a. Transmission charges which may consist of a fixed charge, demand charge and an energy charge or a combination of these;
b. Connectivity charge, which shall be levied to meet the cost of connecting the customer to the licensee's transmission system;
c. Parallel operation charge shall be levied for Captive Power Plant if the plant is connected with the grid.
(2) Transmission charges shall be calculated on a monthly basis.