depletion
of sum insured. That the policy so obtained was All Risk Policy with SRCC & War and basis
RNM CC422014 Page ... policy which revealed that claim is not admissible under policy
and therefore intimated vide letter dated 3/2/2014 mentioning therein that policy excludes
mould
depletion of sum insured. That the policy so obtained was All Risk
Policy with SRCC & War and basis of valuation ... policy which revealed that claim is not admissible under policy
and therefore intimated vide letter dated 3/2/2014 mentioning therein that policy excludes
mould
depletion of sum insured. That the policy so obtained was All Risk
Policy with SRCC & War and basis of valuation ... policy which revealed that claim is not admissible under policy
and therefore intimated vide letter dated 3/2/2014 mentioning therein that policy excludes
Insurance Company for issuance of a Contractor's All Risk policy. The sum insured was Rs. 32,71,86,982. The premium paid there ... Contractor's All Risk provides 'all risk' cover unless the hazard is specifically excluded. It covers the risk of fire, lightning, explosion
complainant which were duly covered under the policy and as per policy of the risk coverage, the risk was covered to the extent ... complainant which were duly covered under the policy and as per policy of the risk coverage, the risk was covered to the extent
fold of the word 'storm' occurring in the risk Policy.
25. Mr. Malhotra made an ultimate attempt to contend that the Policy does ... speed of 80 kms/hr. would reasonably stand included under the policy risk in the light of the other definitions that have been referred
Serilingapally Mandal, Ranga
Reddy District and also obtained Contractor‟s All Risks Policy
No.433702/44/2013/1293 for the period from ... said policy. It is the further contention
of the complainant that the said policy itself, says that it is a
Contractors Risks Policy for developer
vide Policy bearing No.235402/11/2021/276, which was
valid w.e.f. 10.02.2021 to 09.02.2022. Under the said Policy, the risk of
entire ... vide Policy bearing No.235402/
11/2021/278, which was valid w.e.f. 10.02.2021 to 09.02.2022. Under
the said Policy, the risk of entire
Political Risks under the heading "Risks Insured and Exclusions" of your Shipments (Comprehensive Risks) Policy, which reads as follows "....Operations ... Bander Abbas, Iran. The shipment was covered under a Shipments Comprehensive Risk Policy of the Opposite Party No.1 for which a premium was paid
policy and paid a premium of
Rs.44,58,801/- towards the said policy. The policy was renewed on
31.05.2008 and the risk period commenced ... crores, with the opposite party under 'Industrial
All Risk Policy'. Whileso, the unfortunate fire accident took place on
11.12.2008. Hence, a claim