Coastal Regulation
Zone (CRZ) Notification, 2011, notified vide S.O. No.19(E)
dated 6th January, 2011. That the CRZ Notification, 2011
provides for regulation ... that the project proponent had
approached the Ministry of CRZ clearance under CRZ
Notification, 2011 and the matter was taken up in several
meetings
Coastal Regulation Zone (CRZ)
Notification, 2011 was notified on 6th January, 2011 in
supersession of the CRZ Notification, 1991 for regulation of
developmental activities along ... Coastal Regulation Zone (CRZ) Notification,
2011 was notified on 6th January, 2011 in supersession of the CRZ
Notification, 1991 for regulation of developmental activities along
lake falls
8
under CRZ IV; (ii) that Nediyathuruthu island falls under CRZ
III; (iii) that Nediyathuruthu island has CRZ landward of HTL
upto ... that they are clearly covered by CRZ I and not under CRZ III
or CRZ IV.
v. In paragraph 24 this Court also endorsed
CRZ-III area and without
decline for environment clearance under EIA Notification, 2006 and the
CRZ clearance under CRZ Notification, 2011 from the Government ... classified as CRZ I-B. The backup area where landfilling has
occurred is classified as the NDZ in CRZ-III. Under CRZ 2011, the
construction
which are set to be in violation of Coastal
Regulation Zone (CRZ) Regulation 2011 filed the appeal on the
grounds that the impugned order ... suggest that there is no
height restriction in CRZ Notification. The CRZ Notification 2011
envisages 9 meters height and 33% FAR for structures
granted is permitted activity under the CRZ-II Zone. Para 3 of
the CRZ Notification, 2011 deals with the prohibited activities
within the CRZ area ... project area falls in CRZ-II
area as per the provisions of the CRZ Notification, 2011.
16. As per order in Original Application
deep
sea without obtaining necessary CRZ clearance or no objection from
the authority as required under the CRZ Notification, 2011.
3) Major portion of fund ... effluents into the deep sea requires CRZ clearance
following due procedure as laid down in CRZ Notification,
2011. If pipe line for discharge of treated
various
cooperative societies. Ponnani Port is coming under CRZ-I, CRZ-II and
CRZ-IV which is in Ponnani Municipality. The Kerala Coastal Zone
Management ... mining
carried out in CRZ without CRZ clearance is in violation of the provisions of
CRZ Notification, 1991 and 2011.
17. The fifth respondent
transports between the
unit and seashore.
Status of CRZ Clearance under CRZ Notification
2011.
The unit's location ... under CRZ III as per the
approved Map No. 4. However, the unit has not obtained
any CRZ Clearance under CRZ Notification 2011.
Note: CRZ
2018 approving the Coastal Zone
management plans under the CRZ Notification, 2011 for the state of
Tamil Nadu, quash the same and direct ... Tamil
Nadu.
f)Generation of Local Level CRZ Maps at
1:5000 scale as per CRZ Notification, 2011
following standard national color codes,
symbols used