routes. After due survey, they narrowed in on two possible routes and suggested the same with the merits and demerits of both these routes ... second alternate route instead of the original route which was found to be more feasible by the Board as the route was along the existing
under which an otter of alternative routes could be made to those operators whose permits had been cancelled in implementation of a scheme of nationalisation ... fundamental rights of other operators already plying their buses on this alternative route and hence it offends Article 19(1)(g) of the Constitution, interpreted
Divisional Officer and the Village Administrative Officer, including the proposal
for alternative route suggested by some of the land owners, had passed the
impugned order ... further submission of the learned counsel that the suggestion
of alternative route has also been taken into consideration and the report has
specifically mentioned that
procession negatived the alternative route suggested by the petitioner saying that the new route is longer than the old route and covered a distance ... showing the route in which procession was taken hitherto; (2) showing the route suggested by the petitioner; (3) showing the route in which the procession
submit a report with
regard to the feasibility of an alternative route.
4. It is the further submission of the learned senior counsel that ... answering respondent/
Electricity board for the proposal of the alternative route and it was
requested to grant permission to carry on with the project
submit a report with
regard to the feasibility of an alternative route.
4. It is the further submission of the learned senior counsel that ... answering respondent/
Electricity board for the proposal of the alternative route and it was
requested to grant permission to carry on with the project
route of high tension
tower line shall be changed to an alternate route which will cause lesser
damage to the petitioner property.
3.During ... enquiry the second respondent proposed an alternate
route . The petitioner on verification found that the alternate route may not
disturb in higher magnitude as before
Resultantly, they have issued an order on
29.12.2017, whereby the following alternative route towards the return
journey had been permitted.
“Permitted Route: C.B. Hospital ... difficulty experienced by the petitioner
that by taking this alternative route, which is according to the petitioner
is a circuitous one. The petitioner, while return
work, a detailed route survey/study has been conducted. Based on the Survey only, the route alignment was drawn. If an alternate route, as suggested ... saved by the alternate line as proposed by the petitioners is 772 mts. When 772 mts. is saved by alternate route, the respondent-Department
directed the petitioner to clear the objections or to provide an alternate route.
3. Thereafter, on 28.12.2011, the petitioner made an appeal to the concerned ... directed the petitioner to solve the issue or to provide an alternate route.
5. The petitioner has further submitted that the lands situated in Survey