provisions of the Karnataka Municipalities Act , they
sought defendant's permission for demolition by
submitting a sketch map of the building referred to
above ... after the verification of the spot and accorded
:6:
permission for the demolition. In pursuance thereof
the plaintiffs demolished the entire old building.
Thereafter
that the Assistant Commissioner,
Hubballi Dharwad Municipal Corporation (HDMC) granted
permission for the demolition with terms and conditions on
23.09.2024. The petitioners allege that respondents ... report of the engineers concerned, the Assistant Commissioner
accorded the permission for demolition of their properties on
18.02.2025. The permission accorded by the Assistant
Commissioner
that the Assistant Commissioner,
Hubballi Dharwad Municipal Corporation (HDMC) granted
permission for the demolition with terms and conditions on
23.09.2024. The petitioners allege that respondents ... report of the engineers concerned, the Assistant Commissioner
accorded the permission for demolition of their properties on
18.02.2025. The permission accorded by the Assistant
Commissioner
before any Tribunal or other authority for cancellation of such permission or demolition of buildings which were constructed after obtaining the permission from the Corporation ... Commissioner, Bangalore City Corporation for having not carried out demolition of the extra floors. Demolition of extra floors without affecting the security and safety
Survodaya Mills Workers Union vs State Of Karnataka And Others on 31 January, 1994
Equivalent
purpose but not for commercial purposes since she has not obtained permission for demolition and reconstruction and the trial court has not properly considered ... possible for her to apply for conversion, demolition and reconstruction because as soon as she applies for permission, the authorities concerned would inspect the premises
direct
the 7 th respondent not to resort to demolition of the
demolition of the immovable properties, hence, it will be
too far fetched ... took place and he has not sought for any permission
from the Tahsildar for demolition of the properties and further
admits that, the Tahsildar
father had constructed a building and was in occupation of _
it. Permission for demolition of the buitding was s obtained :
by the 2" respondent
Section
149 of IPC the police subsequently obtained permission of
the Magistrate for investigating the matter for the offence
4
punishable under Section ... petitioner submits he also filed writ petition
before for granting the permission to demolition the
building which is pending. The respondent also filed
complaint. Absolutely
committee of temple had attempted to demolish the
temple without obtaining appropriate permission and therefore,
the plaintiffs requested the Trial Court to direct the parties ... petitioners to approach the competent authority or the Court to
obtain permission for demolition or reconstruction of the
temple. If the petitioners obtain the required