4. Was there any bad workmanship on the part of the claimant? If yes, to what extent and whether the same justified enormous deductions as made by the respondent?
5. Whether the claimant is entitled for the amount towards the unpaid bill amounts towards work done but not included in the final bill, and amounts towards loss of profit for de-scoping of certain works?

9. Dealing with issue Nos. 5 and 8 which relate to unpaid bills to the tune of Rs.1,60,44,711/-, the learned Arbitrator concluded that, since the claimant had accepted the various deductions made during the course of the contract without demur, the claimant was entitled only to payment for the work done and not for unpaid bills or loss of profit on de-scoping of the work.