration clause (as for example, a matter
which is reserved for final decision of a
departmental authority and excepted or
excluded from arbitration).

(ii) Merits or any claim involved in the
arbitration.

23. It is clear form the scheme of the Act
as explained by this Court in SBP & Co., that
in regard to issues falling under the second
category, raised in any application under
Section 11 of the Act, the Chief Justice/his
designate may decide them, if necessary, by
taking evidence. Alternatively he may leave
those issues open with a direction to the
Arbitral Tribunal to decide the same. If the
                                            AS.100/2013
                   20

Chief Justice or his designate chooses to
examine the issue and decides it, the
Arbitral Tribunal cannot re-examine the
same issue. The Chief Justice/his designate
will, in choosing whether he will decide such
issue or leave it to the Arbitral Tribunal be
guided by the object of the Act (that is
expediting the arbitration process with
minimum judicial intervention). Where
allegations of forgery/fabrication are made
in regard to the document recording
discharge of contract by full and final
settlement, it would be appropriate if the
Chief Justice/his designate decides the
issue.

24. What is however clear is when a
respondent contends that the dispute is not
arbitrable on account of discharge of the
contract under a settlement agreement or
discharge voucher or no-claim certificate,
and the claimant contends that it was
obtained by fraud, coercion or undue
influence, the issue will have to be decided
either by the Chief Justice/his designate in
the proceedings under Section 11 of the Act
or by the Arbitral Tribunal as directed by the
order under Section 11 of the Act. A claim
for arbitration cannot be rejected merely or
solely on the ground that a settlement
agreement or discharge voucher had been
executed by the claimant, if its validity is
disputed by the claimant.

29. It is thus clear that the arbitration
agreement contained in a contract cannot
be invoked to seek reference of any dispute
to     arbitration,    in     the    following
circumstances, when the contract is
discharged on account of performance, or
accord     and    satisfaction,   or   mutual
agreement, and the same is reduced to
writing (and signed by both the parties or by
the party seeking arbitration):

   (a)    where the obligations under a
contract are fully performed and discharge
of the contract by performance is
acknowledged by a full and final discharge
                                            AS.100/2013
                   21

voucher/receipt, nothing survives in regard
to such discharged contract;

    (b) where the parties to the contract, by
mutual agreement, accept performance of
altered,    modified     and      substituted
obligations and confirm in writing the
discharge of contract by performance of the
altered, modified or substituted obligations;

    (c)    where the parties to a contract,
by mutual agreement, absolve each other
from performance of their respective
obligations (either on account of frustration
or otherwise) and consequently cancel the
account of frustration or otherwise) and
consequently cancel the agreement and
confirm that there are no outstanding
claims or disputes."

52. Some illustrations (not exhaustive) as
to when claims are arbitrable and when they
are not, when discharge of contract by
accord and satisfaction are disputed, to
round up the discussion on this subject are:

(i) A claim is referred to a conciliation or a
pre-litigation Lok Adalat. The parties
negotiate and arrive at a settlement. The
terms of settlement are drawn up and
signed by both the parties and attested by
conciliator or the members of the Lok
Adalat. After settlement by way of accord
and satisfaction, there can be no reference
to arbitration.

(ii) A claimant makes several claims. The
admitted or undisputed claims are paid.
Thereafter negotiations are held for
settlement of disputed claims resulting in an
agreement in writing settling a pending
claims and disputes. On such settlement,
the amount agreed is paid and the
contractor   also    issues    a   discharge
voucher/no claim certificate/full and final
receipt. After the contract is discharged by
accord and satisfaction, neither the contract
nor any dispute survives consideration.
                                            AS.100/2013
                   22

There cannot be any reference of any
dispute to arbitrate thereafter.

