learned Counsel for the opposite party.
21. As far as the external electrification charges are concerned, clause 9 (iv) of the allotment letter duly signed ... charges. Even the price list also does not stipulate payment of external electrification cost as one of the extra charges though several extra charges were
Harshit Kumar Goel vs Rural Electrification Corporation Of ... on 5 May, 2014
IN THE STATE COMMISSION :DELHI
(Constituted under Section 9 of
the Consumer Protection ... Gautam Budh Nagar
Uttar Pradesh
.........APPELLANT
VS
1.
2.
Rural Electrification Corporation
of India,
Core-4, Scope Complex,
7, Lodhi Road,
New Delhi
Rural Electrification Of Corp Ltd vs Tanmay Gupta on 27 April, 2022
Daily Order
STATE CONSUMER DISPUTES REDRESSAL COMMISSION, CHENNAI
BEFORE Hon'ble THIRU ... South)
DATED THIS THE 27TH DAY OF APRIL 2022
M/s Rural Electrification Corporation Ltd,
Regd. Office : Core 4,
Scope Complex, 7, Lodi Road
raised by the Opposite Party for
External Electrification Charges is arbitrary. To resolve this
issue, we deem it appropriate to refer to the relevant provisions ... ALLOTTEE(S). Allottee(s) herein also agrees to pay the
proportionate External Electrification charges including
but not limited to lying of cables, security deposits
amount of Rs.4,47,500/-, which it had charged towards electrification & STP charges, since the said charges are not payable because ... agreement, the complainant agreed to pay the charges towards EDC, STP and Electrification, which were not hidden, as alleged by the complainant. It has further
refund the excess amounts under the heads Service Tax and
External Electrification Charges/EDC until opposite parties No.1
& 2 show, whether they ... Charges and Service Tax; ₹2,25,000/- plus
₹27,810/- for External Electrification Charges and service tax over it
and ₹26,400/- plus
charge any excess amounts
under the head of external electrification charges &
EDC over and above the legitimate charges
amounting ... external electrification charges,
C.C. No.429 of 2019 3
in view of the RTI appended by the complainant
herein above;
(viii) to refund with
demand of Rs.1,80,000/- towards other charges, which were electrification charges, water meter and connection charges, sewerage charges, IFMS and club Membership ... amount of Rs.3,28,445/- towards club membership fee, electrification charges, water connection charges, sewerage connection charges, IFMS charges, inflation charges, which were totally
towards EEDC, Rs. 2,83,715/- towards electrification and STP charges and of Rs. 1,90,700/- towards maintenance and other miscellaneous heads, as raised ... pressed for further payment under various heads like enhanced External Development charges, Electrification and STP Charges, Stamp Duty which were otherwise not part
outstanding dues after
execution of the sale deed and also demanding external
electrification charges amounting to Rs. 1,33,380/- and interest free
maintenance security ... fund @ Rs. 0.50 per sq. ft. per month. Complainant paid
the external electrification charges vide cheque No. 19757 dated
14.3.2011 and receipt No. 457740 dated