Showing contexts for: pacl ltd in M/S Seighteen Electricals vs M/S Pacl Ltd on 3 July, 2015Matching Fragments
If the Engineer-in-Charge fails to give his instructions or decision in writing within the aforesaid period or if the contractor is dissatisfied with the instructions or decision of the Engineer-in-Charge, the contractor may, within 15 days of the receipt of the Engineer-in-Charge decision, appeal to the Director who shall afford an opportunity to the contractor to be heard, if the latter so desires, and to offer evidence in support of his appeal. The Director shall give his Decision within 30 days of receipt of contractor's appeal. If the contractor is dissatisfied with his decision, the contractor shall within a period of 30 days from receipt of the decision, give notice to Director -PACL LIMITED for appointment of arbitrator failing which the said decision shall be final binding and conclusive and not referable to adjudication by the arbitrator.
(ii) Except where the decision has become final, binding and conclusive in terms of Sub para (i) above, disputes or difference shall be referred for adjudication through arbitration by a sole arbitrator appointed by the Director-PACL LIMITED. If the arbitrator so appointed is unable or unwilling to act or resigns his appointment or vacates his office due to any reason whatsoever, another sole arbitrator shall be appointed in the manner aforesaid. Such person shall be entitled to proceed with the reference from the stage at which it was left by his predecessor.
ARB-22-2015 - 3 -
It is a term of this contract that the party invoking arbitration shall give a list of disputes with amounts claimed in respect of each such dispute along with the notice for appointment of arbitrator and giving reference to the rejection by the Director-PACL LIMITED of the appeal.
It is also a term of this contract that no person, other than a person appointed by Director-PACL LIMITED, as aforesaid, should act as arbitrator and if for any reason that is not possible, the matter shall not be referred to arbitration at all.
It is also a term of this contract that if the contractor does not make an demand for appointment of arbitrator in respect of any claims in writing as aforesaid within 120 days of receiving the intimation from the Engineer-in-Charge that the final bill is ready for payment, the claim of the contractor shall be deemed to have been waived and absolutely barred and the PACL LIMITED shall be discharged and released of all liabilities under the contract in respect of these claims. The arbitration shall be conducted in accordance with the provisions of the Arbitration and Conciliation Act, 1996 (26 of 1996) or any statutory modifications or re-enactment thereof and the rules made there under and for the time being in force shall apply to the arbitration proceeding under this clause.