(iii) A contractor executes the work and
claims payment of rupees ten lakhs as due
in terms of the contract. The employer
admittedly claim only for rupees six lakhs
and informs the contractor either in writing
or orally that unless the contractor gives a
discharge voucher in the prescribed format
acknowledging receipt of rupees six lakhs in
full and final satisfaction of the contract,
payment of the admitted amount will not be
released. The contractor who is hard-
pressed for funds and keen to get the
admitted amount released, signs on the
dotted line either in a printed form or
otherwise, stating that the amount is
received in full and final settlement. In such
a case, the discharge is under economic
duress on account of coercion employed by
the employer. Obviously discharge voucher
cannot be considered to be voluntary or as
having resulted in discharge of the contract
by accord and satisfaction. It will not be a
bar to arbitration.

(iv)   As insured makes a claim for loss
suffered. The claim is not admitted nor
rejected. But the insured is informed during
discussion unless the claimant gives a full
and final voucher for a specified amount
(far lesser than the amount claimed by the
insured), the entire claim will be rejected.
Being in financial difficulties, the claimant
agrees to demand and issues an undated
discharge voucher in full and final
settlement. Only a few days thereafter, the
admitted amount mention in the voucher is
paid. The accord and satisfaction in such a
case is voluntary but under duress,
compulsion and coercion. The coercion is
subtle but very much real. The "accord" is
not by free consent, arbitration agreement
can thus be invoked to refer the dispute
arbitration.

(v) A claimant makes a claim for a huge
sum, by way of damages. The respondent
                                                   AS.100/2013
                           23

        disputes the claim. The claimant who is
        keen to have settlement and avoid
        litigation, voluntarily reduces the claim and
        requests for settlement. The respondent
        agrees and settles the claim and obtains a
        full and final discharge voucher. Here even
        if the claimant might have agreed for
        settlement due to financial compulsions and
        commercial pressure or economic duress,
        the decision was his free choice. There was
        no threat, coercion or compulsion by the
        respondent.      Therefore, the accord and
        satisfaction is binding and valid and there
        cannot be any subsequent claim or
        reference to arbitration."



23)   In this case, 2nd Defendant was not appointed

by filing CMP before the Hon'ble High Court of

Karnataka. Sole Arbitrator was appointed at the

request of 1st Defendant by Plaintiff as per the

arbitration clause in contract. Admittedly, while

appointing the Arbitrator by Plaintiff, Plaintiff did

not raise any objection to the request made by 1 st

Defendant to the effect that in view of 'No Claim

Certificate' submitted by Defendant No.1, the

dispute raised by 1st Defendant is not arbitrable.

Instead, without there being any objection to the

request made by 1st Defendant, Plaintiff appointed
                                                            AS.100/2013
                               24

2nd Defendant as sole Arbitrator to arbitrate the

dispute made in the request.


24)   On perusal of objection filed by Plaintiff

before the learned Arbitrator makes it clear that,

Plaintiff has taken the plea that in view of

submission of 'No Claim Certificate', claim petition

be dismissed as not maintainable.



25)   1st    Defendant,        in   its    reply     to     counter

statement has countered the plea contending that,

it was facing financial crisis and as it was condition

precedent to submit 'No Claim Certificate' before

accepting     final   bill    by    Plaintiff,     final    bill   for

escalation was re-submitted               for reduced amount

due to      insistence       of Plaintiff    and      hence,       1 st

Defendant is not debarred from claiming balance

escalation amount. Para-34, 35, 36 and 37 of

Rejoinder filed by 1st Defendant before the learned

Arbitrator read thus :
                                            AS.100/2013
                    25

