directed the petitioner to clear the objections or to provide an alternate route.
3. Thereafter, on 28.12.2011, the petitioner made an appeal to the concerned ... directed the petitioner to solve the issue or to provide an alternate route.
5. The petitioner has further submitted that the lands situated in Survey
routes with merits and demerits of both the routes. The Electricity Board took a definite stand that considering the technical aspects, the original route which ... second alternate route instead of the original route which was found to be more feasible by the Board as the route was along the existing
also directed to
ascertain as to whether there is any alternative route or road for the
operation of heavy vehicles.
List this matter for further ... completed by January, 2020.
8. It is submitted that the alternate route for the plying
heavy vehicles by passing the Vallakkadavu Bridge was from
Kallumoodu
court, appellants/writ petitioners seemed
to have submitted that the said alternative route suggested by respondent
No.4 is not feasible as the proposed route ... third parties or puramboke land, if any, available near the proposed
alternative route and thereafter, submit a report along with the sketch
regarding the location
Electricity Act, 1910 was not obtained and
(b) that there is alternative route available.
While dealing with these contentions, the learned Judge thought that three ... result in the transmission towers being
erected on alternate lands that may not provide the shortest route. The
consequence of this option is that
pipe line, through the residential area, despite an alternate route, without affecting public, through the main road of Madhavaram high road, and further through
arterial road, where movement of vehicles is heavy, and no other alternate route is available. The uninterrupted flow of vehicles and the constant
development trends. Road near the park was being utilised as an
alternative route to enter Anna Nagar East and Kilpauk. It was
observed that this
reported that
C3C3 road can be used as an alternative route to reach other parts of
Kozhikode city and the road starts from Ashokapuram junction
existing highway and two other alternative
routes. The three routes were compared and the second
alternative was found to be the most suitable ... other
properties will not be affected. The Ext.P4 alternate route is
prepared by just putting dotted lines in the approved alignment
plan