terms of clause 23.1.1(e), (q) and
(r) of the EPC contract agreement, highlighting several defaults on the
3
part of the petitioner. The petitioner ... intention to terminate the work, as per Clause-
23.1.2 of the EPC contract agreement, was communicated to the
petitioner alleging that despite several correspondences
Construction Contract and (iv) Onshore Supply Contract. These shall
be hereafter collectively called "the contracts". In addition to these
contracts, Shenzhen ... bank guarantee again amounting to 10% of
the EPC Contracts.
3. The said EPC Contracts contained an arbitration clause. Shenzhen
started the project work
Supply Contract
iii. Onshore Services and Construction
Contract
iv. Onshore Supply Contract
These contracts are hereinafter collectively
referred to as the ‘EPC Contracts’.
2.2 Each ... contracts
did not contain any provision on payment of
Interest.
2.6 Disputes arose between the parties, which
resulted in the termination of the EPC Contracts
contracts
which were perused by the lower authorities indicated and as recorded in the
order-in-original that these contracts were EPC contracts. The period ... turnkey/EPC contract is taxable prior to 1-6-2007 as
well. On and since 1-6-2007, turnkey/EPC contracts must be classified
irrigation, domestic consumption or sewerage disposal even where executed
as turnkey/EPC contracts; (i) would be classifiable under clause (b),
Explanation (ii) of Section ... turnkey/EPC contract is
taxable prior to 1-6-2007 as well. On and since 1-6-2007, turnkey/EPC
contracts must be classified
Mashkour appointing the Respondent as its EPC contractor for the said
project in terms of EPC contract dated 5th July, 2017, the earlier Tripartite
Agreement ... Respondent-Corporate Debtor has
replaced Appellant as EPC Contractor for the project in terms of EPC
contract dated 5th July, 2017 and thereby the Tripartite
MAPEX to
show whether under the terms of the sub-contract/EPC contract, the EPC
Contractor was entitled to raise a claim of prolongation cost ... Principal Contract,
when the sub-contract did not have such a clause. It was held that though
the sub-contract was a back-to-back
MAPEX to
show whether under the terms of the sub-contract/EPC contract, the EPC
Contractor was entitled to raise a claim of prolongation cost ... Principal Contract,
when the sub-contract did not have such a clause. It was held that though
the sub-contract was a back-to-back
above said decision, PLL (Petronet LNG Ltd.)
entered into an EPC contract with M/s. Ishikawajma-Harima Heavy Industries
Ltd., to develop, design, engineer ... potential
expansion to 10 MMTPA capacity at the specified temperatures. The EPC contract
7
Appeal No.ST/53521/2016-CU(DB)
also envisaged providing marine
developed in view of CWG in 2010. As per
the EPC contract, Block-I & Block-II were to be commissioned
within 28 months ... case, the Central Commission has also concluded that
the award of EPC Contract to BHEL was prudent and has also
held that the delay