"34. The other repeated objections of the
respondent that the claimant has given 'no
claim certificate' (R.26.a&b). The claimant
in the letter dt.02.04.09 (C-8) has furnished
the details for payment due, ie. For pre-
final bills (dt.21.03.09 & 15.09.08) for
Rs.106/ lakhs and Rs.27/- lakhs etc along
with escalation bills; with a request to
release payment at the earliest enabling us
to complete the Project in time.          The
claimant in the letter dt.26.05.09 (R-15)
has furnished the final bill for Rs.6,78,612/-
for Alpha Helipad. The claimant in the
letter dt.03.07.09 (C-10) has indicated that
"we are under force to borrow heavily
from outside sources and bank at
exorbitant rate of interest". The claimant
in the letter dt.08.08.2009 (R-20) has
detailed severe financial crises faced.
The claimant in the letter dt. 23.11.2011
(C-15) while reminding about the total
outstanding      as    Rs.1,05,63,662/-    has
explained the severe financial crises
faced and reminded for release of
escalation bill for Rs.45,73,775/-. The
respondent in the letter dt.23.12.11 (C-16)
has rejected the request for payment of
balance in escalation bill. The claimant in
the letter dt.28.12.2011 (C-20) has
informed specifically that clause 26 of
general conditions indicates that " Before
submission of the final bill, the contractor
should sign in a No claim certificate
indicating that the contractor has no claim
against the company under the contract in
question except as included in the final
bill" and in accordance with the above
condition, the amount of Rs.53.83 lakhs for
Periodical service hangar and Rs.6.19 lakhs
for Alpha helipad was already included in
the Final bills but it was resubmitted as per
your instructions' and explained while
insisting for balance in escalation bill, that
the bills were        earlier resubmitted for
reduced amount.
                                             AS.100/2013
                   26

35.    Therefore, the resubmission of final
escalation bill for reduced amount is not
voluntary but due to the insistence of
respondent and the 'no claim certificate',
as the condition precedent, under the
circumstances of economic duress. It is
therefore clear that there was no mutual
settlement to agree with the amount
reduced    by     respondent  under     the
misleading plea of having scrutinized the
bills.

36. It is relevant to note that the work
of Periodical servicing/inspection hangar
was completed on 31.03.2009 (C-13)
and Alpha Helipad was completed on
31.08.08       (C-14),    whereas,    the
respondent, issued the completion
certificate in the letters dt. 31.01.11
(C-13 & 14) and in the letter dt.
23.12.11 (C-16) has         rejected the
request for payment of balance
escalation bill. The respondent in the
letter dt. 02.03.12 (C21) has stated
that the claimant has given no claim
certificate dt. 09.11.09 and accordingly
HAL has settled the final bill and
rejected the request for appointment of
arbitrator. The respondent, at page-14
under the caption RE-Claim-17(a & b) of
counter statement, has informed that
the final bills were released on
31.12.09.       The above sequences
explain the severe financial crisis,
the claimant was subjected to, in
signing the "No claim certificate"
prescribed       in    clause    26    of
conditions of contract referred to in
claimant's letter dt.28.12.11 (C-20)
under economic duress.

37. In the same letter dt. 28.12.2011
(C-20), the claimant gave notice to refer
the disputes relating to payment of
escalation bills to arbitration.     The
respondent in the letter dt. 02.03.12 (C-
                                                       AS.100/2013
                             27

        21)     rejected     the    request     for
        reconsideration on the plea that the
        claimant has given 'no claim certificate'.
        The claimant in the letter dt. 10.03.12
        (C-22) sent a detailed report specifying
        that " If you are not appointing the sole
        arbitrator to decide the above disputes
        within 30 days from the date of receipt
        of this letter, we are forced to take legal
        course of action to safe guard our
        interest."



26)    There is no material to show that, by placing

'No Claim Certificate' before the learned Arbitrator,

whether Plaintiff had pressed for adjudication of the

contention that claim petition is not maintainable in

view of submission of 'No Claim Certificate' by 1 st

Defendant. Learned Arbitrator has framed three

Issues regarding the entitlement of 2 Claims and

interest as claimed by 1st Defendant and exemplary

costs claimed by Plaintiff and passed the award

allowing Claims No.1 and 2 of 1st Defendant. Till

passing the award, Plaintiff kept quite without

pursuing his plea as to maintainability of claim

petition and now sought for setting aside the award

on    the   ground    that     claim    petition       is   not
                                                      AS.100/2013
                                 28

maintainable in view of submission of 'No Claim

Certificate'. This preliminary objection raised by

Plaintiff ought to have been pressed by it before

arbitration of the claims on merits. However, after

making       the    award        on   merits,   Plaintiff    has

questioned the same on the ground which ought to

have been decided as preliminary issue.



