Certificate (CC) was below the threshold limit
of 20000 sq. m., the Answering Respondent did not apply for grant of
prior EC. Thereafter ... April, 2013, Answering Respondent obtained
a Commencement Certificate (CC) for construction
State of Rajasthan by setting up of industrial area.
2
The answering Respondent further submits that it allocates land for the
establishment of industry ... production. In this regard, it is pertinent to state that the answering
respondent has allotted the land subject to the said condition and has
further
Mr. Tanaji Balasaheb Gambhire vs Union Of India on 22 February, 2023
(Pune Bench)
BEFORE
operating and
maintaining Organic Waste Composting Machine for the project.
Hence, the answering Respondent is using alternate technology
for disposal of solid waste. Photograph ... have been using treated water from STP for construction
purpose. Thereafter, the answering Respondent installed a STP
at the Project premises. It is submitted that
total area of Lagoon 1 and 2 is 210 Acres. The
Answering Respondent undertakes to complete the
work of fencing as directed or recommended ... report by 8 months from the date of the
present affidavit. The Answering Respondent
further undertakes that the work of fencing shall
be done
same is
Page 13 of 44
also being addressed holistically by the answering
Respondent and has proposed several new Sewage
Treatment Plants to ensure that ... rivers are not polluted.
The answering Respondent has prepared a detailed project
for rejuvenation of the river Mula, Mutha and Mula-Mutha
flowing through
entrusted to other Authority and therefore it has denied liability to
answer any of the statement in the application. It seeks to excuse
itself from ... private undertaking with foreign
collaboration and is thus answerable for its operation till 1971 and
also answerable for the adverse affects caused to the environment
conclusion in respect of the legality of the
structures in question. The answering Respondent is taking the necessary
actions available to it to prevent ... Lucky Realtch Pvt. Ltd. reply affidavit
dated 17.11.2022 has been filed. The Answering Respondent has
undertaken activity only after securing all permissions from all competent
empowered to collect taxes of Residential Townships and
Companies. The Answering Respondent vide letter dated 31.12.2018
requested the Respondent No. 7 to allot land ... vide
Page 5 of 11
letter dated 14.03.2022, the MIDC informed the Answering Respondent
that the Respondent No. 7 will implement
level structures, prior permission for dewatering is a
regulatory prerequisite. Accordingly, the answering Respondent
has applied for permission for dewatering to the District Advisory
Committee ... Ground Water of the Govt. of NCT Delhi on 06.08.2020.
The answering Respondent undertakes to comply with the decision
and/or conditions imposed