Sushil Ansal vs State Thr.Cbi on 5 March, 2014

installation of the DVB transformer, various structural and fire safety deviations in the building in violation of various Rules and not facilitating the escape ... number of 14 witnesses were examined to prove the structural deviations in the building upon an inspection conducted after the fire incident. An equally large
Supreme Court of India Cites 90 - Cited by 182 - T S Thakur - Full Document

Sushil Ansal vs State Thr.Cbi on 5 March, 2014

installation of the DVB transformer, various structural and fire safety deviations in the building in violation of various Rules and not facilitating the escape ... number of 14 witnesses were examined to prove the structural deviations in the building upon an inspection conducted after the fire incident. An equally large
Supreme Court - Daily Orders Cites 91 - Cited by 0 - T S Thakur - Full Document

Section 315 in The Bihar Municipal Act, 2007 [Entire Act]

Bihar Municipal Act, 2007 315. Construction of building in contravention of building by-law. - Any building or structure of permanent nature which has been constructed ... construction has commenced in contravention or breach or deviation of building by-law shall be liable to be demolished, notwithstanding that it may have been
State of Bihar - Section Cites 0 - Cited by 29

Section 316 in The Bihar Municipal Act, 2007 [Entire Act]

building plan by registered Architect, the Chief Municipal Officer may inquire and verify and satisfy himself that the building construction plan confirms to building ... been approved by the registered Architect in contravention, breach or deviation of building bye-law or other parameters under this Act, he shall immediately stop
State of Bihar - Section Cites 0 - Cited by 13

K.Srinivasa Rao vs The Chairman on 17 December, 2014

apply for service connection in respect of the special building/multi storied building. 9. He further submits that the Division Bench by an order dated ... petitioner had obtained building plan from the 5th respondent dated 31.12.2012. The petitioner has constructed his building with deviation and violation. Therefore, the 5th respondent
Madras High Court Cites 1 - Cited by 0 - C S Karnan - Full Document

K.Srinivasa Rao vs The Chairman on 17 December, 2014

constructed a building consisting of Stilt+4 floors, with eight dwelling units of residential buildings. The building has been constructed after obtaining building permission from ... petitioner had obtained building plan from the 5th respondent dated 31.12.2012. The petitioner has constructed his building with deviation and violation. Therefore, the 5th respondent
Madras High Court Cites 1 - Cited by 0 - C S Karnan - Full Document

K.Srinivasa Rao vs The Chairman on 17 December, 2014

apply for service connection in respect of the special building/multi storied building. 9. He further submits that the Division Bench by an order dated ... petitioner had obtained building plan from the 5th respondent dated 31.12.2012. The petitioner has constructed his building with deviation and violation. Therefore, the 5th respondent
Madras High Court Cites 1 - Cited by 0 - C S Karnan - Full Document