Madhya Pradesh High Court
Kerala Industrial Infrastructure ... vs M/S Zoom Developers (Pvt.) Ltd. on 8 January, 2024
Author: Sushrut Arvind Dharmadhikari
Bench: Sushrut Arvind Dharmadhikari
1
IN THE HIGH COURT OF MADHYA PRADESH
AT INDORE
COMA No. 4 of 2019
(KERALA INDUSTRIAL INFRASTRUCTURE DEVELOPMENT CORPORATION (KINFRA) THROUGH K.A.
SANTHOSH KUMAR Vs M/S ZOOM DEVELOPERS (PVT.) LTD. AND OTHERS)
Dated : 08-01-2024
Shri K. Gopalakrishna Kurup, learned senior counsel with Shri Sumeet
Samvatsar, learned counsel for the petitioner.
Shri H.Y. Mehta, learned counsel for the respondent No.1
Shri Vivek Patwa, learned counsel for the respondent No.2. Shri Himanshu Joshi, learned Deputy Solicitor General for the respondent No.3.
Heard on IA No.1311/2023, an application for urgent hearing. On due consideration, the same is hereby allowed and disposed off. Since interim order has already granted, therefore, IA No.5453/2019, an application for stay stands closed.
This appeal is admitted for hearing.
List this case for final hearing in the week commencing 29/01/2024 in the Final Hearing List.
I.R. to continue, till next date of hearing.
(S. A. DHARMADHIKARI) (DEVNARAYAN MISHRA)
JUDGE JUDGE
Aiyer
Signature Not Verified
Signed by: JAGADISHAN
AIYER
Signing time: 09-01-2024
10:29:25