Showing contexts for: PPPAC in Mihan India Ltd. vs Gmr Airports Ltd. on 9 May, 2022Matching Fragments
However, in the instant case, it is not clear as to why AAI did not seek prior approval of the Cabinet before initiating any bidding process for MIHAN Project.
(b) Since the Nagpur airport is proposed to be developed through PPP, it may be clarified as to whether all the guidelines issued by Department of Economic Affairs and PPPAC (Public Private Partnership Appraisal Committee) in this regard have been followed.
(c) What was the basis for increasing revenue share quoted by the highest bidder from 5.76% to 14.49% and basis of the negotiations held between MIL and GMR?
It may be clarified whether the Model documents issued by the erstwhile Planning Commission (standard document adopted by PPPAC) have been adopted in the tendering process of Nagpur airport. If not, the deviating statement may be furnished.
(ii) Whether there was provision in the Transaction document for negotiation in the bidding parameter? What were the terms of negotiation in the Revenue share from 5.14% to 14.49%? Whether other bidders also given the option of negotiating the revenue share?