27)   From         the   ratio    laid   down   in   National

Insurance Company Limited (supra), it has been

clear that, what are the issues that can be

adjudicated by the Hon'ble Supreme Court/Hon'ble

High Court while appointing the Arbitrator on the

application filed under Section 11 of the Arbitration

and Conciliation Act, 1996. One of the issues that

can be considered for decision while appointing the

Arbitrator    is    that,   "whether      the   parties     have

concluded the contract/transactions by recording

satisfaction of their mutual rights and obligation or

by receiving the final payment without objection".
                                                      AS.100/2013
                            29

Or else, said issue may be left for the decision of

the Arbitrator. Nowhere in the judgment (supra), it

is held that, once the 'No Claim Certificate' is

submitted, the Arbitrator has no jurisdiction to

entertain the claim petition.


28)     Be that as it may. 1st Defendant's contended

in its rejoinder, due to severe financial crisis, final

bill   was    resubmitted        along    with     'No   Claim

Certificate'. As per Clause-26 of Special Conditions

of Contract [SCC], before submitting final bill, the

Contractor     should     sign    'No     Claim    Certificate'

indicating    that   he   has     no     claim    against    the

Company under the contract in question. When it is

mandatory to submit 'No Claim Certificate' before

submitting final bill, Contractor is bound to submit

final bill for the agreed contract value only. Under

Clause-26 of SCC, there would be no option for 1 st

Defendant to submit the final bill before submitting

the     'No    Claim       Certificate'.         Under      such

circumstances, Contractor shall submit final bill for
                                                   AS.100/2013
                         30

the agreed contract value in order to get his

payment. He has no option to submit final bill for

escalation price. Had there been any provision to

submit 'No Claim Certificate' after submitting the

final bill and before passing the final bill, then the

matter would have been different and in that event,

the real fact would come to light in submitting the

final bill after completion of the work. Having regard

to Clause-26, in order to get the bill for the work,

the   Contractor   re-submitted   final   bill.    In   this

background, if the matter is viewed, in view of

submission of 'No Claim Certificate', it cannot be

said that, 1st Defendant has no right to initiate

arbitral proceedings for the revised contract value

under different heads as claimed in Claim Petition.

In that view, it can be fairly said that, 1 st

Defendant's case, certainly, comes under Clause-

(iii) of Para 52 of the judgment in National

Insurance Co. Ltd., case. When such being the

case, there is no reason to contend that 1 st
                                                AS.100/2013
                            31

Defendant has no right to invoke the arbitration

clause     in   view   of   submission   of   'No   Claim

Certificate'.


29)      For the foregoing discussion, it is, thus, clear

that, award passed by learned Arbitrator is based

on the reasons and materials placed before him.

There is no perversity or illegality in the award.

Award can be set aside only on the grounds

mentioned in Section 34 of the Arbitration and

Conciliation Act, 1996. No such grounds are made

out by Plaintiff as enumerated in Section 34 of the

Arbitration and Conciliation Act, 1996, much-less,

the grounds mentioned in plaint. There is no reason

to interfere with the reasoned award. In that view of

the matter, it can be fairly said that, Plaintiff fails in

its suit; accordingly, I answer the above point in the

negative and proceed to pass the following:
                                                    AS.100/2013
                             32

                        ORDER

(1) Suit filed by Plaintiff under Section 34 of Arbitration and Conciliation Act, 1996, for setting aside the award dated 17.09.2013 passed by sole Arbitrator/Defendant No.2; is hereby dismissed.

(2) No order as to costs.

[Dictated to the Judgment Writer directly on computer, typed matter corrected and then pronounced by me in open Court, on this the 15th day of October, 2020.] [RAMA NAIK] VI ADDL.CITY CIVIL & SESSIONS JDUGE BENGALURU CITY