routes. After due survey, they narrowed in on two possible routes and suggested the same with the merits and demerits of both these routes ... second alternate route instead of the original route which was found to be more feasible by the Board as the route was along the existing
route suggested by the 1st
Respondent by holding that the route suggested by the K.S.E.B
was the most feasible route ... verifying whether the routes suggested by the
W.A.No.1650/2015 & conn. cases 10
appellants were feasible routes alternative to the one
suggested
aside on a finding that there is
no consideration of the alternate routes suggested by the parties and
WANos.1573/2013 & 1695/2013 ... both the routes. He has recorded therein
that the people affected along the approved route is more when
compared with the alternate route suggested from
respondent. The case of the petitioners is
that Ext.P4 alternate route suggested by them is much more
economical and feasible than the route ... respondent and that if the line is drawn through the alternate
route proposed by the petitioners, it will mostly pass through
Divisional Officer and the Village Administrative Officer, including the proposal
for alternative route suggested by some of the land owners, had passed the
impugned order ... further submission of the learned counsel that the suggestion
of alternative route has also been taken into consideration and the report has
specifically mentioned that
present proposed route, was not
disturbed in any of the three routes including the proposed route and the
alternate routes. Thus, learned Advocate has tried ... that apart from the
route in question which is marked as the proposed route, there are two
other routes being alternate route
present proposed route, was not
disturbed in any of the three routes including the proposed route and the
alternate routes. Thus, learned Advocate has tried ... that apart from the
route in question which is marked as the proposed route, there are two
other routes being alternate route
BEFORE THE 1ST RESPONDENT ALONG WITH THE DETAILED SKETCH
OF THE ALTERNATIVE ROUTE PROPOSED BY THE PETITIONER BEFORE THE 1ST
RESPONDENT.
EXT.P12:COPY ... common judgment. It was observed that, the objections
raised and the alternate routes suggested by the petitioners
were not considered and the District Magistrate
objections before the
District Collector and also suggested an alternate route for the transmission
line to pass, as evidenced by Ext.P2 produced along ... line, and also failed to consider the feasibility of the alternate
route suggested by the petitioner, which, according to the petitioner, would
have minimised
submit a report with
regard to the feasibility of an alternative route.
4. It is the further submission of the learned senior counsel that ... answering respondent/
Electricity board for the proposal of the alternative route and it was
requested to grant permission to carry on with the project