Showing contexts for: Docket explosion in M.S.J. Construction (P) Ltd. vs Delhi Development Authority And Anr. on 8 September, 2006Matching Fragments
43. Award dated 27.1.1992 published by Shri S. Nagarajan, the sole arbitrator is accordingly set aside.
44. Award shows that the learned arbitrator has since relocated in Madras. Docket explosion in this Court kept the petition on hold for 14 years. Parties would have to incur huge expenses in appearing before the arbitrator in the state of Tamil Nadu and if he is required to come to Delhi, his traveling expenses, boarding and lodging expenses would have to be paid by parties.
45. I, therefore, do not remit the award to Shri S. Nagarajan for reconsideration.