III. An amount of Rs.1,24,58,119.45 (Rupees One Crore Twenty Four Lakhs Fifty Eight Thousand One Hundred and Nineteen only) to be paid to the claimant by the respondent, on account of non payment, by the respondent of the price of gases consumed by it during the period December, 2010 to August, 2011; which includes interest @ 1.5% per annum, with monthly rests from the date of default till 30.6.2012.
IV. A direction in the nature of perpetual, permanent mandatory injunction to the respondent to replace and replenish the 60 PDCs issued under Article 14.1 of the contract, with PDCs, in favour of the claimant, for an amount of Rs.39 lakhs, in accordance with Article 14.1 of the Amendment, such that the claimant should have in its possession 60 PDCs of Rs.39 lakhs each, in its favour, at all times, upto the 10th year of the agreement.
V. A direction in the nature of a perpetual, permanent mandatory injunction, to the respondent, to provide to the claimant a separate gate with free entry and exit and easementary rights for consent and unhindered access into the ASU Production Facilities, which access is approachable through main roads.
VI. A direction in the nature of a perpetual, permanent mandatory injunction, to the respondent, to provide to the claimant uninterrupted power @ 3 MW per hour (operating load) at the production facilities switchboard, strictly in accordance with Article 7.3.2 of the contract; and such additional power as contemplated in Article 7.3.2 at the rates and in terms of the contract and the Amendment.
VII. A direction in the nature of a perpetual, permanent mandatory injunction, to the respondent, to provide to the claimant, treated makeup water (about 5 M3/hour), firewater and drinking water of required quantity, quality, pressure as specifically required in Article 7.3.5 of the contract and at the price prescribed in Article 7.3.5 of the contract.
VIII. An amount of Rs.12,90,13,808/- (Rupees Twelve Crores Ninety Lakhs Thirteen Thousand Eight Hundred and Eight only) to be paid to the claimant by the respondent, on account of losses caused to the claimant, on account of the closure of its merchant market operations under Article 29 of the contract.
IX. Pendentelite interest @ 1.5 per month, with monthly rests, on the amounts of the claims Nos.I, II, III and VIII, till the date of the award.
X. Future interest @ 1.5 per month, with monthly rests, on the amounts of the claim Nos.I, II, III and VIII, from the date of the award till the date of realisation and recovery thereof.
XI. Perpetual permanent mandatory injunction directing the respondent to pay to the claimant the monthly MTOP amounts as provided in Article 9 of the contract, from 1.7.2012 till the date of the award.