work adverted to in the punch list;
(b). secondly, whether the delay in completion of the punch list items was
attributable to the respondent ... detail out as to what
are considered as : punch list items. The punch list items are, accordingly,
culled out below. I may only note that
Joint
Commission has allowed Rs. 3.54 crores as punch list
items. In case of items already covered the cost agreed
in PPA, allowing such expenditure ... after COD of the Project a number of
items called 'punch list items' which do not have a
direct bearing
have
appended thereto a list of outstanding
items signed jointly by the Independent
Engineer and the Concessionaire (the
"Punch List"); provided that ... incomplete and/or deficient have been
specified in the Punch List appended
hereto, and the Concessionaire has agreed
and accepted that it shall complete
Linde Ag, Linde Engineering Division ... vs Deputy Director Of Income Tax on 23 April, 2014
order by Railway
Authority and the same been included in the Punch
List items annexed along with the Provisional
Completion Certificate (Annexure ... Head Quarters and the same has also been
included in the Punch List items annexed along with
the Provisional Completion Certificate (Annexure
such cost and profit for the same was based on the punch list
given by the client,that it was necessary to make provision ... supplies of replacement
spares,site related costs,cost of completion of punch list work,cost of modification for
uncompleted projects has to be considered while