work relating
to construction of building undertake or any
alteration, addition or modification of an
existing building unless, the building plan is
approved ... year or both.
Section 315 . Construction of building
in contravention of building bye-law:-Any
building or structure of permanent nature
which has been constructed
some deviation in the construction
which was within the permissible limit.
3. Since the deviation in the construction of the building
was within the permissible ... regularized by sanctioning the modified
building plan. The modified building plan means any
modification made to the original building plan. Hence, the
construction
easily be ascertained whether there have
been unauthorised deviations. The building is still standing. These
are matters which can easily be verified by the Court ... Union of India & Ors. 13 noticed the deviations in the building plans of
the theater. The High Court considered a similar argument
accommodation to the petitioners and thereafter, rectifying the
deviations / demolish the unauthorised portion of the building.
7.This court has considered the submissions made ... every person in occupation of the
building or portion thereof to which the notice relates shall vacate the
building or portion as directed
accommodation to the petitioners and thereafter, rectifying the
deviations / demolish the unauthorised portion of the building.
7.This court has considered the submissions made ... every person in occupation of the
building or portion thereof to which the notice relates shall vacate the
building or portion as directed
submitted by the appellants/writ petitioners
herein.
29. The deviation in the sanctioned G+2 building by constructing
additional two floors is not only major ... CODE for the G+2 building.
But, the appellants/writ petitioners had constructed building thereby
deviating from the sanctioned plan as sanctioned
permit regularization of
deviations is not with respect to all kinds of deviations and the set
back, but only the deviations to the extent ... this Court in ACES, Hyderabad (supra),
with respect to the building deviations issued directions in para-36
which is reproduced as under:
"36. Having
Town and Country Planning Act and he
has also constructed the building, deviating from the original planning
permission, by making additional construction, he would
petitioner had sought for only time to remove the deviated
portions of the building so that he could restore the building back ... when there are deviations committed by the owner of
the building, indicating the deviations to be rectified, a lock and seal
notice and the discontinuation
found
that building on the schedule property was being
constructed contrary to the Building plan and that
there are several deviations. The petitioner was called ... doubt, in the Provisional Order, the
second respondent has given deviation of building
which are disputed by the petitioner who had called
upon the respondent